Standard Special Provision Update

November 15, 2013

2010 SSPs used with 2010 Standard Plans:

SSPNo / Effective Date / Description / Update
SN-410 / A11-15-13 / -- / Updated to the next fiscal year.
StdPln / A11-15-13 / Standard Plans List / Revised the Standard Plans List to coincide with the Revised Standard Plans for the 2010 Standard Plans Erratum No. 8.
RSS / A11-15-13 / -- / Sections 1-1.11 and 5-1.13C. Changed because statutory and regulatory changes have occurred requiring additional contractual activities of contractors with respect to DVBE substitutions.
Section 9-1.16D(2). Changed heading.
Section 13-1.01A. Minor revision to update the reference to the new permit order number.
Section 20-2.01C(2). Corrected trench depth in pars 7 and 8.
Section 20-2.01C(2). Deleted carriage return between pars 12 and 13.
Section 20-2.10B. Added swing joints to riser sprinkler assemblies and tree well sprinkler assemblies.
Section 28-2. Correct a typo.
Section 39-4.04A. Corrected typo.
Section 59-2.03C. Deletes section 59-2.03C(4)(b) of section 59-2.03C was erroneously added for State Specification PWB coating. It only applies to zinc coating.
Sections 72-2.02A and 72-2.3.02B. Minor revision to replace tables for rock material properties and hence restore notes for the tables.
Section 83-1.03. Corrected the pay limits of midwest guardrail system. This revision will eliminate the need for the current NSSP that covers this statement and will parallel technical content with the 2006 edition.
Section 86-2.05C. Corrected a mistranslation from the 2006 specifications.
8-1.04G / A11-15-13 / Potential Budget Impasse Start / Updated to the next FY.
14-11.05 / C11-15-13 / Naturally Occurring Asbestos / Canceled SSP. Specifications are no longer valid.
14-11.10 / C11-15-13 / Disposal of Electrical Equipment Requiring Special Handling / Canceled SSP. Specifications are no longer valid.
20-1.03C / A11-15-13 / -- / Revised instructions for clarification.
20-2.01C(2) / A11-15-13 / -- / Revised par 1 to clarify maximum width of turf to be removed.
30-4 / A11-15-13 / Full-Depth Reclamation-Cement / SSP 30-4. Correct a section reference in the Quality Control Requirements table.
40-5 / A11-15-13 / -- / Minor revisions to cross-references and the pay clauses.
59-7 / A11-15-13 / Acid Staining Concrete / Correct intro statement that incorrectly deleted the list in the 1st par.
73-3 / A11-15-13 / -- / Revised the sentence added to section 73-3.01C to require the submittal of preconstruction and post construction surveys signed and sealed by either a land surveyor registered in the State or civil engineer registered in the State.