XXX, 0000 IEEE P802.15-01/087r0

IEEE P802.15

Wireless Personal Area Networks

NOTE: To change <title> and other required fields, select FileèProperties and update the appropriate fields in the Summary tab. DO NOT replace field codes with text. After updates are entered, delete this paragraph and update all fields (ctl-A then F9) Note: dates will not be updated until document is saved. After fields are updated, delete this paragraph..

Project / IEEE P802.15 Working Group for Wireless Personal Area Networks (WPANs)
Title / TG3-Monterey-Wed-PHY-Sub-Meeting-Minutes
Date Submitted / [The date the document is contributed, in the format “21 May, 1999”]
Source / []
[Broadcom]
[address] / Voice: [ ]
Fax: [ ]
E-mail: [ ]
Re: / [If this is a proposed revision, cite the original document.]
[If this is a response to a Call for Contributions, cite the name and date of the Call for Contributions to which this document responds, as well as the relevant item number in the Call for Contributions.]
[Note: Contributions that are not responsive to this section of the template, and contributions which do not address the topic under which they are submitted, may be refused or consigned to the “General Contributions” area.]
Abstract / [Description of document contents.]
Purpose / [Description of what the author wants P802.15 to do with the information in the document.]
Notice / This document has been prepared to assist the IEEE P802.15. It is offered as a basis for discussion and is not binding on the contributing individual(s) or organization(s). The material in this document is subject to change in form and content after further study. The contributor(s) reserve(s) the right to add, amend or withdraw material contained herein.
Release / The contributor acknowledges and accepts that this contribution becomes the property of IEEE and may be made publicly available by P802.15.


802.15.3 Interim Meeting, Monterey 1/15-19

Username: P802.15

Password: Bluetooth (Case sensitive)

Wednesday, 1/18/2001, PHY Subcommittee meeting, Chaired by J. Gilb, Called to order 8:09AM

Approved PHY subcommittee conference call minutes.

Moved: Jeyhan

Second: John Barr

Unanimously approved.

Refer to 01/030r0 for definitions of Acronyms/Definitions for the PHY section of the 802.15.3 standard.

JB: How are we going to make sure everybody gets an update of the acronym list?

JG: It will be periodically distributed to WG members.

JG: 00000D01P802.15.3_Clause03.fm (definitions clause of the standards) resides on the private 3 section of the TG3 website

Refer to 01/030r0 for Header Format description.

Rick: Change PLME to PLCP

JK: Change 22 Mbps Preamble header to 11 Msymbol/s O-QPSK

JG: OK

JG: Scrambler? We need to determine if it is going to be self-synchronized or side-stream. How do we initialize it? It will be added to the issues list

Refer to 01/030r0 for description of Physical Observables

JG: How do you access the PHY SAP?

RR: It is not a physical interface but a logical interface. We should definitely include it in the spec.

Raju: Never describe it as a certain implementation but leave it logical

JG: Is it in Normative or Informative section?

JG: If PHY SAP implemented and exposed shall conform to a description in the normative section of the standard.

TG3 Draft Standard Organization (Refer to 00/407r1)

Al Heberling will tell Rick Alfvin to get the “data base for comment resolution” from Ian Gifford, we’ll enter our existing issues list in that data base.

For procedures for submission to the TG3 standard refer to document 01/030r0.

Draft clauses are in 01/059r0.

Individual contributions to the specification will be submitted with a TG3 document number and name of the clause and then it will be incorporated into the frame format by the editor.

AH: Where is the template for the frame format document?

JG: It will be given a document number and will be posted on the web

Pat Kinney to host ad-hoc interim meeting in Denver between Feb. 8-9. Details to go out shortly.

Hilton Head Agenda:

Sunday afternoon: available

Monday (4 hrs morning, 2 hrs afternoon, 3 hrs evening): Draft standard issue resolution presentation, clause review, summarize clause, comments taken later, clause resolution

Monday Afternoon, vote to accept baseline draft as published 1 week prior with notations

Tuesday, Wednesday, Thursday Morning, Clause work sessions

Adjourn at 10:09 AM