P12036 Notification Alert Team

Weekly Status Report MSD II Week 5

Submitted: April 13, 2012

Team Members
Michael Myers / Scott Tucker / Matt Gesner
/ /
Cory Duell / Joe Gaglione / Alvaro Berceruelo
/ /

Major Milestone Chart (Milestones from 11 week schedule):

Task / Expected Date / Responsible
Team
Member / Modified Completion Date / Comments
Finish Detailed Design Phase / 3/23/12 / Individual / 3/27/12
Finish PCB Layout / 3/23/12 / Cory / 3/27/12 / Sent Out
Finalize CAD Models/Sent Out Files / 3/30/12 / Mike / 4/06/12 / Completed
Order All Remaining Parts / 3/20/12 / Alvaro / 3/30/12
Update GUI/ Device Code / 3/30/12 / Joe / 4/13/12 / MSP430 is in
Send Out PCB / 3/21/12 / Cory/Matt / 3/27/12
Finalize Component Placement / 3/23/12 / Matt / 3/23/12
Update Test Plan / 3/20/12 / Joe / 3/21/12
Build Prototype / 3/30/12 / Team / 4/13/12
Surface Mount Components / 4/8/12 / Scott/Matt / 4/20/12
Prep Enclosure for Assembly / 4/10/12 / Mike / 4/11/12
Load Device Code onto MSP430 / 4/16/12 / Joe / 4/20/12
Assemble Full Device / TBD / Mike / TBD
Test Prototype / 4/13/12 / Team / 4/27/12
Test Circuitry / 4/6/12 / EE’s / 4/20/12
Test Alarm/Snooze Functionality / TBD / Joe / TBD
Test Bed Shaker Functionality / TBD / Cory/Alvaro / TBD
Table Drop Test / TBD / Mike / TBD
Begin Poster & Technical Paper / TBD / Team / TBD
Finalize Prototype Assembly / TBD / Mike/Matt / TBD
Wrap-Up Testing / TBD / Joe / TBD
Compile Test Results / TBD / Scott/Cory / TBD
Customer Demo / Week 8 / Team / Week 8
Create User Manual / TBD / Scott / TBD
Finish Poster/Paper / TBD / Alvaro/Cory / TBD
Create Manufacturing Plan / TBD / Mike/Matt / TBD
Update EDGE & Finalize Docs / TBD / Individual / TBD


Completed for 04/13/12:

Task / Responsible / Comp Date / Comment
Create DWG Package for Manufactured Model / Mike / 4/13/12
Update/Finalize BOM & Unit Costs / Scott / 4/10/12
Start Paper Abstract / Cory / Week 9
Develop MSP430 Code / Joe / TBD / Alarm Works
Help Cory with Paper / Alvaro / Week 9
Finalized Schematic & Performed Circuit Tests / Matt / 4/8/12 / LED/Charging
Investigate Case Testing and Team Activities / Mike / 4/13/12
Update EDGE / Work Plan Document / Mike/Matt / 4/10/12 / Final Design Files
Start User Manual / Scott / 4/27/12
Update Test Plan / Joe / 4/13/12

To Be Completed for 04/20/12:

Task / Responsible / Comp Date / Comment
Update Risk Assessment & EDGE / Mike / 4/16/12
Continue Software/BT Development / Joe / 4/17/12
Surface Mount Components / Matt & Scott / 4/20/12
Continue to Work on Paper / Cory/Alvaro / 4/20/12
Main PCB Testing / Matt / 4/17/12
Continue User Manual / Scott / 4/20/12
Update BOM/Component Check-Off / Alvaro / 4/16/12
Case Post-Processing & Test Fitting / Mike / 4/17/12
Action Items
Item # / Description / Responsible / Due Date / Close Date / Comments
A001 / Case & Lid Successfully Printed / Mike / 4/8/12 / 4/9/12 / Fits Well
A002 / Tested Charging Circuit / Matt & Scott / 4/4/12 / 4/4/12 / 100% Functional
A003 / Tested Alert LED Circuitry / Cory & Matt / 4/6/12 / 4/6/12 / 100% Functional
A004
A005
Issues
Item # / Description / Responsible / Open Date / Close Date / Comments
I001 / Burned Out LED Transistor / EE’s / 4/10/12 / 4/10/12 / Order 2 more
I002 / Need to find Ultrasonic Bath for Case / Mike / 4/11/12 / 4/18/12 / Remove Support Mat’l
I003
I004
Decisions
Item # / Description / Contributing Individuals / Decision Date / Comments
D001 / Make one prototype for test fit / Mike & Gary / 4/6/12
D002
D003
D004