INDICATIVE TIME PERIODS FOR TYPICAL PROJECTS

The following gives examples of the likely timescales for typical project types. Please note that these are indicative timescales only and each project will need to be programmed according to its own requirements and complexity. Please also note that if planning permission is required for a project, this can take 12 weeks following submission of the planning application.

Project Type / Example / Typical Value / From Request to RIBA stage D (detailed design) / From RIBA stage D to Tender complete / Construct / Total
A: Small works / Office redecoration 20m2, paint , carpet, lights / £5-40k / 3 weeks / 6 weeks / 5 weeks / 14 weeks
B: Minor works ‘revenue’ / Re-order 50m2-100m2: partitions, lab benching, mechanical vent, paint, flooring, lights / £40-250k / 8 weeks / 8 weeks / 10 weeks / 26 weeks
C: Minor works ‘capital’ / Full refurbishment and change of use of a floor of a building including partitioning, new toilets, all internal finishes, 800m2 / £250k-2m / 15 weeks / 20 weeks / 20 weeks / 55 weeks
D: Major capital / Full refurbishment of listed building / £9m / 30 weeks / 30 weeks / 60 weeks / 120 weeks

WORKS REQUESTED

REQUESTOR

/

Click here to enter text.

/

DEPARTMENT

/

Click here to enter text.

/

FUNDING SOURCE & AMOUNT AVAILABLE

/

Click here to enter text.

/

PROJECT TYPE (select from A-D above)

/

Please select

/

LOCATION OF WORKS

/

Click here to enter text.

/
OUTLINE OF WORKS BEING REQUESTED / Click here to enter text.
REASON FOR WORKS/(ATTACH BUSINESS CASE IF AVAILABLE) / Click here to enter text.
OPTIONS EXPLORED TO DATE / Click here to enter text. /
ZONE FACILITIES MANAGER / Click here to enter text. / HAS THE ZFM BEEN CONSULTED? / Click here to enter text. /
ANY CONDITIONS ON FUNDING? / Click here to enter text. / WORKS REQUIRED BY DATE / Click here to enter text. /
NOTES: (Please include any additional information here)
Click here to enter text.

REQUESTOR HEAD OF DEPARTMENT SUPPORT

In signing this document I confirm that Isupport the above works request.
Name / Signature
Position / Date

DECISION(To be completed by Estates Dept.)

Proceed to Feasibility Study / Further Information Requested / Request on hold / Rejected
Signature / Date
Gary Ashmore / Head of Development, Estates Services
Kevin Whelan* / Head of Operations, Estates Services
Strategic/ Major Projects (as above plus the following)
Stephen Talboys / Director of Estates and Campus Services
Senior Finance Manager
*Signature as appropriate
FINANCE WORKORDER / DEVELOPMENT/OPERATIONS
PROJECT MANAGER / OPERATIONAL CHAMPION
PROJECT SPONSOR
IMPREST DATA
DATE RAISED
(Start of current financial year) / 01 August Year
PORTFOLIO/PROGRAMME: / Equipment (EQ) / Estates Renewals (ER) / Finance (FIN)
Strategic Projects (SP) / Other Projects (OP)
PROJECT TYPE: / Major Works / Minor Works
APPROVAL BODY: / DECS / VC & SMG
University Council / Policy & Resources Committee
PROJECT CATEGORY:
VAT CATEGORY: / FR (fully recoverable) / PR (partially recoverable) / NR (non-recoverable)

Uncontrolled if Copied or Printed Works Request v4, January 2017