Our reference: Eiel/ site/2206/13-14 Date 22.06.2013

To

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject:-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR, ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD (QS) WO/CISF/336/08/10 DT 06.08.10

Dear Sir

With reference to Your letter no DCSE/CE(C2) 229/59 dated 6th June 2013, regarding progress of work. We are thank full for allowing the scaffolding with bamboo up 8th floor to expedite the external plastering work of II B .The bamboos are being purchase and scaffolding work with cup-lock system is also in progress. In II B central portion double slab set shuttering material procured and manpower also established so we are planning to complete at least 2 slabs in a month so that we can achieve the targets.

Regarding labour strength as mentioned in above letter it is 40% of actually at site. Still we are increasing the labour for following work:-

Water proofing—6 labour

External plastering-6 mason+10 labour including scaffolding work

Flooring 4 mason +6 labour

Carpenter for B Block 8+8=16

Total we are increasing 48 labour by which we can achieve revise strength of 165

Material :-

  1. FRP DOOR SHUTTER order we are placing but sizes will be finalized after 45 days since it is made to sizes actually available at site so these door shutters will be available by end of September.
  2. CUDAPPAH STONE:- 1/3 quantity we procured for IIB block remaining also ordered.
  3. Zet black granite: - order placed and by this month same will be at site by considering one piece up sink and sink piece separate if you allow we can procure the same.
  4. Aluminum window quantity is being calculated, the order of same also be placed in 2nd week of july-13 and material also be procured by end of july-13.

With above we are very hopeful to complete the above project as per given program.

Thanks

With regards

Komalsharma

Our reference: Eiel/ site/2705/13-14 Date 27.05.2013

To

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject:-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR, ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD (QS) WO/CISF/336/08/10 DT 06.08.10

Dear Sir

With reference to above please find enclosed here with the detailed revised M.B. for following item:-

1.RCC WORK

2. SHUTTERING WORK

3. REINFORCEMENT STEEL WORK

You are here by requested to depute your representative with our representative so that before closing of May month bill these left out quantity also be considered for payment.

Thanks

With regards

Komal Sharma

General Manager

For Era Infra Eng. Ltd

Our reference: Eiel/ site/1405/13-14 Date 14.05.2013

To

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject:-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR, ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD (QS) WO/CISF/336/08/10 DT 06.08.10

Dear Sir

As discussed several time in meeting as well as during site visit regarding river sand is not being supplied by the venders because of Mumbai court has banned the production of same since last 18 month due to which our plastering and water proofing work is suffering badly .

Therefor you are requested to please give some other solution so that work could be completed.

Thanks

With regards

Komal Sharma

General Manager

For Era Infra Eng. Ltd

Our reference: Eiel/ site/2004/13-14 Date 20.04.2013

To

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject:-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR, ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD (QS) WO/CISF/336/08/10 DT 06.08.10

Regarding your letter no DCSEM/PE(B)CISF/846(a)

Dear Sir

With reference to your above letter we would like to give you the reference of last meeting held with you & honorable chief Engineer (2).the point of nonpayment discussed but no solution held till date. Our payment was stuck-up with you as under since last three months, the phase program also submitted three month back :-

Work done due to hold which is not reflecting in part rate:- 20 lacs

P.H.Work already done but not entered in bill :-11 lacs

MAS of steel 110 mt @ 50000*90% :-49.5 lacs

MAS of SANITARY ITEM G.I. PIPES AND OTHER :-10.5 lacs

S.S.SINK,C.P.FITTING ,DOOR FITTING AND OTHER :-10 LACS

TOTAL :-101 LACS

You should appreciate our passivity towards work, after more than one crore payment held up with the department still we are working.

Regarding slow progress of plaster and brick work no solution of sand yet given by the department .we already spent more than 50 lacs in account of extra cost paid toward purchase of sand from other state to complete at least IV D building. No compensation in this account paid nor even thought by the department to come out from such a big problem.

We are once again promising to complete the work but same time department also should see toward s our dues and solution of river sand. Because same is not only our problem it shear responsibility and liability of both of us.

Thanks

With regards

Yours very truly

Komal Sharma

For Era Infra Engg ltd

Our reference: Eiel/ site/1704/12-13 Date 17.04.2013

To

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject:-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR, ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD (QS) WO/CISF/336/08/10 DT 06.08.10

Regarding approval of DEVIATION in items of IV D BUILDING

Dear Sir

With reference to above we are here by submitting the list and quantity of deviated items for IV D building .so you are here by requested to please take the administrative approval from competent authority.

Your early approval is requested so that we can get the payment in next R.A.Bill

Thanks

With regards

Yours very truly

Komal Sharma

For Era Infra Engg ltd

Enclosed :- List of deviated item

Our reference: Eiel/ site/1604/12-13 Date 16.04.2013

To

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject:-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR, ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD (QS) WO/CISF/336/08/10 DT 06.08.10

Regarding approval of substitute item of kitchen sink (REVISED)

Dear Sir

With reference to above we are here by submitting the rate analysis for providing and fixing of 1145x510x200 mm (large anti-scratch) in place of 610x460x200 mm (large anti-scratch)

your early approval is required so that we can get the payment in next R.A.Bill

Thanks

With regards

Yours very truly

Komal Sharma

For Era Infra Engg ltd

Enclosed price ANALYSIS OF RATE & BILL OF SINK

Our reference: Eiel/ site/1204/12-13 Date 12.04.2013

To

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject:-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR, ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD (QS) WO/CISF/336/08/10 DT 06.08.10

Regarding approval of substitute item of kitchen sink

Dear Sir

With reference to above we are here by submitting the rate analysis for providing and fixing of 1145x510x200 mm (large anti-scratch) in place of 610x460x200 mm (large anti-scratch) :-

Our boq rate as per item no part II 5.1=5106/(A)

Less cost of sink =-8425/(B)

Less cost of granite sand wicthplatefarm:-

0.610 x0.46=.281 sqm @3275/= -920/©

Net status =-4239/(d)

ADD Cost of large kichen sink=14335/(e)

add cost of granite sand wicthplatefarm:-

1.145 x0.510=0.584 sqm @3275/=1912.43/(f)

Add extra labour for fixing of large sink=100/ (g)

D+e+f+g=12108.43

Add wct 2%=242.16/

Tds 2%=242.16/

Total=12592.75

Add c.p.15%=1888.91

Total after c.p.=14481.67

Say Rs. 14482/-

your early approval is required so that we can get the payment in next R.A.Bill

Thanks

With regards

Yours very truly

Komal Sharma

For Era Infra Engg ltd

Enclosed price list of Nirali

Our reference: Eiel/ site/0504/12-13 Date 05.04.2013

To

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject:-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR, ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD (QS) WO/CISF/336/08/10 DT 06.08.10

Regarding approval of precast chequered tile

Dear Sir

With reference to above we are hereby submitting the chequered tile catalog for your kind approval. Few available samples are also being submitted for your early approval.

Thanks

With regards

Yours very truly

Komal Sharma

For Era Infra Engg ltd

Enclosed catalog of super tile

Our reference: Eiel/ site/2402/12-13

To Date 24.2.2012

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject:-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR, ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD (QS) WO/CISF/336/08/10 DT 06.08.10

Regarding time extension

Dear Sir

With reference to above we are here by requesting you to please grant us time extension till 30.9.2013. Earlier we were planned to complete the above by 31.6.2013 but due to following reason same seems very tough.

In IV D Building 100% Brick work and R.C.C. structure has been completed long back but due to non-availability of sand for plastering we are finding our self very tight to complete the external plaster work .it is because of ban on production of river sand by the state government with the order of court. For reference the copy of new paper cutting is attached.

We are now getting bricks for remaining brick work in II B building because new bricks production just started on kilns since last Monsoon .the already procured bricks we used to complete the brick work of II B Building up to 6thfloor.

The rising main approval we received on 18th march , fire alarm approval not yet received since it is imported item will take at least 3 -4 month in procurement.

Lightning arrester approval yet to receive.

Laborers are always short because of central government scheme implemented that is, the unemployed are getting 120 days job at their respective state.

Therefore you are requested please consider our request and grant us extension of time up 30.9.2013.

Thanks

With regards

Yours very truly

Komal Sharma

For Era Infra Engg ltd

To Date 01.03.2013

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject:-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR, ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD (QS) WO/CISF/336/08/10 DT 06.08.10

Regarding :- Engineering staff at site

Dear Sir

With reference to above please find attached here with the organization chart of above said project.

Thanks

With regards

Yours very truly

Komal Sharma

For Era Infra Engg ltd

Our reference: Eiel/ site/2412/12-13

To Date 24.12.2012

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject:-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR, ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD (QS) WO/CISF/336/08/10 DT 06.08.10

Regarding time extension

Dear Sir

With reference to above we are here by requesting you to please grant us time extension till 30.6.2013. Earlier we were planned to complete the above by 31.3.2013 but due to following reason same seems very tough.

In IV D Building 100% Brick work and R.C.C. structure has been completed long back but due to non-availability of sand for plastering we are finding our self very tight.it is because of ban on production of river sand by the state government with the order of court.

We are not getting bricks for remaining brick work in II B buildingbecause new bricks production not yet available on kilns since last Monsoon .the already procured bricks we used to complete the brick work of II B Building up to 6 th floor.

The rising main, fire alarm approval not yet received since it is imported item will take at least 3 month in procurement.

Lightning arrester approval yet to received.

Laborers are always short because of central government scheme implemented that is, the UN employed are getting 120 days job at their native in their respective state

Therefore you are requested please consider our request and grant us extension of time up 30.6.2013.

Thanks

With regards

Yours very truly

Komal Sharma

For Era Infra Engg ltd

Our reference: Eiel/ site/2612a/12-13

To Date 26.12.2012

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject:-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR, ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD (QS) WO/CISF/336/08/10 DT 06.08.10

Payment certificate

Dear Sir

This is for your kind information that we have paid all wages of worker up to date Dues on above said project site.

Thanks

With regards

Yours very truly

Komal Sharma

For Era Infra Engg ltd

Our reference: Eiel/ site/2612/12-13

To Date 26.12.2012

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject:-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR, ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD (QS) WO/CISF/336/08/10 DT 06.08.10

Submission of R.A.Bill

Dear Sir

We are here by submitting our R.A. Bill no .it for your kind checking and processing of bill as soon as possible.

Thanks

With regards

Yours very truly

Komal Sharma

For Era Infra Engg ltd

Our reference: Eiel/ site/0512/12-13

To Date 05.12.2012

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject:-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR, ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD (QS) WO/CISF/336/08/10 DT 06.08.10

Submission of R.A.Bill

Dear Sir

We are here by submitting our R.A. Bill no .it for your kind checking and processing of bill as soon as possible.

Thanks

With regards

Yours very truly

Komal Sharma

For Era Infra Engg ltd

Our reference: Eiel/ site/2210/12-13

To Date 22.10.2012

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject:-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR, ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD (QS) WO/CISF/336/08/10 DT 06.08.10

Request for gate pass of flush door

Dear Sir

The 50 mm thick flush doors are failed in end immersion so we want to take out these shutters from site. So please arrange to permit us to take out these shutters.

  1. 50 mm thick size(770x2010mm) 100 nos
  2. 50 mm thick size(870x2010 mm) 18 nos

Thanks

With regards

Yours very truly

Komal Sharma

For Era Infra Engg ltd

Our reference: eiel site/0310a/12-13

To Date 3.10.2012

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject :-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR ,ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD(QS)WO/CISF/336/08/10 DT 06.08.10

Submission of door lock and night latch samples for approval

Dear Sir

Please find the samples of lock & night latch as per item ,so please approve the same so that we can execute the work .

Thanks

With regards

Yours very truly

Komal Sharma

For Era Infra Engg ltd

Our reference: eiel site/0310/12-13

To Date 3.10.2012

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject :-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR ,ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD(QS)WO/CISF/336/08/10 DT 06.08.10

Submission of revised shop Drawing of IV D aluminum window

Dear Sir

Please find attached here with the shop drawing of aluminum window to be fixed at above said project the section used are Jindal b series. These are the typical drawings,so please approve the same so that we can execute the work .

Thanks

With regards

Yours very truly

Komal Sharma

For Era Infra Engg ltd

Our reference: eiel site/1409/12-13

To Date 14.9.2012

The Project Engineer (B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject :-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR ,ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD(QS)WO/CISF/336/08/10 DT 06.08.10

Dear sir

Please find attached here with the revised completion program of above said project. Although we are facing very big crisis of sand to be used in plaster and other work due production of sand is totally banned in entire Maharashtra .we also not getting bricks. Still we will try to complete as per schedule attached.

Thanks

With regards

Yours very truly

Komal Sharma

For Era Infra Engg Ltd

Our reference: eiel site/2008/12-13

To Date 21.8.2012

The Project Engineer(B)

DCSEM (DILWRA BULDING)

Anushakti Nagar (MUMBAI-94)

Subject :-CONSTRUCTION OF 194 FLATS OF IIB TYPE (STILT+13 UPPER FLOORS) AND 18 FLATS OF IV D TYPE (STILT+6 UPPER FLOORS) INCLUDING INTERNAL PH & ELECTRICAL WORKS FOR CISF AT WESTERN SECTOR ,ANUSHAKTI NAGAR. W.O.NO: DCSE/HEAD(QS)WO/CISF/336/08/10 DT 06.08.10

Dearsir

Please find attached here with the shop drawing of 2,3,4,5 track sliding window to be fixed at above said project the section used are Jindal b series. Thesetypical drawing if sections used are approved than window wise revised drawing will be submitted to your office within week.