TYPE IIICONDITIONAL USE PERMIT, TYPE III VARIANCE, TYPE II SITE PLAN REVIEW & CRITICAL AREA REVIEW

Application File:Energize Eastside Transmission Line Project

Application File Number:CUP17-002/ VAR17-004/ SITE18-001/ CAR17-013

Applicant:Bradley Strauch

Puget Sound Energy

PO Box 98034, EST-3,

Bellevue WA 98009-9734

City Official Contact: Thara Johnson, Senior Planner

Date Original Application Filed: November 9, 2017

Date Complete Application Filed:January 19, 2018

Date Determined Complete:February 2, 2018

Date of Notice of Application:February 16, 2018

Comment Period Ending Date: March 19, 2018 at 5:00 PM

Project Location:Parcel# Various (1.5 miles within existing Puget Sound Energy easement)

Project Description:Application for placement of a new 230 kV transmission line within an existing utility corridor which currently consists of two 115 kV transmission lines.

Environmental Review: On April 30, 2015, the Environmental Coordinator for the City of Bellevue, serving as lead agency, published a Notice of Determination of Significance, indicating that this proposal could have a significant adverse impact on the environment and required preparation of an Environmental Impact Statement (EIS) under Revised Code of Washington (RCW) 43.21C.030(2)(c). On January 28, 2016, the lead agency issued a Phase 1 Programmatic Draft EIS, which evaluated alternative methods to achieve PSE’s project objectives. On May 8, 2017, the lead agency issued a Phase 2 Draft EIS, which analyzed several alternatives for overhead 230 kV lines and a new substation. A Final EIS has been prepared to analyze PSE’s Proposed Alignment, including one option for the Newcastle segment that was not described in the Phase 2 Draft EIS. The EIS is not a permit - it is one of many sets of information permitting agencies will consider as they decide whether to approve the project and issue necessary permits.

Permits requested in this application:Conditional Use Permit, Variance, Site Plan Review Critical Area Review Approval

Consistency with applicable City plans and regulations:This proposal will be reviewed for consistency with the Zoning Ordinance, Critical Areas Ordinance, Public Works Standards, Comprehensive Plan.

Other permits not included in this application:SEPA Checklist Review, Building Permit, ROW Permit, Engineering Review Permit

Comments must be submitted by the comment period ending date noted above to: Thara Johnson, Senior Planner, City of Newcastle, 12835 Newcastle Way Suite 200, Newcastle, WA 98056.

Information about the appeal process will be included in the Notice of Final Decision. The project application may be reviewed at Newcastle City Hall. Anyone wishing to comment on this proposal may do so in writing to Thara Johnson at or at 12835 Newcastle Way Suite 200, Newcastle, WA 98056.

NOTE: If you require this material in Braille, audiocassette, or large print, please call (425) 649-4444.

Please send me notification of official notices concerning this application.

File: CUP17-002/ VAR17-004/ SITE18-001/ CAR17-013(Energize Eastside Transmission Line Project)

Name:______

Address:______

Email______Telephone # ______Best Contact: Email/Mail/Phone