Major Objectives / Key Tasks / Lead Organization / Timeline (from contract signature date)
60 days / 90 days / 120 days / 150 days / 180 days / 240 days
- Contract with software vendor completed
 
- Negotiate contractor functions, deliverables and costs.
 
- Launch Core Site.
 
- Establish URL. Launch core site with Background information on the project and educational service descriptions.
 
- Implement the web-based Service Directory statewide.
 
- Establish ResourceCenter policies and procedures for keeping the directory accurate and complete. The ADRC site will be responsible for maintaining the directory.
 - Conduct follow-up calls to ensure entry of information; ResourceCenter staff enter information for providers without Internet access in the 7-county area. Additional providers can have access to add and update listings.
 - Online Service Directory and I&R go live.
 
2. MS ADRC/AAAs
3. MS ADRC/AAAs
4. Software Vendor / X
X
X
X
- Modify and implement the Software
 
- In consultation with ADRC and DAAS plan and implement minor Software modifications necessary for use in Mississippi.
 - Establish policies and procedures for use of the Software system.
 - Transfer existing client records to Software from SAMS database. (if applicable)
 - Train employees on use of Software system
 - Begin using the Software to assess, refer, and enroll elderly clients in services.
 
X
X
X
- Implement Software for phase 2 (3 AAA sites)
 
- Develop ResourceCenter procedure manual, and train all employees using the manual. There will be different sections for the various functions so the same manual can be used across all sites.
 - Train employees on use of Software
 
X
X
X
- Implement Software for phase 3 (3 AAA sites)
 
- Optional training.
 - Implementation of Software at additional AAA sites.
 
- Software Vendor DAAS and AAAs
 
X
- Software phase 4 (3 AAA sites)
 
- Optional training.
 - Implementation of Software at additional AAA sites.
 
2. Software Vendor DAAS and AAAs / X
X
- Suggested: Develop and implement social marketing campaign in preparation for opening the Aging and DisabilityResourceCenter
 
- Convene the Advisory Committee to provide input in planning the campaign
 - Locate community resources to assist with the campaign, including provider organizations, individuals, local TV, radio, newspapers, etc.
 - Launch the statewide campaign at least two weeks before official opening and continue components of the campaign for at least two months after the opening.
 
X
X
X