CITY OF ATMORE

INFORMATION REQUIRED FOR

COMMERCIAL PERMIT

1.) Two (2) complete sets of plans including a site plan.

2.) Rivercane Only: One (1) complete set of plans including a site plan

submitted to the Rivercane Architectural Review Committee. There is

a $500.00 review fee associated with this submittal. Permit will not be

issued without written approval from the Rivercane Architectural

Review Committee.

3.) Completed building permit application.

4.) If project value is $50,000 or more; proof of current City of Atmore

business license and proof of current State General Contractors License.

5.) If project value is less than $50,000; proof of current City of Atmore

business license or signed Owner-Contractor Agreement.

6.) List of subcontractors performing work on the project.

7.) Documentation of sewer service.

I HEREBY CERTIFY THAT I HAVE SUBMITTED ALL OF THE ABOVE REQUIRED ITEMS.

CONTACT PERSON: ______

PHONE: ______EMAIL: ______

SIGNATURE: ______

CITY OF ATMORE

COMMERCIAL PERMIT APPLICATION

New Construction: _____ Addition: _____ Renovation: _____

Electrical: _____ Plumbing: _____ Mechanical: _____

Address: ______

______

Contractor: ______Phone: ______

General Contractors License # ______

City of Atmore License # ______

Owner: ______Phone: ______

______

Flood Zone: ______Zoning: ______Sq. Ft. of project area ______Project Value: ______

Parcel #: ______

Lot Size: ______sq. ft. /acres Lot Dimensions: ______

Current Occupancy Type: ______Proposed Occupancy Type: ______

______

Utilities Available To Site: Sewer _____ Water _____ Gas _____

Sanitary Sewer Tap: Existing _____ New Installation _____

Septic Tank: Existing_____ New Installation _____

Water: Existing _____ New Installation _____

______

Proposed Setbacks:

Front: ______Rear: ______Sides: ______& ______Building Height: ______

______

Approved: ______Date: ______

WEST ESCAMBIA UTILITIES

APPLICATION FOR APPROVAL OF SEWER SERVICE

Address where service is requested: ______

Improvement Type:

___ Single Family Dwelling ___ Multi-Family Dwelling ___ Commercial Building

___ Duplex ___ Manufactured Home

Applicant:

Name ______

Address ______

Phone ______

THIS SECTION TO BE COMPLETED BY WEST ESCAMBIA UTILITIES
Payment of Inspection Fee
Date ______Amount $ ______Received By: ______
Site Inspection
Water Meter ___ Approved ___ New Meter Required Estimated Cost $______
Sewer ___ Approved ___ New Meter Required Estimated Cost $______
Signed ______Date ______
WEU Manager or Supervisor

In the event that West Escambia Utilities determines that an existing service connection is useable, they will install a cleanout at the property line. Maintaining this cleanout shall be the responsibility of the property owner. Where West Escambia Utilities determines that there is no sewer connection or that the existing sewer connection is insufficient, the customer will be required to pay an additional $1,500.00 for the installation of a new sewer connection. Existing service lines shall be of at least schedule 40 PVC.

This form must be completed and submitted to the City of Atmore Building Department prior to obtaining a permit for the proposed project.

CITY OF ATMORE

COMMERICAL BUILDING

OWNER-CONTRACTOR AGREEMENT

Permit # ______

Applicant: ______

Address: ______

I hereby make application to the City of Atmore for a permit so that I may perform work on a structure that I own located at the address referenced above. I understand that I will be acting as my own contractor and will therefore be responsible for ensuring all work performed is compliant with all applicable codes, ordinances, laws, rules and regulations. I take full responsibility for ensuring any subcontractor that may perform work on this project is properly licensed, certified, and qualified to perform such work. It will be my responsibility to notify the City of Atmore when work is ready for inspection and to make sure the structure is not used or occupied prior to obtaining final approval.

Signature ______Date ______