Exhibit Eto RFB-17066 / CSI Division Work AssignmentSchedule

Complete the information requested below per the applicable CSI Division required for this Bid. Any portion of the form not filled in will be considered non-conforming and an irregularity, and may affect the award of this Bid. EXCEPTION: Any Division not applicable to this Bid may be left void or blank.

PROJECT: Interior Lighting Replacement Project Phase IIDATE: November 15, 2016

ARCHITECT/ENGINEER:Apogee Consulting Group

CONTRACTOR NAME: ______

Do not combine categories of work; list separately per respective Construction Specification Institute (CSI) Division.

WORK DESCRIPTION CSI Division / PRIME, SUBCONTRACTOR, SUPPLIER
Name, City and State / **WORK LEVEL
SP or Tier 1 / % of BID VALUE / BID
AMOUNT / TRADESPerformed by Division
Div 01: General Requirements / $
Div 02: Existing Conditions / $
Div 03: Concrete / $
Div 04: Masonry / $
Div 05: Metals / $
Div 06: Wood, Plastics, Composites / $
Div 07: Thermal & Moisture Protection / $
Div 08: Openings / $
Div 09: Finishes / $
Div 10: Specialities / $
Div 11: Equipment / $
Div 12: Furnishings / $
Div 13: Special Construction / $
Div 21: Fire Suppression / $
Div 22: Plumbing / $
Div 23: HVAC / $
Div 25: Integrated Automation / $
Div 26: Electrical / $
Div 27: Communication / $
Div 28: Electronic Safety & Security / $
Div 31: Earthwork / $
Div 32: Exterior Improvements / $
Div 33: Utilities / $
Other – Please specify / $
Totals of: % of Bid Valueand Bid Amount(% must add up to 100 and Bid must equal RFB-16045 Bid Value) / $
  1. Fill in information for each Division of work to be completed under this Bid, even if, the work is self-performed by the General Contractor.
  2. ** Work Level Descriptions: SP = Self performed by Prime/General Contractor; Tier 1: Subcontractor to Prime/GC;

Document #00-416