Waiver of “Significant Impact” Request3
2015 Waiver of “Significant Impact” Request
The sponsor(s) of transmission projects with operating voltages 200 kV and above, and are not seeking a path rating, may request waivers of the WECC Project Coordination Process. The request must either provide documentation of how the project is being coordinated in another forum, or provide an explanation of why the project is not expected to have any significant impact to the operation of the WECC interconnected electric system. More information about the WECC Project Coordination Process can be found here.
Project Name Project Sponsor
- Hassayampa‐N.Gila #2 (aka HANG2) 500 kV Project (2015) APS
- Palm Valley‐Trilby Wash 230 kV Project (2015) APS
- Sun Valley‐Trilby Wash 230 kV Project (2016) APS
- Palo Verde‐Delaney 500 kV Project (2016) APS
- Delaney‐Sun Valley 500 kV Project (2016) APS
- Ocotillo Modernization Project (2017) APS
- Mazatzal 345/69 kV Substation (2017) APS
- Sun Valley‐Morgan 500 kV Project (2018) APS
- N.Gila‐Orchard 230 kV Project (2018) APS
- Sun Valley‐Morgan 230 kV Project (2026) APS
- Scatter Wash 230/69 kV Substation (TBD) APS
- Bill Durfee (Sundance) 230 kV Substation BHP
- Raver 500/230 kV Transformer Addition Project BPA
- McNary 500/230 kV Transformer Addition Project BPA
- Second 230kV line from Front Range Plant to Nixon-Kelker (NX-KE) Line CSU
- Midpoint T232 230/138 kV Transformer Addition Project IPC
- Midpoint West Upgrade Project IPC
- Wallula – McNary 230 kV Line PAC
- Planned Generation Interconnection Projects (PACE) PAC
- Table 8b: Planned Generation Interconnection Projects (PACW) PAC
- Los Banos-4C779 #1 230kV Line Reconductoring Project PG&E
- Gregg-Herndon #2 230 kV Line Circuit Breaker PG&E
- Bellota – Warnerville 230 kV Line Reconductoring PG&E
- Glenn 230/60 kV Transformer No. 1 Replacement PG&E
- Monta Vista 230 kV Bus Upgrade PG&E
- Midway-Kern PP 230 kV #2 Line Project PG&E
- Estrella Substation PG&E
- Midway Fault Duty Mitigation Project PG&E
- Wheeler Ridge Junction Substation PG&E
- Morgan Hill Area Reinforcement Project PG&E
- Q779 PG&E
- Q829 PG&E
- Q643X PG&E
- Q877 PG&E
- Q258 PG&E
- Blue Lake/Gresham 230 kV Project PGE
- Horizon Phase II Project PGE
- Port Westward II generation PGE
- Tucannon River Wind Farm PGE
- Laporte 230 kV Substation Expansion PRPA
- Boyd 230/115kV Transformer Addition Project PRPA
- Miguel Synchronous Condenser SDGE
- Phase Shifting Transformer (PST) at Imperial Valley SDGE
- SVC at Suncrest Substation SDGE
- Browning ‐ Rogers 230kV line SRP
- Hassayampa – Pinal West 500kV line loop into Jojoba Substation SRP
- Price Road Corridor Project SRP
- Eastern Mining Expansion Project SRP
- Santan – Rogers 230kV line Reconfiguration SRP
- Browning – Corbell 230kV line Reconfiguration SRP
- Abel – Pfister ‐ Ball 230kV line SRP
- Hassayampa – Pinal West #2 500kV line SRP
- Southwest Weld Expansion Project TSGT
Western Electricity Coordinating Council