Cameroon: EducationDevelopmentCapacityBuilding – P075964 - CR.4070-CM
Simplified Procurement Plan Revised in June 2008
- Project information: Cameroon - Education Development Capacity BuildingSupport Project – ID No- P075964 - CR- 4070-CM -
2.Bank’s approvalDate of the procurement Plan: March 31, 2005
Revised April 2006 and June 2008
- Date of General Procurement Notice: November 2005
- Period covered by this procurement plan:12 months
II. Works, goods and non-consulting services
1.Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement:
Procurement Method / Prior Review Threshold(US$ equivalent) / Comments
1. / ICBand LIB (Goods) / 150,000 / All contracts
2. / NCB (Goods) / 50,000 and 150,000 / First 3 contracts to be executed
3. / ICB (Works) / 200,000 / All contracts
4. / NCB (Works) / 50,000 and 200,000 / First 3 contracts to be executed
5. / ICB (Non-Consultant Services) / 150,000 / All contracts
6 / Direct contracting / All / All contracts
2.Prequalification. Bidders shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines: Non applicable
3.Any Other Special Procurement Arrangements: N/a
4.Procurement Packages with Methods and Time Schedule
Works
1 / 2 / 3 / 4 / 5 / 6 / 7 / 8Ref. No. / Contract
(Description) / Procurement
Method / Prequalification (yes/no) / Domestic Preference
(yes/no) / Review
by Bank
(Prior / Post) / Expected
Bid-
Opening
Date / Comment/
Completion
Date
UCP
No activity / N/A / N/A / N/A / N/A / N/A / /NA / N/A
Goods
1 / 2 / 3 / 4 / 5 / 6 / 7 / 8Ref. No. / Contract
(Description) / Procu-rement
Method / Prequali-fication (yes/no) / Domes-tic Pre-ference
(yes/no) / Review
by Bank
(Prior / Post) / Expected
Bid-
Opening
Date / Comment/Comple
Tion Date
1 / Production/multiplication et distribution des guides, de support de campagne pour la DPOS/IGE/DESG; l'IGS et les ZEP / Shopping / NO / NO / Post / Novembre 2008 / Janvier2009
2 / Production des instruments (matériel) pour la réalisation de la collecte des données des personnels / Shopping / NO / NO / Post / Juillet 2008 / Octobre2008
3 / Equipement du niveau central (DPOS) et des DPEN, en matériel informatique, système d'information et matériel divers / ICB / NO / NO / Prior / Octobre2008 / Janvier 2009
4 / Mobilier pour le niveau central (DPOS) et les 06 DPEN / NCB / NO / NO / Prior / Octobre2008 / Janvier 2009
5 / Production Multiplication et distribution des Instruments, des Guides des Documents de formation, des documents de séminaires et de 25 000 curricula / NCB / NO / NO / Post / Octobre2008 / Janvier 2009
6 / Production Multiplication et distribution des questionnaires portant sur l’enquête sur la santé scolaire / Shopping / NO / NO / Post / Novembre 2008 / Janvier 2009
7 / Equipement des DPEN, DDN, DPEM, en matériel informatique et l'extension des réseaux internet dans les 10 DPEN en deux lots (Lot 1: Ordinateurs; Lot 2: risographes, tableaux conférenciers, accessoires, flip chartes, vidéo projecteurs) / NCB / NO / NO / Prior / Octobre2008 / Janvier 2009
8 / Fourniture/installation matériel informatique et divers pour le GDLN / ICB / NO / Yes / Prior / Octobre2008 / Avril 2009
9 / Fourniture/installation équipements audiovisuels pour vidéo conférence au GDLN / DC / NO / NO / Prior / Octobre2008 / Avril 2009
10 / Production des supports de communication et de sensibilisation pour la reforme des programmes de l’enseignement secondaire et de supports de sensibilisation communautaires en matières de redoublement scolaire / NCB / NO / NO / Post / Octobre2008 / Avril 2009
11 / Production et multiplication des dépliants, plaques et manuel de procédures de la gestion des subventions accordées par l’Etat à l’Enseignement Privé. / Shopping / NO / NO / Post / Novembre2008 / Janvier 2009
12 / Acquisition réfrigérateur, cafetières (04) et divers meubles pour le PASE en 2 lots:
[(Lot 1: fauteuil pour le Coordonnateur Technique, meuble support pour télévision le serveur et onduleur) et, Lot 2: Cafetières et bouilloire] / Shopping / NO / NO / Post / Juillet2008 / Septembre2008
13 / Acquisition consommables et clé USB pour le PASE / Shopping / NO / NO / Post / Novembre 2008 / Janvier 2009
15 / Prestataire de service pour la maintenance des équipements du PASE en 2 lots - (Lot 1: Informatique, et lot 2: copieurs) / Shopping / NO / NO / Post / Novembre 2008 / Janvier 2009
16 / Prestataire de service pour la maintenance des climatiseurs du PASE / Shopping / NO / NO / Post / Novembre 2008 / Janvier 2009
20 / Prestataire de service pour l’acheminement des courriers pour le PASE / Shopping / NO / NO / Post / Novembre2008 / Janvier2009
21 / Prestataire de service pour la mise en place en place d’une connexion internet à haut débit. / Shopping / NO / NO / Post / Novembre 2008 / Janvier2009
Consultancy
III.Selection of Consultants
1.Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants:
Selection Method / Prior Review Threshold(US$ equivalent) / Comments
1. / Competitive Methods (Firms) / 100,000 / All contracts value above $100,000and first 3 contracts to be executed regardless of the contracts amounts
2. / Single Source (Firms) / All / All contracts
3. / Competitive Methods (IC) / 50,000 / All contracts value above $50,000 And first 3 contracts to be executed regardless of the contracts amounts
4. / Single Source (IC) / All / All contracts
2.Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$100,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.
3.Consultancy Assignments with Selection Methods and Time Schedule
1 / 2 / 3 / 4 / 5 / 6Ref.
No. / Description of Assignment / Selection
Method / Review
by Bank
(Prior / Post) / Expected
Proposals Submission
Date / Comments/
Completion
Date
Component 1
1 / Cabinet pour la réalisation d'un audit des marchés publics avec le nouveau guide et formation en audit interne / QCBS / Post / Septembre 2008 / Février 2009
2 / Cabinet/Organisme pour la formation des Inspecteurs IGS en organisation et méthode / QCBS / Prior / Septembre 2008 / Mars 2009
3 / Cabinet/Organisme pour la formation des gestionnaires des services centraux / QCBS / Post / Septembre 2008 / Mars 2009
Component 2
5 / Cabinet pour un appui a l’élaboration d’un nouveau système / QCBS / Prior / Octobre 2008 / Avril 2009
7 / Traduction des curricula d'EVF, VIH/SIDA / CQ / Post / Septembre 2008 / Février 2009
Component 3
10 / Recrutement d'un consultant pour la production d'un manuel de procédures du CIRD / QCBS / Post / Septembre 2008 / Février 2009
11 / Cabinet/Organisme de consultation pour la formation des bibliothécaires / QCBS / Post / Septembre 2008 / Février 2009
12 / Recrutement d'un consultant pour la production d'un manuel de procédures du CITI / QCBS / Post / Septembre 2008 / Février 2009
13 / Cabinet/Organisme de consultation pour la formation des techniciens de Centre "CITI" / QCBS / Post / Septembre 2008 / Février 2009
14 / Cabinet pour la réalisation des études économiques relatives pour GDLN / QCBS / Prior / Juin 2008 / Novembre 2007
15 / Cabinet pour la réalisation du schéma directeur du système d’information de l’Enseignement Supérieur / QCBS / Prior / Décembre 2007 / Septembre 2007
16 / Cabinet pour l’élaboration d’un plan directeur de la recherche universitaire / QCBS / Prior / Septembre 2008 / Mars 2009
Component 4
17 / Cabinet/Organisme de renommée Internationale pour le renforcement des systèmes d'information (développement d'un logiciel de traitement et d'analyse des données universitaires) et une formation locale des cadres en technique de gestion des données. / QCBS / Prior / Septembre 2008 / Mars 2009
Component 5
17 / Recrutement d'un consultant qui devra mener une étude sur l'impact du don EFA-FTI sur la qualité et l'efficacité du recrutement des enseignants / QCBS / Prior / Septembre 2008 / Mars 2009
17 / Recrutement d'un Cabinet de Suivi évaluation des sous-objectifs 2 (Allocation rationnelle des postes dans toutes les écoles de chaque province), 3(Affectation, mutations et nomination des enseignants selon des critères explicites) et 5 (Renforcement des capacités en vue de la mise en oeuvre d'une gestion déconcentrée des personnels enseignants) / IC / Prior / Septembre 2008 / Mars 2009
Unité de Coordination du Projet
18 / Consultant pour l’audit des comptes du projet pour une durée de deux ans / LCS / Prior / Mai 2008 / Décembre 2008
19 / Cabinet d’audit technique sur deux années des activités du projet (ONG) / QCBS / Prior / Septembre 2008 / Mars 2009
20 / Cabinet de communication pour l’élaboration et la mise en place du plan de communication du PASE sur deux années / QCBS / Prior / Janvier 2008 / Mai 2008
ICB: Limited International Bidding
NCB: National Competitive Bidding
QCBS: Quality and Cost – Based Selection (QCBS)
QBS: Quality-Based Selection
CQ:Selection Based on the Consultant’s Qualifications
LCS: Least – Cost Selection (LCS)
Page 1 of 5