ABI-301
Management Science-2
Final Period Practical Problems
QUESTION#1
When Fox Commercial opened a new office, they defined a work as project with the following activities and predecessor(s).
Activity / Imm. Predecessor / TimeWeeks
A / -- / 5
B / -- / 3
C / A / 3
D / A / 2
E / D / 4
F / B / 7
G / C,E,F / 2
i. Draw the project network using AOA & AON?
ii. How many paths in the network?
iii. What is the critical path?
iv. Calculate the Slack of each activity?
v. If Activity F delayed by 4 weeks what will be the effect of project completion time?
vi. If Activity C delayed by 3 weeks what will be the effect of project completion time?
QUESTION#2
The following table contains information related to the major activities of a research project. Use the information to do the following:-
a) Draw a precedence diagram using AOA and AON.
b) Find the Critical Path.
c) Determine the SLACK of each activity.
Activity / Imm. Predecessor / Time WeeksA / -- / 5
C / A / 8
D / C / 2
B / A / 7
E / -- / 3
F / E / 6
I / B,D / 10
M / F,I / 8
G / -- / 1
H / G / 2
K / H / 17
H / K,M
QUESTION#5
From the following network diagram answer the following questions:
1) The Critical path in the above network diagram is
2) The time required to finish this project as early as possible is
3) The slack of activity C and F are ------and ------respectively.
4) The Early Start ES for Activity H is ------week(s)
5) In order to get second Critical Path activity E should be delayed by ------weeks
6) The Early start and late finish for activity J are ------and ------respectively.
7) The Slack for activity G is
8) Build the predeceasing tables of the above network.
QUESTION#6
From the following network diagram answer the following questions:
1) The Critical path in the above network diagram is
2) The time required to finish this project as early as possible is
3) The slack of activity B and D are ------and ------respectively.
4) The Early Start ES for Activity E is ------week(s)
5) In order to get second Critical Path activity F should be delayed by ------weeks
6) Build the predeceasing tables of the above network.
======GOOD LUCK ======