Demolition Pre-Bid Meeting/Minutes 10:45 am
8/13/13
Employees in attendance: Herman Augerhole, Delana Kimble, Tracie Cochran, Willie Hooper, Barry Allen, Rex Jordan, Larry Sloan
Points of Discussion during Meeting
A bid packet was provided to all parties covering pertinent dates, bonding requirements, mandatory bid documents, and sealed bid submittal instructions. Herman Augerhole covered handout in detail.
Questions regarding scope of work and specifications were covered by Herman Augerhole.
The following points were made during the meeting:
Summary of Bids
Preparation Outline was read
Bid Bond 5% Grand Total of Demo
Interpretation of Bid Docs
Due dates
TERO (Tribal Employment Rights Office) was represented by William Augerhole. Information regarding TERO was explained by Herman. The following points were discussed:
- Indian Preference applies to the General Contractor, Sub-Contractors, and employees on the jobsite.
- TERO fees of ½ of 1% of total award amount apply
- Core Crew list will be required from successful bidder
- $25.00 per day permit fee for every Non-Indian
- On-site monitoring will be done by TERO
- Certified payroll required
Additional Questions asked during walk-thru
TERO fees-discussed
Asbestos required TERO
$25 per employee per day
Are dump truck drivers considered on site? Yes
Have Inspections been performed on units? Yes
Will it fall under ODOL? Yes
What units with asbestos? #3, #8, and #25
What is the square footage? Approx. 4900 sq. ft.
Do we include in our bid fill for elevation? None needed, enough on the project that can be used to reach required elevation.
Is plumbing going to be capped off? Already has been by the HACN
Sewer or Septic capped off yet? Will be capped off by the Contractor 25 ft. from Main Line
Is demo only required in asbestos? Entire Project will be demo, 3 Asbestos units will be under Wet demo procedures.
Where are the Sewer/Septic lines located coming out of apt. and will we be able to locate? Yes easily when you start. HACN Inspector will assist in locating.
56 calendar days to complete entire project.
Item 20 Payment Phase of Contract will be paid in 3 phases - 30% at 30% complete, 30% at 60% complete and 40% at 100% completion. –With the approval of HACN Inspector.
Wet demo required even if structure appears to be structurally sound? Environmental said wet demo procedures will be used. Pg 29.
Can we bid it either way as long as we do it right? Affirmative Head nod by Rex Jordan as long as you are in ODOL compliance.
Site Inspection
Cutting driveways? Yes, even with the street.
Tin horns come out
Take out trees if they are in the way
Water Lines
Mailbox comes out-slab comes out
Contractor /HACN Inspector will locate the main sewer lines and cap off 25 ft. from main
Certified payroll will be required from General & Sub’s
Require license plumber? HACN states yes or at your own risk. Will be inspected by HACN Inspector.
Gas is all dead.