1

DATEINVERTED INSULATED ROOF WATERPROOFINGPAGE 01

PROJECT: SECTION 001

1 WATERPROOFING

1.1 SUBMITTALS

1.1.1 Product Data: Include physical properties of the specified materials and explanations aboutproduct installation, including installation techniques, restrictions, limitations and manufacturerrecommendations.

1.1.2 Warranty: Certification that all components of the waterproofing assembly are being supplied andwarranted by a single manufacturer. Provide a specimen warranty from the manufacturer that includes all components of the waterproofing installation.

1.1.3 Shop Drawings: Include details for all assemblies. These should include details for walls, curbs,drains, penetrations, edges and expansion/control joints. Include installation details forwaterproofing, flashing, fastening and insulation as applicable.

1.2 QUALITY ASSURANCE

INSTALLER QUALIFICATIONS

1.2.1 The installer shall demonstrate its qualification to perform the work of this section by providingwritten evidence from the manufacturer.

MANUFACTURER QUALIFICATIONS

1.2.2 Shall have a minimum of 30 years experience manufacturing waterproofing membrane systems.

1.2.3 Shall submit a current copy of their ISO 9002 manufacturing certification for the plant wherematerials will be manufactured and shipped from. Additionally, the sequential production log and theISO 9002 production control record documents shall accompany the material shipment and made apermanent part of the job record and warranty file.

1.3 MOCK UP:

1.3.1 Provide a mock-up for evaluation of surface preparation techniques and application workmanship.

1.3.2 Do not proceed with remaining work until workmanship is approved by Architect.

1.4 PRE-INSTALLATION CONFERENCE

1.4.1 Convene no less than five days prior to commencing Work at a time and location to bedetermined.

1.4.2 All parties responsible for Work of this section shall be required to attend including the Architect,Builder, Contractor and any other trades affected by the waterproofing work.

1.4.3 All outstanding issues shall be noted in writing designating the responsible party for follow-upaction and the timetable for completion.

1.4.4 Application of waterproofing system shall not take place until all outstanding issues are resolved

1.5 DELIVERY, STORAGE, AND HANDLING

Deliver materials in original unopened containers of packaging clearly labeled withmanufacturer's name, brand name and all identifying numbers.

1.6 QUALITY CONTROL

1.6.1 Inspection: At a minimum, inspections shall be required at start-up and at intervals ofapproximately 30 percent, 60 percent and 90 percent completion. A final inspection shall berequired.

1.6.2 Warranty shall be issued upon approval of the installation.

1.6.3 A final inspection report from the Technical Representative, certifying that the waterproofingsystem has been satisfactorily installed according to the project specifications, approved details andgood general waterproofing practice, shall be provided.

1.6.4 At all times, the contractor shall permit and facilitate access to the site by the manufacturer'srepresentative.

1.7 SITE PROTECTION

1.7.1 During waterproofing work, exposed surfaces of finished surfaces shall be protected to prevent damage. Contractor shall assume full responsibility for any damage.

1.7.2 The Contractor shall provide for adequate protection of the installed membrane preventingdamage that might arise from work performed by the other trades.

1.7.3 Apply drainage/ protection board/ insulation as soon as possible after membrane installation.

1.8 PROJECT CONDITIONS

Maintain environmental conditions (temperature, humidity, and ventilation) within limits recommended bymanufacturer for optimum results. Do not install products under environmental conditions outsidemanufacturer's absolute limits.

1.9 WARRANTY

The product manufacturer shall issue a written and signed document in the name of the owner,certifying the product will meet all the physical characteristic published by the manufacturer, for aperiod of 20 years, starting from the date of completion of installation of membranes. No letteramending the manufacturer’s standard warranty will be accepted and the warranty certificate mustreflect these requirements.

1.10 MANUFACTURERS/SUPPLIERS

1.10.1 Acceptable Manufacturer: SOPREMA Inc., Melbourne Victoria. Phone: (03) 99383887Fax: (03) 99383899 Web

1.10.2 Licensed / Registered agent: Allduro, which is located in Perth, Western Australia.Tel: (08) 94551658 Fax: (08) 94562079 Email: Web

1.11 PRODUCTS

Soprasun 3.0 S, Soprasun 4.0 F, Elastocol 500 Primer and Sopramastic

1.12 PRODUCTS DESCRIPTION

1.12.1Soprasun 3.0 S is an APP modified thermo fusible waterproof sheet membrane.

1.12.2 Soprasun 4.0 F is an APP modified thermo fusible waterproof sheet membrane with a UV stable mineral surface.

1.12.3 Elastocol 500is a quick drying APP membrane primer.

1.12.4 Sopramastic is solvent based caulking mastic containing modified bitumen, fibres and mineral fillers.

1.13 SYSTEM

One layer of Soprasun 4.0 F cap sheet over one layer of Soprasun 3.0 S base sheet laid over substrate with falls to waste. (Insulation and stone ballast over waterproofing by others)

1.14 SUBSTRATE PREPARATION

1.14.1 GENERAL

Apply insulation covered with geo-textile to architects specification on roof slab. Apply sand cement screed over insulation system to falls min 50mm over. All surfaces should be sound, dry and free from but not limited to, dirt, dust, oil, grease, wax, tar, asphalt, mildew, mould, paint, foreign sealers, coatings, curing agents, loose particles, laitance or any other foreign matter that may impede with the bonding of the primer or membrane.

1.14.2 PRIMING

The screed/substrate to falls is to be primed using Elastocol 500 primer at a rate of 4 to 6 m² per litre.

1.15 MEMBRANE APPLICATION

One layer of Soprasun 3.0 S base sheet is to be fully bonded to the screed/ substrate with 100mm side laps and 150mm end laps fully sealed together with propane torch fusion. This is followed by a layer of Soprasun 4.0 F with side and end laps laid staggered and fully bonded with propane torch to the base layer with side laps of 100mm and end laps of 150mm. (drainage sheet, insulation, geofabric and stone ballast to be placed over waterproofing)