ATC090 10/6/09

Prime Flowdowns for NRO 000-07-C-0372, BITTERN

FAR Clauses

52.227-1, Authorization and Consent (Jul 1995) and Alternate I (Apr 1984) - The basic clause is already called out in Corpdocs, but Alternate I also applies to you if your contract is for research and development.

52.232-17, Interest (Jun 1996) (Applicable for all purchase orders/subcontracts) "Government" means "Lockheed Martin."

52.243-2, Changes – Cost Reimbursement (Aug 1987) and Alternate V – The basic clause is already called out in Corpdocs, but Alternate V also applies if your cost reimbursable contract is for research and development.

52.246-8, Inspection of Research and Development – Cost Reimbursement (May 2001). Applicable if you have a cost reimbursable subcontract and will be performing research and development work.

NRO Clauses

N52.203-001, NRO Inspector General and the NRO Hotline (Aug 2004) – Applicable for all purchase orders/subcontracts over $100,000, except those for commercial items.

N52.203-002, Prohibition on Persons Convicted of Fraud or Other Defense-Contract-Related Felonies (May 2003) – Applicable for all purchase orders/subcontracts over $100,000.

N52.203-003, Personal Conduct (May 2003) – Applicable if you will be performing work on a Government facility.

N52.204-001, Security Requirements (Nov 2007) – Applicable to the extent that any aspect of your contract involves access to Sensitive Compartmented Information (SCI).

N52.209-003, Organizational Conflict of Interest (Aug 2006) – Applicable for all purchase orders/subcontracts.

N52.209-006, Enabling Clause for Prime and Support Contractor Relationships (Aug 2006) – Applicable for all purchase orders/subcontracts, except for procurements for commercial and /or non-developmental items.

N52.211-001, Use of the Metric System of Measurement (Apr 2004) – Applicable for all purchase orders/subcontracts.

N52.211-003, NRO Standards Document Compliance (Jan 2006) – Applicable for all purchase orders/subcontracts.

N52.215-014, Cost Estimating System Requirements (Jan 2005) – Applicable if your contract is for $50 million or more and certified cost or pricing data was required.

N52.219-001, Utilization of Small Business Concerns (Oct 2003) – Applicable if you are a large business and your contract if $500,000 or more.

N52.219-002, Small Business Subcontracting Plan (Aug 2006) – Applicable if you are a large business and your purchase orders/subcontract is over $500,000.

N52.223-006, Contractor Compliance with Environmental, Occupational Safety and Health, and System Safety Requirements (Oct 1997) – Applicable for all purchase orders/subcontracts.

N52.227-002, Rights in Technical Data and Computer Software: Noncommercial Items (Jun 2007) – Applicable for all purchase orders/subcontracts that will be providing noncommercial technical data and/or computer software.

N52.227-003, Validation of Restrictive Markings on Technical Data and Computer Software (Jan 2004) – Applicable for all purchase orders/subcontract that will be providing technical data and/or computer software.

N52.227-007, Rights in Bid or Proposal Information (Jan 2004) – Applicable for all purchase orders/subcontracts.

N52.227-009, Deferred Delivery of Technical Data or Computer Software (May 2005) (Applicable if you will be delivering technical data or computer software under this contract.)

N52.243-003, Request for Equitable Adjustment (Applicable for all purchase orders/subcontracts. “Government” means “Lockheed Martin.”)

N52.244-001, Subcontracts (Educational Institutions) (Applicable if you will be contracting with an educational institution supporting your contract with Lockheed Martin. Request of consent will be communicated through Lockheed Martin to the Contracting Officer.)

N52.244-002, Subcontract Reporting, Monitoring and Consent (Dec 2006) – Applicable for all purchase orders/subcontracts, except those with U.S. owned companies providing only unclassified commercial products or services on a fixed price basis.

N52.245-001, Contract Accountable Government Property (Applicable to all purchase orders/subcontracts. Reporting to the government under this clause shall be through Lockheed Martin. Quarterly reports required under this clause shall be provided to Lockheed Martin by December 1st, March 1st, June 1st and September 1st.)

ATC090 (Rev. 1)