1.Welcome, Call to Order, Introductions

Mr. W. Shannon Black, WECC staff, called the meeting to order at2:00 p.m. on May 25, 2017. A quorum is not required. A list of attendees is attached as Exhibit A.

2.Antitrust Policy

Mr. Black read aloud the WECC Antitrust Policy statement. A link to the posted Policy was provided in the meeting agenda.

3.Approve Agenda

Mr. W. Shannon Black introduced the proposed meeting agenda. The agenda was approved by consensus.

On a standing motion by Mr. David Lemmons the drafting team approved the agenda by consensus.

4.ReviewMinutes

On a standing motion from the drafting team chair, the drafting team approved the minutes from the previous meeting.

5.Review of Previous Action Items

WECC-0127 VAR-002-WECC 2 Request to Retire – Pending WECC Standards Committee approval June 2017

Mr. Israel Perez is a Mechanical Engineer and has worked at Salt River Project (SRP) for over 10 years. The first three years focused on completing numerous engineering projects as a rotational engineer in SRP’s generation fleet.

In 2009, Mr. Perez accepted a permanent position at an SRP generating facility and spent the next six years managing plant overhauls, budgeting contracts & services, and developing to a Senior Engineer position as a Turbine Engineer.

In 2015, Mr. Perez joined SRP’s Electric Reliability Compliance department in the Operations and Planning team. In this position, Mr. Perez is responsible to work with SRP’s responsible departments to ensure compliance with all O&P Reliability Standards.NoneWECC-0125 Governor Droop Five-year Review

6.Drafting

SAR Location and Background

The Standard Authorization Request (SAR) is currently located at the DT’s project page on the SAR Form accordion.

The drafting team reviewed proposed Posting 1 and agreed by consensus to post the document for a 45-day period. Mr. Black briefed the team on possible hurdles when trying to argue that the WECC Standard was not as stringent as the NERC Standard. To be successful the team will need to argue against the arguments made by WECC when the document was first approved by FERC.

The team agreed by consensus to post Posting 1 for a 45-day comment period. The posting would open May 31, 2017 and close July 18, 2017. The team would meet again to answer comments on July 27, 2017 and August 1, 2017, both meeting to run from 10:00 a.m. to 12:00 p.m. (Mountain).

7.Public Comment

All WECC Drafting Team meetings conducted in accordance with the Reliability Standards Development Procedures are open to the public. Public comment is continuously allowed and solicited.

8.Review of New Action Items

  • Mr. Black will post Posting 1.

9.Upcoming Meetings

July 27, 2017, 10:00 a.m. to 12:00 p.m...... Webinar

August 1, 2017, 10:00 a.m. to 12:00 p.m...... Webinar

10.Adjourn

The drafting team meeting was adjourned by consensus without objection.

Exhibit A: Attendance List

Members in Attendance

Todd Komaromy...... Arizona Public Service

David Lemmons...... Ethos Energy

Shane Kronebusch...... Bonneville Power Administration

Israel Perez...... Salt River Project – Pending WSC June 2017

Members not in Attendance

Others in Attendance

W. Shannon Black...... WECC Staff

Charles Tellis...... (No Further Information) NFI

Chris Nebrigich...... NFI

Chuck...... NFI

Greg...... NFI

James Weddell...... NFI

Molly Devine...... NFI

Sean Adkin...... NFI

Toni Orth...... NFI