China: Liaoning Coastal Zone Sustainable Development Project

Procurement Plan – May31, 2016

The procurement plan will cover the whole period of the project implementation. The Project Implementation Agency shall update the procurement plan throughout the duration of the project at least annually by including contracts previously awarded. All procurement plans, their updates or modifications shall be subject to Bank’s prior review and no objection before implementation.

I. General

1. Borrower: The People’s Republic of China

Project Name: Liaoning Coastal Zone Sustainable Development Project

Loan No./Project Code: P126611

Project Implementation Agency (PIA): All procurement of the Project will be carried out by the Provincial Project Management Office (the PMO) and the following Project Implementation Unit (the PIU):

No. / Project City / Main Procurement Activities / Implementation Agency
1 / Donggang / Road CW and equipment procurement / Donggang city Municipal Administration
2 / Kuandian / Road CW and equipment procurement / Kuandian county Urban and RuralConstruction Bureau
3 / Panjin / Road CW and bus procurement / Panjin city Public Transportation Co., LTD
4 / Lingyuan / Road CW and equipment procurement / Lingyuan city Municipal Administration
5 / Lingyuan / CW and equipment procurement of Water subproject / Lingyuan Emergency Water Supply Construction Administration
6 / Liaoning / Consulting service / Liaoning Provincial PMO

2.Updates of Procurement Plan:

No. / Updated date / The main updates
1 / Nov. 2012 / Original procurement plan
2 / 30 Dec 2013 /
  1. The content and contract amount in three civil engineering contract packages of Chaoyang have been adjusted;
  2. The content of Donggang equipment contract has been adjusted;
  3. The vehicle quantity of Panjin equipment contract has changed to 140;
  4. The date of procurement has been changed.

3 / 15 Sep 2014 / Procurement plan of Suizhong county has been terminated
4 / 25 Dec 2014 /
  1. Procurement time has been adjusted
  2. KDRC01 has been opened on Oct.10 2014
  3. LYWC01 has been opened on Dec.11 2014

5 / 25 Jun 2015 /
  1. Procurement plan of Chaoyang City has been terminated
  2. KDRC01 needs to re-tendering
  3. LYWC02 is split into three: LYWC02、LYWC03、LYWC04
  4. Additional Panjin bus equipment procurement package:PJRG02
  5. Additional Lingyuan water equipment procurement package:LYWG02
  6. Purchase amount of LYRG01 has adjusted
  7. Procurement time has been adjusted

6 / Dec.9 2015 /
  1. The amount has been adjusted road maintenance equipment 0f LYRG01 in LingYuan.

7 / Mar.15 2016 /
  1. The amount has been adjusted road construction 0f LYRC01 and LYRC03 in LingYuan.
  2. The amount of KDRC02 contract has been adjusted in Kanduan.
  3. Procurement time has been adjusted.

Note:

A. Suggestion will the road subprojects LYRC03 inLingYuan with its line of small iron bridge as the boundary,the project can be divided into the southern section of BinHe east road and the northern section of BinHe east road, and the southern section of BinHe east road into the road subprojectsLYRC01, mainly based on the following reasons:

a)It’s better to promote the whole project process;

b)Reduce the land demolition and resettlementof the requisition of the capital;

c)The influence of rural land transfer rules.

B.Suggestion will the road subprojects LYRC01 in LingYuan is divided into two parts, the roads and Bridges (means LYRC04) by adding a fourth package, mainly based on the following reasons:

A) It’s better to promote the whole project process;

B) It can be made more professional construction team for the bridge construction of this project;

C) The bridge construction of this project does not involve the land demolition and resettlement;

D) The project total cost too much.

If WB will agreetothe proposal, including the bridge project (total cost $13.1 million)will plan in the tender of the public in December 2016,the road engineering including the southern section of BinHe east road (total cost $7.85 million)will plan in the tender of the public in June 2017.

II. Goods and Works and Non-consulting Services.
  1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement:

Expenditure Category / Contract Value (US$) / Procurement Method / Bank Prior Review
Goods, IT Systems Non-Consulting Services / ≥ 10 million / ICB / All ICB contracts
≥ 500k to
10 million / NCB
Remarks: Where goods are not normally available from within China, the method of procurement will be ICB even if the contract value is less than USD 10 million. / First NCB goods contract by each PMO irrespective of value and all contracts ≥ USD 3 million.
500 K / Shopping / None
N/A / DC / All contracts ≥ USD 200k.
Works, Supply & Installation / ≥ 40 million / ICB / All ICB contracts
≥ 500k to
40 million / NCB / First NCB works contract by each PMO irrespective of value and all contracts ≥ USD 15 million.
500 K / Shopping / None
N/A / DC / All contracts ≥ USD 200k.
Notes: / ICB: International Competitive Bidding
NCB: National Competitive Bidding / DC: Direct Contracting
NA: Not Applicable

2.Prequalification.Bidders for all ICB works contracts shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines.

3.Proposed Procedures for CDD Components (as per paragraph. 3.19 of the Guidelines: NA.

  1. Reference to (if any) Project Operational/Procurement Manual: The PMO has prepared a procurement management manual, which has been reviewed by the Bank.

5. Any Other Special Procurement Arrangements: Retroactive financing will be agreed under this project. All advance contracts are subject to Bank’s prior review. Payments will be made only for contracts procured in accordance with applicable Bank procurement procedures.

III. Selection of Consultants
  1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants:

Expenditure Category / Contract Value (US$) / Selection Method / Bank Prior Review
Consultants / ≥ 300,000 / QCBS, QBS / Firms: First contract for each selection method and all contracts ≥ USD 1 million;
Firms: All SSS contracts ≥ USD 100 K;
Individual Consultant: Only in Exceptional Cases;
SSS for individual consultant: ≤ USD 50 K
< 300,000 / QCBS, QBS, CQS
N/A / SSS
N/A / IC
All terms of references (TOR) will be reviewed by the Bank Task Team regardless of the contract value
Notes: / QCBS: Quality- and Cost-Based Selection
QBS: Quality-Based Selection
CQS: Selection Based on the Consultants’ Qualifications / SSS: Single-Source Selection
IC: Individual Consultant selection procedure
NA: Not Applicable
  1. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD500, 000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.
  1. Any Other Special Selection Arrangements: Retroactive financing will be agreed under this project. All advance contracts are subject to Bank’s prior review. Payments will be made only for contracts procured in accordance with applicable Bank procurement procedures.

1 / 7

Procurement Packages with Methods and Time Schedule

Procurement of Civil WorksNote: Exchange Rate 1USD=6.25CNY

Contract
(Description) / ProcurementMethod / Review
Bank / Planned/
Actual / Cost
(USD M) / Bid Starting
(YY/MM/DD) / Bid Opening
(YY/MM/DD) / Contract Signing
(YY/MM/DD) / Contract Period
(Months)
A. Urban road
A1. Dongang road network project
DGRC01. Zhanqiandadao Avenue Road and ancillary infrastructure / NCB / Prior / Planned / 10.67 / 2015/2 / 2015/3 / 2015/5 / 18
Actual / 11.99 / 2015/3 / 2015/4/15 / 2015/8/5 / 14
DGRC02. Haiguanbeilu and Gaotiedajie and ancillary infrastructure / NCB / Post / Planned / 14.90[1] / 2016/2 / 2016/4 / 2016/6 / 18
Actual
DGRC03. Hengyi, Henger, Hengsan Roads and ancillary infrastructure / NCB / Post / Planned / 13.62 / 2016/6 / 2016/8 / 2016/10 / 16
Actual
A2. Kuandian urban roads rehabilitation
KDRC01. Urban roads rehabilitation and ancillary infrastructure (Package 1) CANCELED / NCB / Prior / Planned / --- / --- / --- / --- / 24
Actual / 6.88 / 2014/9 / 2014/10/10 / 2015/2/2 / Terminated
KDRC01B Urban roads rehabilitation and ancillary infrastructure (Package 1 rebidding) / NCB / Prior / Planned / 6.88 / 2015/9 / 2015/11 / 2016/1 / 24
Actual / 7.84 / 2015/10/10 / 2015/11/10 / 2016/3/3 / 18
KDRC02. Urban roads rehabilitation and ancillary infrastructure (Package 2) / NCB / Post / Planned / 11.81 / 2015/12 / 2016/2 / 2016/4 / 18
Actual / 4.00 / 2015/12 / 2016/4/21 / 18
A3. Lingyuan road infrastructure
LYRC01. Wenyi Road and ancillary infrastructure / NCB / Post / Planned / 9.47 / 2017/6 / 2017/7 / 2017/8 / 24
Actual
LYRC02. Wuliudalu Road and ancillary infrastructure / NCB / Prior / Planned / 8.781 / 2015/2 / 2015/3 / 2015/5 / 22
Actual / 4.15 / 2015/7/28 / 2015/8/27 / 2015/11/16 / 18
LYRC03. Binhedong Road and ancillary infrastructure / NCB / Post / Planned / 6.4 / 2016/7 / 2016/9 / 2016/11 / 18
Actual
LYRC04:Wenyi Bridge and ancillary infrastructure / NCB / Post / Planned / 13.6 / 2016/12 / 2016/12 / 2017/1
Actual
A5. Panjin bus transportation
PJRC01. Shuangtaizi District bus depot and maintenance facilities / NCB / Prior / Planned / 2.281 / 2014/12 / 2015/1 / 2015/3 / 12
Actual / 2.38 / 2014/12/23 / 2015/2/4 / 2015/6/26 / 18
PJRC02. Xinglongtai District bus depot and maintenance facilities / NCB / Post / Planned / 3.87 / 2016/12 / 2017/1 / 2017/2 / 18
Actual
B.Urban drainage and water reuse project
B1. Lingyuan recycled water project
LYWC01. Sewage and reclaimed water pipelines along Daling River, including primary pumping station / NCB / Prior / Planned / 13.44 / 2014/10 / 2014/12 / 2015/2 / 30
Actual / 8.32 / 2014/11 / 2014/12/11 / 2015/5/25 / 24
LYWC02. Reclaimed water, sewage and drainage pipeline along Lingre Pipeline / NCB / Post / Planned / 5.6 / 2015/9 / 2015/11 / 2015/12 / 12
Actual / 7.71 / 2015/10/12 / 2015/11/12 / 2016/3/9 / 18
LYWC03. Reclaimed water, sewage and drainage pipeline along Lao Kuan Road and main roads in Industrial Park, including secondary pumping station / NCB / Post / Planned / 6.36 / 2016/7 / 2016/8 / 2016/10 / 12
Actual
LYWC04. Reclaimed water, sewage and drainage pipeline along secondary roads in Industrial Park / NCB / Post / Planned / 5.36 / 2016/9 / 2016/10 / 2016/12 / 12
Actual

PS: No Pre-Qualification and Domestic Preference for all civil works.

Procurement of Goods

Contract
(Description) / ProcurementMethod / Review
Bank / Domestic Preference / Planned/
Actual / Cost
(USD M) / Bid Starting
(YY/MM/DD) / Bid Opening
(YY/MM/DD) / Contract Signing
(YY/MM/DD) / Contract Period
(Months)
A.Urban roads
A1. Dongang road network project
DGRG01. Road maintenance equipment for Dongang / ICB / Prior / Yes / Planned / 1.91 / 2016/7 / 2016/9 / 2016/12 / 1.91
Actual
A2. Kuandian urban road rehabilitation
KDRG01. Traffic signaling and road maintenance equipment for Kiuandian / ICB / Prior / No / Planned / 3.97 / 2015/10 / 2015/12 / 2016/6 / 12
Actual / 2015/12/9 / 2016/2/24
A3. Lingyuan road infrastructure
LYRG01. Road maintenance equipment for Lingyuan / ICB / Prior / No / Planned / 1.81 / 2016/8 / 2016/10 / 2017/2 / 6
Actual
A5. Panjin bus transportation
PJRG01. Acquisition of 140 LNG buses. / ICB / Prior / Yes / Planned / 16.32 / 2015/2 / 2015/3 / 2015/5 / 6
Actual / 15.74 / 2015/6 / 2015/9/9 / 2016/2/23 / 6
PJRG02. Road maintenance equipment for Panjin / NCB / Prior / No / Planned / 0.96 / 2016/7 / 2016/9 / 2016/11 / 6
Actual
B. Urban drainage and water reuse project
B1. Lingyuan recycled water project
LYWG01. Equipment for primary and secondary pumping stations / NCB / Prior / No / Planned / 0.79 / 2015/10 / 2015/12 / 2016/2 / 12
Actual / 2016/1 / 2016/3/1
LYWG02. Water pipeline maintenance equipment / Shopping / Post / No / Planned / 0.37 / 2016/12 / 2017/2 / 2017/4 / 12
Actual

PS: No Pre-Qualification for all Goods.

Procurement Consulting Services

Contract
(Description) / SelectionMethod / Review
Bank / Planned/
Actual / Cost
(USD M) / Proposal Submission / Contract Signing / Contract Period
(Months)
CS1. Project management consulting services / QCBS / Prior / Planned / 1.15 / 2014/3 / 2014/6 / 60
Actual / 1.09 / 2014/3 / 2014/8/20 / 60
CS2. Asset Management / CQS / Prior / Planned / 0.25 / 2016/12 / 2016/12 / 12
Actual
CS3. Traffic Management / CQS / Post / Planned / 0.25 / 2016/12 / 2016/12 / 12
Actual

1 / 7

[1]DGRC02的合同额预算临近前后审分界线(1500万美元)。