WEST VIRGINIA DEPARTMENT OF TRANSPORTATION
DIVISION OF HIGHWAYS
ALL ITEMS MUST BE COMPLETED BY CONTRACTOR
CALL NUMBER
CONTRACTOR’S NAME
CONTRACTOR’S FEIN
BID AMOUNT
DBE GOAL (%)
WV LICENSE NUMBER
CONTRACTOR’S PROPOSAL
CONTRACT ID 0003164
COUNTY LINCOLN
NAME OF PROJECT BIG UGLY BRIDGE
PROJECT NUMBER S322-7-3.12 00 STP-0007(166)D
BIDS TO BE RECEIVED UNTIL 10 0’CLOCK A.M. (DATE) AT
THE OFFICE OF THE DIVISION OF HIGHWAYS, CONTRACT ADMINISTRATION
DIVISION, ROOM A-748, BUILDING 5, STATE CAPITOL COMPLEX, CHARLESTON,
WEST VIRGINIA.
NOTICE TO CONTRACTORS
PAPER BID SUBMISSIONS WILL NO LONGER BE ACCEPTED AND ALL
BIDS MUST BE SUBMITTED ELECTRONICALLY VIA THE INTERNET
THROUGH BID EXPRESS.
UNCOMPLETED WORKLOAD
PAGE 1 OF 1, UNCOMPLETED WORKLOAD, MUST BE SUBMITTED TO THE CONTRACT ADMINISTRATION
DIVISION ONE WEEK PRIOR TO THE DESIGNATED BID LETTING DATE IF OVER THE PREQUAILIFED
AMOUNT.
E-MAIL: , , and
Proposal ID: 0003164 State Project Number: S322-7-3.12 00
Federal Project Number: STP-0007(166)D
SECTION: 0001 GRADE, DRAIN & PAVE
Alt Set ID: Alt Mbr ID:
Unit Price Bid Amount Approximate
Quantity and Description Units
Item ID
Proposal
Line
Number Dollars Cents Dollars Cents
0005 201001-000
CLEARING AND GRUBBING LUMP SUM LUMP SUM ______._____
0010 204001-000
MOBILIZATION LUMP SUM LUMP SUM ______._____
0015 207001-001
UNCLASSIFIED EXCAVATION CY
1,213.000
______.______._____
0020 207002-000
SUBGRADE CY
346.000
______.______._____
0025 207034-000
FABRIC FOR SEPARATION SY
670.000
______.______._____
0030 211001-000
UNCLASSIFIED BORROW
EXCAVATION
CY
429.000
______.______._____
0035 211002-000
ROCK BORROW EXCAVATION CY
24.000
______.______._____
0040 307001-000
AGGREGATE BASE COURSE, CLASS
1
CY
312.000
______.______._____
0045 307001-000
AGGREGATE BASE COURSE, CLASS
10
CY
12.000
______.______._____
0050 502001-012
12 INCH PORTLAND CEMENT
CONCRETE APPROACH SLAB
SY
171.000
______.______
0055 604076-010
12 INCH ALUMINUM COATED
CORRUGATED STEEL PIPE, A2
LF
33.000
______.______._____
0060 607001-001
TYPE 1 GUARDRAIL, CLASS II LF
400.000
______.______._____
0065 607006-001
THRIE BEAM GUARDRAIL BRIDGE
TRANSITION
EA
4.000
______.______._____
0070 622003-001
CANTILEVER MAILBOX SUPPORT EA
1.000
______.______._____
0075 636005-001
TEMPORARY STRUCTURE FOR
MAINTAINING TRAFFIC
LUMP SUM LUMP SUM ______._____
0080 636007-001
ERADICATION OF PAVEMENT
MARKING
LF
1,000.000
______.______._____
0085 636008-001
TEMPORARY PAVEMENT
MARKING-PAINT 4 IN
LF
1,500.000
______.______._____
0090 636011-001
TRAFFIC CONTROL DEVICE UN
7,080.000
______.______._____
0095 636012-010
PROJECT TRAFFIC CONTROL
DEVICE CLEANING
EA
2.000
______.______._____
0100 636013-001
INDIVIDUAL TRAFFIC CONTROL
DEVICE CLEANING
EA
50.000
______.______._____
0105 636014-001
FLAGGER HR
300.000
______.______.____
0110 636025-001
WARNING LIGHTS, TYPE B DA
1,200.000
______.______._____
0115 638002-001
RIGHT OF WAY MARKER EA
6.000
______.______._____
0120 638004-001
OUTLET MARKER EA
1.000
______.______._____
0125 639001-001
CONSTRUCTION LAYOUT STAKE LUMP SUM LUMP SUM ______._____
0130 640003-001
BUILDING EQUIPMENT LUMP SUM LUMP SUM ______._____
0135 640006-001
SMALL FIELD OFFICE MO
6.000
______.______._____
0140 642004-001
SEED MIXTURE, TEMPORARY LB
16.000
______.______._____
0145 642004-003
SEED MIXTURE, D LB
22.000
______.______._____
0150 642005-001
MULCH, STRAW OR HAY TN
0.600
______.______._____
0155 642006-001
FERTILIZER TN
0.100
______.______._____
0160 642010-001
AGRICULTURAL LIMESTONE TN
0.500
______.______._____
0165 642012-001
SILT FENCE LF
400.000
______._
0170 652001-001
AGRICULTURAL LIMESTONE TN
0.200
______.______._____
0175 652002-001
FERTILIZER, 10-20-10 TN
0.100
______.______._____
0180 652003-002
SEED MIXTURE, D LB
11.000
______.______._____
0185 652004-001
STRAW OR HAY MULCH TN
0.320
______.______._____
0190 663001-004
EDGE LINE, TYPE II - 4 IN WHITE LF
750.000
______.______._____
0195 663002-038
CENTERLINE, TYPE II - 4 IN LF
750.000
______.______._____
0200 401001-020
AA MARSHALL HMA BASE CRSE, SG, TY I
1
TN
127.000
______.______._____
0205 401001-021
AA MARSHALL HMA BASE CRSE, S, TY I
2
TN
121.000
______.______._____
0210 401001-030
MARSHALL WMA BASE CRSE, SG, TY
I
AA
3
TN
127.000
______.______._____
0215 401001-031
AA MARSHALL WMA BASE CRSE, S, TY I
4
TN
121.000
______.______._____
0220 402001-020
BB MARSHALL HMA SKID PVT, SG, TY I
1
TN
55.000
______.______._____
0225 402001-021
BB MARSHALL HMA SKID PVT, S, TY I
2
TN
53.000
______.______._____
0230 402001-029
BB MARSHALL WMA SKID PVT, SG, TY I
3
TN
55.000
______.______._____
0235 402001-030
BB MARSHALL WMA SKID PVT, S, TY I
4
TN
53.000
______.______._____
Section: 0001 Total: ______._____
0240 203001-000
DISMANTLING STRUCTURE LUMP SUM LUMP SUM ______._____
0245 212001-000
STRUCTURE EXCAVATION CY
215.000
______.______._____
0250 212005-000
SELECT MATERIAL FOR
BACKFILLING
CY
49.000
______.______._____
0255 218006-000
FOUNDATION PROTECTION CY
345.000
______.______._____
0260 601002-001
CLASS B CONCRETE CY
64.000
______.______._____
0265 601003-001
CLASS K CONCRETE CY
19.000
______.______._____
0270 601009-001
CLASS H CONCRETE CY
97.000
______.______._____
0275 602002-001
EPOXY COATED REINFORCING
STEEL BAR
LB
33,002.000
______.______._____
0280 615001-001
STEEL SUPERSTRUCTURE LUMP SUM LUMP SUM ______._____
0285 616005-018
HP14X73 STEEL BEARING PILE,
PRE-DRILLED AND DRIVEN
LF
214.000
______.______._____
0290 639001-001
CONSTRUCTION LAYOUT STAKE LUMP SUM LUMP SUM ______._____
Section: 0002 Total: ______._____