WEST VIRGINIA DEPARTMENT OF TRANSPORTATION

DIVISION OF HIGHWAYS

ALL ITEMS MUST BE COMPLETED BY CONTRACTOR

CALL NUMBER

CONTRACTOR’S NAME

CONTRACTOR’S FEIN

BID AMOUNT

DBE GOAL (%)

WV LICENSE NUMBER

CONTRACTOR’S PROPOSAL

CONTRACT ID 0003164

COUNTY LINCOLN

NAME OF PROJECT BIG UGLY BRIDGE

PROJECT NUMBER S322-7-3.12 00 STP-0007(166)D

BIDS TO BE RECEIVED UNTIL 10 0’CLOCK A.M. (DATE) AT

THE OFFICE OF THE DIVISION OF HIGHWAYS, CONTRACT ADMINISTRATION

DIVISION, ROOM A-748, BUILDING 5, STATE CAPITOL COMPLEX, CHARLESTON,

WEST VIRGINIA.

NOTICE TO CONTRACTORS

PAPER BID SUBMISSIONS WILL NO LONGER BE ACCEPTED AND ALL

BIDS MUST BE SUBMITTED ELECTRONICALLY VIA THE INTERNET

THROUGH BID EXPRESS.

UNCOMPLETED WORKLOAD

PAGE 1 OF 1, UNCOMPLETED WORKLOAD, MUST BE SUBMITTED TO THE CONTRACT ADMINISTRATION

DIVISION ONE WEEK PRIOR TO THE DESIGNATED BID LETTING DATE IF OVER THE PREQUAILIFED

AMOUNT.

E-MAIL: , , and

Proposal ID: 0003164 State Project Number: S322-7-3.12 00

Federal Project Number: STP-0007(166)D

SECTION: 0001 GRADE, DRAIN & PAVE

Alt Set ID: Alt Mbr ID:

Unit Price Bid Amount Approximate

Quantity and Description Units

Item ID

Proposal

Line

Number Dollars Cents Dollars Cents

0005 201001-000

CLEARING AND GRUBBING LUMP SUM LUMP SUM ______._____

0010 204001-000

MOBILIZATION LUMP SUM LUMP SUM ______._____

0015 207001-001

UNCLASSIFIED EXCAVATION CY

1,213.000

______.______._____

0020 207002-000

SUBGRADE CY

346.000

______.______._____

0025 207034-000

FABRIC FOR SEPARATION SY

670.000

______.______._____

0030 211001-000

UNCLASSIFIED BORROW

EXCAVATION

CY

429.000

______.______._____

0035 211002-000

ROCK BORROW EXCAVATION CY

24.000

______.______._____

0040 307001-000

AGGREGATE BASE COURSE, CLASS

1

CY

312.000

______.______._____

0045 307001-000

AGGREGATE BASE COURSE, CLASS

10

CY

12.000

______.______._____

0050 502001-012

12 INCH PORTLAND CEMENT

CONCRETE APPROACH SLAB

SY

171.000

______.______

0055 604076-010

12 INCH ALUMINUM COATED

CORRUGATED STEEL PIPE, A2

LF

33.000

______.______._____

0060 607001-001

TYPE 1 GUARDRAIL, CLASS II LF

400.000

______.______._____

0065 607006-001

THRIE BEAM GUARDRAIL BRIDGE

TRANSITION

EA

4.000

______.______._____

0070 622003-001

CANTILEVER MAILBOX SUPPORT EA

1.000

______.______._____

0075 636005-001

TEMPORARY STRUCTURE FOR

MAINTAINING TRAFFIC

LUMP SUM LUMP SUM ______._____

0080 636007-001

ERADICATION OF PAVEMENT

MARKING

LF

1,000.000

______.______._____

0085 636008-001

TEMPORARY PAVEMENT

MARKING-PAINT 4 IN

LF

1,500.000

______.______._____

0090 636011-001

TRAFFIC CONTROL DEVICE UN

7,080.000

______.______._____

0095 636012-010

PROJECT TRAFFIC CONTROL

DEVICE CLEANING

EA

2.000

______.______._____

0100 636013-001

INDIVIDUAL TRAFFIC CONTROL

DEVICE CLEANING

EA

50.000

______.______._____

0105 636014-001

FLAGGER HR

300.000

______.______.____

0110 636025-001

WARNING LIGHTS, TYPE B DA

1,200.000

______.______._____

0115 638002-001

RIGHT OF WAY MARKER EA

6.000

______.______._____

0120 638004-001

OUTLET MARKER EA

1.000

______.______._____

0125 639001-001

CONSTRUCTION LAYOUT STAKE LUMP SUM LUMP SUM ______._____

0130 640003-001

BUILDING EQUIPMENT LUMP SUM LUMP SUM ______._____

0135 640006-001

SMALL FIELD OFFICE MO

6.000

______.______._____

0140 642004-001

SEED MIXTURE, TEMPORARY LB

16.000

______.______._____

0145 642004-003

SEED MIXTURE, D LB

22.000

______.______._____

0150 642005-001

MULCH, STRAW OR HAY TN

0.600

______.______._____

0155 642006-001

FERTILIZER TN

0.100

______.______._____

0160 642010-001

AGRICULTURAL LIMESTONE TN

0.500

______.______._____

0165 642012-001

SILT FENCE LF

400.000

______._

0170 652001-001

AGRICULTURAL LIMESTONE TN

0.200

______.______._____

0175 652002-001

FERTILIZER, 10-20-10 TN

0.100

______.______._____

0180 652003-002

SEED MIXTURE, D LB

11.000

______.______._____

0185 652004-001

STRAW OR HAY MULCH TN

0.320

______.______._____

0190 663001-004

EDGE LINE, TYPE II - 4 IN WHITE LF

750.000

______.______._____

0195 663002-038

CENTERLINE, TYPE II - 4 IN LF

750.000

______.______._____

0200 401001-020

AA MARSHALL HMA BASE CRSE, SG, TY I

1

TN

127.000

______.______._____

0205 401001-021

AA MARSHALL HMA BASE CRSE, S, TY I

2

TN

121.000

______.______._____

0210 401001-030

MARSHALL WMA BASE CRSE, SG, TY

I

AA

3

TN

127.000

______.______._____

0215 401001-031

AA MARSHALL WMA BASE CRSE, S, TY I

4

TN

121.000

______.______._____

0220 402001-020

BB MARSHALL HMA SKID PVT, SG, TY I

1

TN

55.000

______.______._____

0225 402001-021

BB MARSHALL HMA SKID PVT, S, TY I

2

TN

53.000

______.______._____

0230 402001-029

BB MARSHALL WMA SKID PVT, SG, TY I

3

TN

55.000

______.______._____

0235 402001-030

BB MARSHALL WMA SKID PVT, S, TY I

4

TN

53.000

______.______._____

Section: 0001 Total: ______._____

0240 203001-000

DISMANTLING STRUCTURE LUMP SUM LUMP SUM ______._____

0245 212001-000

STRUCTURE EXCAVATION CY

215.000

______.______._____

0250 212005-000

SELECT MATERIAL FOR

BACKFILLING

CY

49.000

______.______._____

0255 218006-000

FOUNDATION PROTECTION CY

345.000

______.______._____

0260 601002-001

CLASS B CONCRETE CY

64.000

______.______._____

0265 601003-001

CLASS K CONCRETE CY

19.000

______.______._____

0270 601009-001

CLASS H CONCRETE CY

97.000

______.______._____

0275 602002-001

EPOXY COATED REINFORCING

STEEL BAR

LB

33,002.000

______.______._____

0280 615001-001

STEEL SUPERSTRUCTURE LUMP SUM LUMP SUM ______._____

0285 616005-018

HP14X73 STEEL BEARING PILE,

PRE-DRILLED AND DRIVEN

LF

214.000

______.______._____

0290 639001-001

CONSTRUCTION LAYOUT STAKE LUMP SUM LUMP SUM ______._____

Section: 0002 Total: ______._____