WECC-0110 Posting 1 INT-011-WECC-CRT-3 Final for Ballot

WECC-0110 Posting 1 INT-011-WECC-CRT-3 Final for Ballot

Ten-Minute Recallable e-Tag Functionality for Operating Reserves – Supplemental

INT-011-WECC-CRT-3

Document name / Ten-Minute Recallable e-Tag Functionality for Operating Reserves – Supplemental
INT-011-WECC-CRT-3
WECC Regional Criterion
Category / ( )Regional Reliability Standard
(X)Regional Criterion
( )Policy
( )Guideline
( )Report or other
( )Charter
Document date
Adopted/approved by
Date adopted/approved
Custodian (entity responsible for maintenance and upkeep) / Standards
Stored/filed / Approved Regional Criteria
Previous name/number / On September 5, 2012, the WECC Board of Directors (Board) changed the designation from “CRT” to “RBP.”
On June 25, 2014, the Board changed the designation from “RBP” to “CRT.”
This document retires INT-011-RBP-1.
Status / ( ) in effect as of June 12, 2013
( ) usable, minor formatting/editing required
( ) modification needed
( ) superseded by ______
( ) other ______
( ) obsolete/archived)

Version Control

Version / Date / Action / Change
1 / 3/6/08 / Approved by the Operating Committee
1 / 8/31/09 / Converting current approved Business Practice (INT-BPS-011-1) into new Regional Criterion format – no other changes are being submitted. / No other change
2 / 9/5/12 / “Criterion” changed to “Regional Business Practice” designation / No other change
2 / 3/13/2013 / WECC Board of Directors (Board) approved / Redraft as part of the INT Rewrite Project
2 / 6/25/2014 / Board designated this document as a Regional Criterion. / Designation change
3 / 6/24/2015 / Board approved / Align the INT with BAL-002-WECC-2, Contingency Reserve

Project Roadmap

This section is maintained by the drafting team, is subject to change, and will be removed after final approval. Future dates are a projection and are only advisory.

Completed Actions / Completion Date
  1. SAR Filed
/ 7-29-2014
  1. WSC approved the SAR
/ 8-5-2014
  1. DT solicitation notice dispatched
/ 8-15-2014
  1. Notice of DT Assignment
/ 9-29-2014
  1. Posting 1 Comments Open
/ 12-5-2014
  1. Posting 1 Comments Closed (45-day)
/ 1-19-2015
  1. DT Meets to answer Comments
/ 1-27-2015
  1. WSC approves for ballot
/ 2-4-2015
  1. Notice of Standards Briefing
/ 2-6-2015
  1. Standards Briefing
/ 2-25-2015
  1. Notice of Ballot Pool Forming
/ 3-4—2015
  1. Ballot Pool – Open
/ 3-5-2015
  1. Ballot Pool – Closed
/ 3-24-2015
  1. Ballot Opens
/ 3-31-2015
  1. Ballot Closes
/ 4-22-2015
  1. WSC approves forwarding document to the WECC Board of Directors
/ 5-19-2015
  1. Notice to WECC Board of Directors (NLT)
/ 5-21-2015
  1. WECC Board of Directors
/ 6-24-2015
  1. Effective Date
/ 10-1-2015

Developed as WECC-0110; prior designation WECC-0079Page 1

Ten-Minute Recallable e-Tag Functionality for Operating Reserves – Supplemental

INT-011-WECC-CRT-3

A. Introduction

1. Title:Ten-Minute Recallable e-Tag Functionality for Operating Reserves – Supplemental

WECC Regional Criterion

2.Number:INT-011-WECC-CRT-3

3.Purpose:To define the use of ten-minute recallable e-Tags as Operating Reserve - Supplemental

4.ApplicabilityThis document applies only to those entities whose market rules allow for ten-minute recallable transactions.

4.1.Balancing Authority

4.2.Purchasing-Selling Entity

5. Effective Date: The first day of the second quarter following approval by the WECC Board of Directors

B.Requirements

WR1.Each Purchasing-Selling Entity (tag author) submitting a Request for Interchange (RFI) for ten-minute recallable transactions for Operating Reserves – Supplemental shall specify each of the following:

1)Transaction type option set to “recallable”;

2)Both the source point and sink point are located within the Western Interconnection;

3)Energy product type option set to “C-RE”.

WM1. Each Purchasing-Selling Entity (tag author) submitting a Request For Interchange (RFI) for ten-minute recallabletransactions for Operating Reserve – Supplemental will have evidence that it specified in the Request For Interchange (RFI) each of the items as required in Requirement WR1.

WR2. Each Purchasing-Selling Entity and each Source Balancing Authority that activates ten-minute recallable transactions for Operating Reserve – Supplemental shall submit a downward e-Tag market level profile adjustment that includes each of the following characteristics:

1)A start time that is no earlier than ten minutes prior to the submittal time.

2)A default start time ramp duration of zero minutes.

WM2. Each Purchasing-Selling Entity and each Source Balancing Authority thatsubmits an adjustment to a ten-minuterecallabletransactions for Operating Reserve – Supplemental will have evidence that it submitted a downward e-Tag market level profile adjustment for that activation and that the e-Tag included each of the characteristics required in Requirement WR2.

WR3.Each Source Balancing Authority and each Sink Balancing Authority that receives a downward adjustment request for a ten-minute recallable transaction shall approve the request.

WM3. Each Source Balancing Authority and each Sink Balancing Authority that receives a downward adjustment request for a ten-minute recallable transaction will have evidence that, upon receipt of a downward e-Tag market profile adjustment for ten minute recallabletransactions, it approved the request as required in Requirement WR3.

For purposes of proving compliance with Requirement WR3, if an entity has not received such a request, the entity shall certify in writing that no such requests were received.

Guidance Section

WR1 instructseach Purchasing-Selling Entity (tag author) on what informationis needed to indicate that the Request for Interchange (RFI) is a ten-minute recallable transaction for Operating Reserves – Supplemental.

WR2 recognizes that the Purchasing-Selling Entity (tag author) or the Source Balancing Authority may request an adjustment to the market level profile of a ten minute recallable transaction for Operating Reserve – Supplemental.

WR3 ensures that the adjustmentsto ten-minute recallable transactions are approved.

Developed as WECC-0110; prior designation WECC-0079Page 1