LMC Task List for Monday November 7th, 2016

  1. Install rollers on Gate #5
  2. Remove piano wire and brackets on Gate #5
  3. Install handrail on STA 2+22
  4. Remove scaffold from Gate#5
  5. Formwork at plunge pool & penstock
  6. Pour concrete at plunge pool @ 1:30 pm
  7. Install anchors for pipe support on gatehouse
  8. Strip forms on plunge pool footing

TET workers notified me of a potential asbestos hazard on site. An old pipe which may or may not contain asbestos in its insulated wrapping was found outside the generating plant. I asked the NB Power operations manager on site at the time if he was aware whether or not the pipe wrapper contained asbestos. As we were not 100% sure without analysis, he contacted George Kelly who called Peter White to come and test the pipe insulation. The pipe is currently marked off with red tape and tagged as potential asbestos hazard until a determination can be made.

Monitored the concrete pour from 1:30pm to 3:00 pm. One truckload of concrete was delivered and used on siteusing a boom and concrete box for extra-controlled pouring. No spillage.

LMC Task List November 8th, 2016

  1. Scaffold mod for ED at pipe support.
  2. Bathymetry survey @ 11:00 am
  3. Drainage pipe on plunge pool footing
  4. Remove scaffold from Gate#5
  5. Formwork @ penstock
  6. Remove Anchor templates + zip cut k-bolt anchors
  7. Install Anchors for pipe support on gatehouse

Monitored the bathymetry survey from on top of the gate structure. I noticed a small paint slick in the water from drips of heavy spray paint. Painting of some grating which was being done by NB Power had dripped down into water and was being contained by the logs below. I notified the operators and they took immediate action by absorbing it with an absorption sock attached to a rope and pole.

LMC Task List November 9th, 2016

  1. Remove whalers from plunge pool
  2. Drainage pipe on plunge pool footing
  3. Remove scaffold from Gate#5
  4. Formwork at penstock
  5. Remove anchor templates + zipcut + k-bolt
  6. Install Anchors for pipe support on gatehouse
  7. Remove lashing on Gate#5

Weekly meeting discussed the concrete pour to take place on Tuesday from the bridge. Should be all done pouring concrete by the end of the month. Excavation at parking lot for burial of concrete will be monitored.