The underlying impact of change orders on labor productivity

Tracking labor productivity is crucial for the success of construction projects. Generally, the project duration relies on productivity. Change orders are common practice during construction. Because each project is unique, change orders are[N1] mainly result from defective engineering drawings along with others[N2] factors. These changes make disruptions on[N3] the project. There are three pioneered[N4] published studies assessing the cumulative impact of change orders on the[N5] labor productivity. Yet, these studies did not address two important element: change time, and calculating extra working hours. Currently, these studies are the base of contractor argument to accuse the owner for productivity loss claim. The first study (Leonard)[N6] was the bedrock of the other studies. This article will review each study and indicate its limitation.

The first study was conducted by Leonard is 1988 in Canada. He investigated 57 different projects on both commercial and institutional buildings. According to Leonard, he defined multitude impact of change orders as “Generally delays and disruptions caused by change orders were found to bring about gradual deterioration of the contractor’s planning and scheduling. Orderly sequences of operations were divided into several, perhaps isolated, activities completed in piecemeal fashion over an extended period.” The impact of change on labor productivity in Leonard’s study are[N7] summarized as: re-sequencing of work, trade stacking, overtime, material sourcing problems, weather conditions, labor problems, low morale, shift work and the need for schedule compression (acceleration). Leonard calculated the productivity index, which is generally agreed between researchers as a measurement of lost productivity. He found that cumulative change orders are associated with labor productivity lost. He also discovered that the loss of productivity would increase as the cumulative change orders are accompanied by another factors, such as inclement weather or overmanning (Leonard). Leonard’s data was collected from projects that reached dispute level. It is worthwhile to mention that all Leonard’s projects were Canadian; therefore, Leonard’s model is not reliable to be applied in different weather conditions. This study was the first, which connected change orders with productivity loss quantitatively.

A study was conducted under the supervision of the Construction Industry institute[N8] by Ibbs and Allen. This study showed that productivity loss because of change orders is less than Leonard’s figures. They studied 104 projects, both domestically and internationally. In addition, their data included industrial, commercial, and heavy civil projects. They compared the effect of cumulative change orders on civil/architectural and mechanical/electrical. They found that there is not a distinction on the basis of type of trade. The authors defined the percent change as “the number of work-hours expended on authorized changes that originated during the construction phase divided by the total number of work-hours expended for construction.” (Ibbs and Allen). The study was general, and it is difficult to file a productivity loss claim based on the study.

In 1999, Hanna investigated the impact of changes orders on mechanical and electrical projects. The values of the examined projects were between $61,000 and $13, 6000,000. He found that the percent change calculated by dividing change order hours over the estimated contract base hours is more significant than what had been performed by Leonard, Ibbs and Allen. He introduced two empirical formulas for each trade (Hanna). It is not reliable to depend on the project estimation as a base in finding insufficient working hours. In addition, the projects that Hanna studied were limited to only two trades.

The findings of the three studies are restricted to calculating the percent loss due to cumulative impact of change orders. They evaluated the impact on each trade, and concluded that change orders hurt labor productivity drastically. The findings of this study[N9] have a number of important implications for future practice such as arbitration and mediation the productivity loss, and awarding the contractor extra time and compensation for the damages cause by such changes. Further work needs to be done to establish whether the time of change has an effect on the productivity loss figure or not. In addition, future field investigations are needed to estimate the extra working insufficient hours.[N10]

Work [N11]Cited

Leonard, C A. "The Effect of Change Orders on Productivity." The Revay Report 6.2 (1987): N. pag. Web. Spring .

Ibbs, C W., and W E. Allen. "Quantitative Impacts of Project Change." Construction Industry Institute 43.2 (1995): N. pag. Web. Spring .

Hanna, A. "Impact of Change Orders on Labor Efficiency for Mechanical Construction." J.C.E.M 125.3 (1999): 176-184. Web. Spring 2014.

[N1]delete

[N2]other

[N3]cause disruptions in the project / disrupt the project

[N4]pioneering?

[N5]omit

[N6]In most styles you need a date here. This may not apply to the syle you are using.

[N7]is

[N8]Institute

[N9]What study?

[N10]awkward - not clearly expressed

[N11]Works