TAMUC-SIS-Banner XE-Phase II
Project Charter Document
1/12/2017
Version: [v1.1]
Revision Date: [4/19/17]
Approval of the Project Charter indicates an understanding of the purpose and content described in this deliverable. By signing this deliverable, each individual agrees work will be initiated on this project and necessary resources are committed as described herein.
Project Sponsor / CITE / Project Type / Maintenance /ITSSC Approval
Approver / Approved / DateTim Murphy, CIO / ☒Yes
☐No / 4/19/2016 /
Choose an item. / ☐Yes
☐No / Click here to enter a date. /
Choose an item. / ☐Yes
☐No / Click here to enter a date. /
Choose an item. / ☐Yes
☐No / Click here to enter a date. /
Choose an item. / ☐Yes
☐No / Click here to enter a date. /
Choose an item. / ☐Yes
☐No / Click here to enter a date. /
Choose an item. / ☐Yes
☐No / Click here to enter a date. /
Choose an item. / ☐Yes
☐No / Click here to enter a date. /
Overview
Project Purpose
The purpose of the Banner XE Program is to upgrade the SIS modules to Banner 9 prior to the end of INB-support for Banner Support. Immediate goal is to stand up a three-tier environment (DEV, QA, and PROD) as soon as possible so an INB switchover could occur if we had a 90-day notice that Microsoft was discontinuing support for the Java plugin.
Project Objective
Project Goals / Project ObjectivesHave the most updated version of Banner so students and faculty can utilize the newest features of Banner XE / Update all modules of Banner 8 to Banner XE
Project scope
Upgrade the Banner 8 to Banner 9 in order to have access to Ellucian / Oracle support services and to utilize the new features in Banner’s latest version. Banner XE is used for the Extended Ecosystem construct which could be Banner 8 or 9, while the new release is Banner 9.
This will include the following:
- Adding data objects necessary for Database Extension Utility (DBEU)
- Upgrade of Oracle Database to 12c
- Moving to Oracle Fusion Middleware 12c
- Populating necessary values for DBEU Phase II
- Setup of Banner XE with a Single Sign On Solution
- Necessary for Single Sign On into Banner XE modules
- Banner XE Registration
- Banner INB Replacement (Banner 9 Admin Pages)
- Setup/Configuration of Banner 9 SSB (Rebranded as Campus)
This will not include:
- Faculty/Staff Training on Banner 9 after implementation
Project Budget
This is an internal project and level of effort will be provided once business requirements document is completed. This project is a medium sized and will exceed 400 hours.
Major Project Milestones and Deliverables
List the major milestones and deliverables and their targeted completion dates. This list should reflect products and/or services included with this project, as well as the delivery of key project management or other project-related deliverables.
Milestone/Deliverable / Targeted Completion DateOracle Database 12c Upgrade / 12/2015
DBEU Phase II / 6/10/2016
Set Up IDP / 9/15/2016
Phase I Hardware Setup / 1/25/2017
Set Up Oracle Fusion Middleware 12 / 2/10/2017
Banner XE DEV Hardware Setup / 2/17/2017
Banner XE DEV Admin & SSB Boxes Installed / 3/3/2017
Hook Up IDP to DEV and Active Directory / 4/4/2017
Release Banner XE DEV to Business Owners / 4/5/2017
Banner XE Configuration Discussions / 5/31/17
Banner XE QA Environment Set Up to ComDev1 / 6/22/17
Testing Expands with QA / 7/28/17
Banner XE PROD Environment Set Up to ComDev2 / 8/9/17
Switch Out XE Servers from ComDev1 to TEXQA / 9/29/17
Switch Out XE Servers from ComDev2 to TEXP (Commerce Production) / 9/29/17
Close-out / 10/6/17
Project Authority
Project Manager
Responsible for:
- Working with all stakeholders to ensure the business requirements have been accurately recorded and implemented for this request.
- Providing weekly project status reports to customer via email.
- Managing project communications and documentation for the project
- Coordinating resources for each objective
Project Core Team
Name / Project Role / ResponsibilityChris Frost / COE- Director/Banner Developer / Provides approach and direction in managing the project, Assists with setup of Banner XE
Douglas Dodd / Banner Developer / Setup/Configuration of Banner XE
Gerald Hill / Business Analyst / Banner Analyst, Documentation Support
Robert Twombly / Infrastructure – System Administrator / Creation on Virtual Servers, OS Level Server Maintenance
Quentin Thomas / Business Analyst / Documentation Support
Shashi Magadi / Oracle Database Administrator / Oracle Database Upgrade
Simon Chio / Banner Administrator / Oracle Middleware Upgrade, Setup/Configuration of Banner XE
Oversight Committee Business Unit members will be added if the project is approved for implementation)
Who are the main stakeholders for this project?
Paige Bussell, Charles Robnett, Tina Livingston, Maria Ramos, Mary Beth Sampson, Jeremy Gamez, Jody Todhunter
Assumptions, Contraints, Dependencies
Assumptions
- SIS team will be able to develop as much backend work as possible as Ellucian progresses through its Java Transformation project
- Ellucian provides 1-to-1 replacement functionality for INB forms through the project
- Ellucian is replacing earlier Banner XE stand-alone and SSB components that were built on ZK framework. This should allow us to not deploy any ZK framework modules for Banner XE.
- Ellucian will continue developing a timeline for moving their SSB delivered content into a Banner 9 package
- Ellucian will provide a WebTailor replacement solution through the Extensibility project
Constraints
- Upgrade should be completed before 12/1/17
- Ellucian just released the last of its INB replacement forms for Financial Aid in January 2017
- Ellucian currently cannot address some of the SSB functionality and is not sure when they can address the issue
- TCC Support is limited because of delays by Group I and Group II schools in implementing HR and Finance
- Servers will need to be configured to connect through the firewall
- VM’s will limited by available memory and storage
Dependencies
- SIS team will need to work with Infrastructure on an approach to tie in Banner with Single Sign-On
- Some tasks are dependent on Ellucian support and could delay project progress.
- The Application navigator navigates users to the appropriate version of Banner (Banner XE or Banner 8) depending on what application they are trying to access
- Columbia Advisory Group’s team implementations are dependent on Ellucian delivering their side of the product