Delay Notice

Letter No (1)

28/Mar/12

Subject: Notification for Additional Cost and Time due late permission of local authorities

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.1 dated3/25/2012

We hereby notify the client that there will be additional cost /time due to the late permission ion of local authorities.

Following are the impacted activities due to Employer instruction:

Following are due to the late authorization impacted activities:

Activity ID

Activity Name

Letter 1 - 1

Authorities Permissions

The Impacted Existing Activity:

Activity ID

Activity Name

SUBz100020

Excavation Activity

Any additional cost /time which may arise from this event will be submitted with substantiation in due course of time.

Delay Notice

Letter No (2)

24/Mar/12

Subject: Notification of delay for late handing over of site

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.2 dated3/20/2012

Please be informed that as per the plan the site was supposed to be handed over on 10th march,12 to the contractor to start the execution, due the fact the site is hand over on 20th mar,12.the contractor hereby notify you that its an event which will cause delay to the project completion, this event along with substantiation will submitted in due course of time.

Following are the impacted activities due to this event:

The additional scope of work:

Activity ID

Activity Name

Letter 2 - 1

Site Delivery Delay

The Impacted Existing Activity:

Activity ID

Activity Name

SUBZ100010

Mobilization

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice

Letter No (3)

18/Apr/12

Subject: Additional Cost and Time notice for Pumps Submittal

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.3 dated4/15/2012

We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID

Activity Name

MAR-20-1

New Pumps Submittal

The Impacted Existing Activity:

Activity ID

Activity Name

0801MW0011

INSTALLATION OF WATER & FIRE PUMPS

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice

Letter No (4)

15/May/12

Subject: Additional Cost and Time notice for Lighting Fixture Type 2*26 w

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.3 dated5/12/2012

We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID

Activity Name

MAR 4-1

Delay of MAR response

The Impacted Existing Activity:

Activity ID

Activity Name

A2250

LIGHTING FIXTURES& SWITCHS Procurement

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice

Letter No (5)

3/Jan/13

Subject: Additional Cost and Time notice for Item no.1 ( Utilities will be available on 1 July 2013 ).

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.1 dated2/1/2013

We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID

Activity Name

MOM-13-1

Delay of Utilities availability

The Impacted Existing Activity:

Activity ID

Activity Name

A2450

Elevators TESTING AND COMMISSIONING

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice

Letter No (6)

9/3/20162

Subject: Additional Cost and Time notice for Supplying Safe door

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.2 dated9/1/2012

We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID

Activity Name

MOM 9-1

Safe Door Supplying Delay

The Impacted Existing Activity:

Activity ID

Activity Name

Arch1070

Wall Preparation for Painting

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice

Letter No (7)

1/Apr/12

Subject: Additional Cost and Time notice for Under Ground Water Level

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.1 dated3/29/2012

We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID

Activity Name

RFI No.3-1

Response from Consultant

The Impacted Existing Activity:

Activity ID

Activity Name

SUBZ100030

COMPACTING WORKS UNDER THE P.C LAYER

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice

Letter No (8)

4/Feb/13

Subject: Additional Cost and Time notice for Clash between Lighting Unit and Diffuser

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.3 dated2/1/2013

We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID

Activity Name

RFI-6- 1

Remove Fixed Lighting Fixture

The Impacted Existing Activity:

Activity ID

Activity Name

0801EL0005

LIGHTING FIXTURES& SWITCHS & OUTLETS

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice

Letter No (9)

10/May/12

Subject: Additional Cost and Time notice for Doors and Windows Shop Drawing

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.3 dated5/7/2012

We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID

Activity Name

SDF 2-1

New Door Submittal

The Impacted Existing Activity:

Activity ID

Activity Name

ARCH1150

WOODEN DOORS INSTALLING

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice

Letter No (10)

5/Jun/12

Subject: Additional Cost and Time notice for Change Marble Fixation

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.1 dated6/2/2012

We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID

Activity Name

SWI1_1

Demolish all fixed marble

The Impacted Existing Activity:

Activity ID

Activity Name

Arch1110

MARBLE WORKS VIP SEC. WALL'S CLADDING &FLOORING

The additional cost and / or time impact analysis will be submitted in due course.

Delay Notice

Letter No (11)

19/Mar/13

Subject: Additional Cost and Time notice for Change Painting Color Code

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.3 dated3/15/2013

We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID

Activity Name

SWI 2_1

Submit new material for approved

The Impacted Existing Activity:

Activity ID

Activity Name

A2290

Painting Site delivery date

The additional cost and / or time impact analysis will be submitted in due cour