Delay Notice
Letter No (1)
28/Mar/12
Subject: Notification for Additional Cost and Time due late permission of local authorities
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.1 dated3/25/2012
We hereby notify the client that there will be additional cost /time due to the late permission ion of local authorities.
Following are the impacted activities due to Employer instruction:
Following are due to the late authorization impacted activities:
Activity ID
Activity Name
Letter 1 - 1
Authorities Permissions
The Impacted Existing Activity:
Activity ID
Activity Name
SUBz100020
Excavation Activity
Any additional cost /time which may arise from this event will be submitted with substantiation in due course of time.
Delay Notice
Letter No (2)
24/Mar/12
Subject: Notification of delay for late handing over of site
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.2 dated3/20/2012
Please be informed that as per the plan the site was supposed to be handed over on 10th march,12 to the contractor to start the execution, due the fact the site is hand over on 20th mar,12.the contractor hereby notify you that its an event which will cause delay to the project completion, this event along with substantiation will submitted in due course of time.
Following are the impacted activities due to this event:
The additional scope of work:
Activity ID
Activity Name
Letter 2 - 1
Site Delivery Delay
The Impacted Existing Activity:
Activity ID
Activity Name
SUBZ100010
Mobilization
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (3)
18/Apr/12
Subject: Additional Cost and Time notice for Pumps Submittal
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.3 dated4/15/2012
We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.
Following are the impacted activities due to Employer instruction:
The additional scope of work:
Activity ID
Activity Name
MAR-20-1
New Pumps Submittal
The Impacted Existing Activity:
Activity ID
Activity Name
0801MW0011
INSTALLATION OF WATER & FIRE PUMPS
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (4)
15/May/12
Subject: Additional Cost and Time notice for Lighting Fixture Type 2*26 w
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.3 dated5/12/2012
We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.
Following are the impacted activities due to Employer instruction:
The additional scope of work:
Activity ID
Activity Name
MAR 4-1
Delay of MAR response
The Impacted Existing Activity:
Activity ID
Activity Name
A2250
LIGHTING FIXTURES& SWITCHS Procurement
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (5)
3/Jan/13
Subject: Additional Cost and Time notice for Item no.1 ( Utilities will be available on 1 July 2013 ).
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.1 dated2/1/2013
We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.
Following are the impacted activities due to Employer instruction:
The additional scope of work:
Activity ID
Activity Name
MOM-13-1
Delay of Utilities availability
The Impacted Existing Activity:
Activity ID
Activity Name
A2450
Elevators TESTING AND COMMISSIONING
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (6)
9/3/20162
Subject: Additional Cost and Time notice for Supplying Safe door
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.2 dated9/1/2012
We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.
Following are the impacted activities due to Employer instruction:
The additional scope of work:
Activity ID
Activity Name
MOM 9-1
Safe Door Supplying Delay
The Impacted Existing Activity:
Activity ID
Activity Name
Arch1070
Wall Preparation for Painting
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (7)
1/Apr/12
Subject: Additional Cost and Time notice for Under Ground Water Level
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.1 dated3/29/2012
We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.
Following are the impacted activities due to Employer instruction:
The additional scope of work:
Activity ID
Activity Name
RFI No.3-1
Response from Consultant
The Impacted Existing Activity:
Activity ID
Activity Name
SUBZ100030
COMPACTING WORKS UNDER THE P.C LAYER
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (8)
4/Feb/13
Subject: Additional Cost and Time notice for Clash between Lighting Unit and Diffuser
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.3 dated2/1/2013
We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.
Following are the impacted activities due to Employer instruction:
The additional scope of work:
Activity ID
Activity Name
RFI-6- 1
Remove Fixed Lighting Fixture
The Impacted Existing Activity:
Activity ID
Activity Name
0801EL0005
LIGHTING FIXTURES& SWITCHS & OUTLETS
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (9)
10/May/12
Subject: Additional Cost and Time notice for Doors and Windows Shop Drawing
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.3 dated5/7/2012
We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.
Following are the impacted activities due to Employer instruction:
The additional scope of work:
Activity ID
Activity Name
SDF 2-1
New Door Submittal
The Impacted Existing Activity:
Activity ID
Activity Name
ARCH1150
WOODEN DOORS INSTALLING
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (10)
5/Jun/12
Subject: Additional Cost and Time notice for Change Marble Fixation
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.1 dated6/2/2012
We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.
Following are the impacted activities due to Employer instruction:
The additional scope of work:
Activity ID
Activity Name
SWI1_1
Demolish all fixed marble
The Impacted Existing Activity:
Activity ID
Activity Name
Arch1110
MARBLE WORKS VIP SEC. WALL'S CLADDING &FLOORING
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (11)
19/Mar/13
Subject: Additional Cost and Time notice for Change Painting Color Code
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.3 dated3/15/2013
We hereby notify the client that there will be additional cost and / or time due to the client instructions mentioned above.
Following are the impacted activities due to Employer instruction:
The additional scope of work:
Activity ID
Activity Name
SWI 2_1
Submit new material for approved
The Impacted Existing Activity:
Activity ID
Activity Name
A2290
Painting Site delivery date
The additional cost and / or time impact analysis will be submitted in due cour