Steps to create a single word document with the Simulation Powered Learning software.

  1. Login into Simulation Powered Learning system.

  2. Review completed project by navigating to Manage Projects and clicking the Review Project link.

  3. Create PDF of History by clickingon Reports -> Creae Report PDFs -> Print all History Reports (portrait)
  1. Print all charts by clicking on the Create PDF of Charts (landscape) button.


  1. Open .PDFs with Adobe and export the document to word by clicking on File-> Export -> Microsoft Word.

  1. At this point you can copy and paste (CTRL-C, CTRL-V) the history and charts into your final report document. See Appendix A – Final Report Sample

Appendix A- Final Report Sample/Template

Name:< Your Name >

Date:< Today’s Date >

Assignment:IS 455 - Simulation Final Report

Project Finish Week:< Enter week that project finished >

Actual Cost:< Enter Actual Project Cost

Number of Tasks:< Enter Number of Tasks from Project

Quality / Number of Defects:< Enter Actual Project Cost

Quality

16

14

12

10

C)

ai8

0

6

4

2


TargetSoftware

PrOjedDay

Hardware-Pro;ect

6C)CXX)

"sii:i

IJ...

"'C

5()CXX)......

40CXX)

;3000)

CD

a.. 20CXX)

10CXX)

0 ..

()

Project Day EAC

6()CXX)

CD 5()CXX)

CD

]!

::i

E

::i

40CXX)

3C)CXX)

t)2()CXX)

10CXX)

0

<:)


Earned Value

Day

PlannedVaueAc:ualCost

12

10

ii

41)

B

..r:

Ill

C

6

"C

......

41)4

a..

2

0------

ProjedOayEstmatedProject Fi ish

1.4

1.2

c[

CL.

1.0

0.8\

0.6

0.4

0.2

0------

,------

Pf"O!ecl. Day

PPI

TaskNameWlW2W3W4wsW6W7W8W9WlOWllW12W13

  1. SystemsDesign
  1. Network Design / Implementation

r ------·------]

,_-------_JI _ -----

r------


3.Software Implementationf------_]

r------

4.ProductDocumentation

5.SystemsIntegration

6.Customer AcceptanceTest

7.DocumentationReview

r------]

·------

;r_------_-.i------l

------]

Status Report For Week# 1

For: Tom Sulzer

Run Time: 2/6/2018 6:25:48 AM Run Id: #16371

Monday

Assistant

You are about to execute your first project week. Read the messages in this window carefully; you will often have multiple responses available. When choosing the best one, consider the anticipated short and long term results of each response. At the completion of each week, you will be redirected to the Reports screen. There are 8 different reports/charts on this screen and each has an Info window which provides a description of how the particular chart will help you understand the project status. So, good luck and happy managing!

Your response:

OK

4000

Tuesday

B. D. Smith

I must reinforce how critical it is that you successfully complete this prototype project on schedule and within budget. Our future is dependent on the success of the subsequent Alliance project and we can't allow anything to negatively impact Alliance. Do not hesitate to ask me for help.

Your response:

I look at this project as a growth challenge and will do my best to meet all of the objectives.

1100

B. D. Smith

I expect nothing less.

Your response:

Acknowledged.

1101

Wednesday Thursday

David Lewis

We need to send out invitations for the design approval meeting. Your response:

Send out an email to all departments notifying them when and where we will be holding the meeting.

16

Friday

Weekly Summary Reports

Weekly Resource Hours

NameTotal HoursTask : Hours Worker Productivity David Lewis48 (8 Hours of Overtime)1: 48 110%

Total Hours For the Week 48 Worker Availability Report There was no new staffing activity. Initial Task Assignment

Worker InformationAssigned Task Priorities and Overtime NameSkillStatusPriority 1 Priority 2 Priority 3Overtime

David Lewis IT Specialist Onproject 12.8

Task Hours Report

TaskHours worked this week Hours worked so far Planned total hours 1484880

All Tasks: 48

Task Status Report

Task #1 is: Working and is 66.14% complete

Project Status Report
The Project % complete / 5.75%
Actual Cost / $1720
Planned Value / $2609
Earned Value / $2875

------< END OF WEEK : 1 >------

Status Report For Week# 2

For: Tom Sulzer

Run Time: 2/6/2018 6:39:06 AM Run Id: #16371

Monday

A Status Report was sent to the Sponsor.

A Status Report was sent to the Subcontractor.

A Status Report was sent to the Executive Management. Tuesday

Conference

A conference was held with David Lewis to discuss Quality. The conference duration was 1 hour and the feedback provided was Coach.

Wednesday

Task 1 is now complete.

David Lewis

I think we made a mistake sending out the meeting notification like we did. More people showed up than the room could hold, some guy who doesn't have any stake in this project asked all kinds of questions and really impacted the meeting; and, worst of all, the key stakeholder in marketing left in disgust before we could get approval. What should we do now?

Your response:

Even though it will probably impact our schedule a couple of days, lets schedule another meeting and this time just invite the key stakeholders.

17

David Lewis

The VIP parking space is great; thank you for the recognition. Everyone will be very jealous. Your response:

You deserve the recognition.

1034

Thursday

Delayed Task

TASK 2 IS DELAYED 2 DAYS DUE TO RESCHEDULING OF THE DESIGN APPROVAL MEETING.

Friday

Delayed Task

TASK 2 IS DELAYED 2 DAYS DUE TO RESCHEDULING OF THE DESIGN APPROVAL MEETING.

Weekly Summary Reports

Weekly Resource Hours

NameTotal HoursTask : Hours Worker Productivity David Lewis29 (6 Hours of Overtime) 1: 24 ,2: 5 113%

Total Hours For the Week 29 Worker Availability Report

Sally NicolesNetwork Specialist

arrives in 1 week.

Initial Task Assignment

Worker InformationAssigned Task Priorities and Overtime NameSkill Status Priority 1 Priority 2 Priority 3Overtime

David LewisIT SpecialistOn project12.8

Sally Nicoles Network Specialist Arrives in 2weeks...0

Task Hours Report

TaskHours worked this week Hours worked so far Planned total hours 1247280

255240

All Tasks: 29

Task Status Report

Task #1 is: 100% complete

Task #2 is: Working and is 2.32% complete Task #4 is: Working and is 0% complete

Project Status Report
The Project % complete / 9.3%
Actual Cost / $3940
Planned Value / $5652
Earned Value / $4650

------< END OF WEEK : 2 >------

Status Report For Week# 3

For: Tom Sulzer

Run Time: 2/6/2018 6:44:18 AM Run Id: #16371

Monday Tuesday Wednesday

David Lewis, IT Specialist, was absent

David Lewis

We had the meeting and received our design approval. I wish it could have occurred earlier. Hopefully we won't have to redo something later on.

Your response:

Good job.

21

Thursday Friday

Weekly Summary Reports

Weekly Resource Hours

NameTotal HoursTask : Hours Worker Productivity David Lewis37 (5 Hours of Overtime)2: 37 121%

Total Hours For the Week 37 Worker Availability Report

Adam HerrezDocumentation Specialist

arrives in 1 week.

Jane HodgesSoftware Engineer

arrives in 1 week.

Omar MosaTest Engineer

arrives in 1 week.

Sally NicolesNetwork Specialist

has arrived and is available to work on the project next week!

Tea DominqueSoftware Engineer

arrives in 1 week.

Initial Task Assignment

Worker InformationAssigned Task Priorities and Overtime Name Skill Status Priority 1 Priority 2 Priority 3Overtime

Adam Herrez Documentation Specialist Arrives in 2weeks...0

David LewisIT SpecialistOn project2..6

Jane HodgesSoftware EngineerArrives in 2 weeks...0

Omar MosaTest EngineerArrives in 2 weeks...0

Sally Nicoles Network SpecialistArrives in 1 week ...0

Tea DominqueSoftware EngineerArrives in 2 weeks...0

Task Hours Report

TaskHours worked this week Hours worked so far Planned total hours 23742240

All Tasks: 37

Task Status Report

Task #1 is: 100% complete

Task #2 is: Working and is 21% complete Task #4 is: Working and is 0% complete

Project Status Report
The Project % complete / 14.17%
Actual Cost / $5660
Planned Value / $12174
Earned Value / $7085

------< END OF WEEK : 3 >------

Status Report For Week# 4

For: Tom Sulzer

Run Time: 2/6/2018 6:48:25 AM Run Id: #16371

Monday

Meeting

A meeting was held to discuss Teamwork. The meeting lasted 0.5 and the feedback provided was Counsel

Conference

A conference was held with David Lewis to discuss Attendance. The conference duration was 1 hour and the feedback provided was Counsel.

B. D. Smith

I see you're off to a particularly bad start. You realize that if you don't get your project back on schedule this company stands to lose a lot of money. With this much at stake I have asked Kitty Frost to assist you as co- project manager. She is our best project manager and her track record speaks for itself. I expect you to listen to her input and to act on it accordingly. Now get back to work and get this project back on track.

Your response:

Yes ma'am. Thank you for the assistance.

8

Assistant

She didn't sound very happy.

Kitty Frost

I believe Ms. Smith discussed with you my assignment as the co-project manager for this project. Since you have managed to get this project off to a bad start I am going to have to review your plans with a fine tooth comb to see if I can resurrect this project. I'll be getting back to you soon with my recommendations.

Your response:

I look forward to your recommendations.

9

David Lewis

I'm having some problems at home right now but I'll try my best not to miss anymore days at work. Your response:

Is there anything I can do to help?

35

David Lewis

I've been missing work because I am caring for a sick family member. If I could do some of my work at home that would really help.

Your response:

That is a difficult situation. Work from home as much as you need.

36

Tuesday Wednesday

Kitty Frost

I just finished reviewing your plans and it looks like your biggest issue is a leadership problem. I recommend that you properly motivate these people before we have a real crisis on our hands. Also I think you could have done a better job in your staff selection.

Your response:

Thanks for the review. I'll get right on it.

13

Thursday Friday

Weekly Summary Reports

Weekly Resource Hours

NameTotal HoursTask : Hours Worker Productivity David Lewis58.5 (20 Hours of Overtime)2: 58.5 86%

Sally Nicoles47.5 (8 Hours of Overtime) 2: 47.581% Total Hours For the Week106

David Lewis voluntarily worked overtime. Worker Availability Report

Adam HerrezDocumentation Specialist

has arrived and is available to work on the project next week!

Jane HodgesSoftware Engineer

has arrived and is available to work on the project next week!

Omar MosaTest Engineer

has arrived and is available to work on the project next week!

Tea DominqueSoftware Engineer

has arrived and is available to work on the project next week! Initial Task Assignment

Worker InformationAssigned Task Priorities and Overtime Name Skill Status Priority 1 Priority 2 Priority 3Overtime

Adam Herrez Documentation Specialist Arrives in 1week...0

David LewisIT SpecialistOn project2..8

Jane HodgesSoftware EngineerArrives in 1 week...0

Omar MosaTest EngineerArrives in 1 week...0

Sally Nicoles Network SpecialistOn project25.8

Tea DominqueSoftware EngineerArrives in 1 week...0

Task Hours Report

TaskHours worked this week Hours worked so far Planned total hours 2106148240

All Tasks: 106 Task Status Report

Task #1 is: 100% complete

Task #2 is: Working and is 57.91% complete Task #4 is: Working and is 0% complete

Project Status Report
The Project % complete / 23.8%
Actual Cost / $9220
Planned Value / $18696
Earned Value / $11900

------< END OF WEEK : 4 >------

Status Report For Week# 5

For: Tom Sulzer

Run Time: 2/6/2018 6:56:06 AM Run Id: #16371

Monday

Omar Mosa, Test Engineer, was absent

Meeting

A meeting was held to discuss Teamwork. The meeting lasted 0.5 and the feedback provided was Counsel

Meeting

A meeting was held to discuss Team Needs. The meeting lasted 0.5 and the feedback provided was Coach

Sally Nicoles

We seem to lose a lot of time traveling back and forth to the local coffee shop. If we had our own coffee machine here we could save some valuable time. I would be willing to research how much it would cost us to equip the project with our own coffee maker.

Your response:

Sounds ok to me. Let me know what you find out.

25

B. D. Smith

I just got out of a meeting with the head of marketing and they claim that you have not sent them any status on the project within the past month. They're pretty upset about this. You have got to keep the customer informed of where you are on a regular basis.

Your response:

I'll send a project status report out to them right away.

38

Sally Nicoles

Actually I have already done some research on it and I have found that we can get a pretty good quality coffee maker and initial supplies for about $300.

Your response:

Sounds good to me. Let me know what the actual amount is and I'll make sure you're reimbursed.

510

Tuesday

Wednesday

Louis Styles

I have reviewed your budget, specifically the Reserves category. You set aside money for risk in your planned budget. I'm alarmed because you have already spent 75% of what you had planned! There is an excessive amount in your reserves due to having people on your project and assigned to tasks they can't work on. You are not paying enough attention to your resource plan and task assignments. Make sure resources with the right skills are assigned to the currently active tasks. The currently active tasks are identified in the Gantt chart and at the end of every weekly report. If you have resources on the project with skills you don't need within the next two weeks, release them to the resource pool and hire them again when their task is two weeks from starting.

Your response:

Thank you, I will manage my resources better.

1350

Project Assistant

At the start of each run week, I always tell you if a worker is on the project but has not been assigned to work on a task. You need to correct these situations before running the week. Whenever you get the 'unassigned worker' message, go back to Staffing and look at the Task Assignment Window. Make sure that the assigned task is currently active (not waiting on a predecessor task to finish.) Use your Gantt Chart to see which tasks are active.

Your response:

I understand. Thank you.

1355

O. M. Smith

With the project about half completed, I have scheduled you for a formal status presentation in my boardroom next week.

Your response:

We look forward to presenting our status to you.

1410

Thursday Friday

Weekly Summary Reports

Weekly Resource Hours

NameTotal HoursTask : HoursWorker Productivity

Total Hours For the Week

177

NameTotal HoursTask : HoursWorker Productivity

Adam Herrez43 (4 Hours of

Overtime)

David Lewis63 (23 Hours of

Overtime)

4: 4375%

2: 6366%

Jane Hodges0Resource paid to be idle! Worker costhas been0%

Omar Mosa32 (0 Hours of Overtime)

Sally Nicoles39 (0 Hours of

Overtime)

Tea Dominque0Resource paid to be idle! Worker cost has been charged toReserves.*

Total Hours For the Week

177

Worker Availability Report There was no new staffing activity. Initial Task Assignment

Worker InformationAssigned Task Priorities and Overtime NameSkill Status Priority 1 Priority 2 Priority 3Overtime

Adam Herrez Documentation Specialist Onproject 47.4

David LewisIT SpecialistOn project 2..8

Jane HodgesSoftware EngineerOn project 3..0

Omar MosaTest EngineerOn project 4..0

Sally Nicoles Network SpecialistOn project 25.0

Tea DominqueSoftware EngineerOn project 35.0

Task Hours Report

TaskHours worked this week Hours worked so far Planned total hours 2102250240

47575120

All Tasks: 177 Task Status Report

Task #1 is: 100% complete

Task #2 is: Working and is 85.93% complete Task #4 is: Working and is 46.57% complete

Project Status Report

The Project % complete / 37.19%
Actual Cost / $19337
Planned Value / $25217
Earned Value / $18595

------< END OF WEEK : 5 >------

Status Report For Week# 6

For: Tom Sulzer

Run Time: 2/6/2018 7:04:42 AM Run Id: #16371

Monday

Meeting

A meeting was held to discuss Teamwork. The meeting lasted 0.5 and the feedback provided was Counsel

Meeting

A meeting was held to discuss Team Needs. The meeting lasted 0.5 and the feedback provided was Coach A Status Report was sent to the Executive Management.

Louis Styles

I will be putting three important memo's into your inbox later today. Please watch for them. Review them and I will get back to you shortly for something I need you to do ASAP.

Your response:

I'll read them.

8200

Tuesday

B. D. Smith

I just stopped by to see how things were progressing and I noticed that your product defect level is reaching into dangerous territory. I suggest that you address these quality problems as soon as possible or we are going to have a serious product delay on our hands.

Your response:

I'll get right on it.

26

Wednesday

Task 2 is now complete.

Assistant

Your budget has been charged for materials used.

O. M. Smith

Even though you are behind schedule and over budget I was very encouraged to see the confidence and enthusiasm that you and your team demonstrated. You obviously have been challenged by this project and seem to be on the road to recovery. Keep up the good work. By the way, I was very impressed with Sally Nicoles.

Your response:

Thank you. I will pass along your kind words to the team and Sally.

1414

Thursday

Louis Styles

Have you even read the Project Charter? I highlighted the section regarding Quality for you. Please read the Charter and review the information about Task 6, then get back to me.

Your response:

Thanks for the clarification. I'll make sure we meet the quality objective.

2100

Friday

Task 4 is now complete.

Weekly Summary Reports

Weekly Resource Hours

NameTotal HoursTask : Hours Worker Productivity Adam Herrez47 (8 Hours of Overtime) 4: 43 ,7: 4 80%

David Lewis63 (23 Hours of Overtime) 2: 34 ,3: 2973%

Jane Hodges17 (0 Hours of Overtime) 3: 1793%

Omar Mosa39 (0 Hours of Overtime) 4: 35 ,7: 481%

Sally Nicoles26 (4 Hours of Overtime) 2: 2656%

Tea Dominque17 (0 Hours of Overtime) 3: 1793% Total Hours For the Week209

David Lewis voluntarily worked overtime. Worker Availability Report

There was no new staffing activity.

Initial Task Assignment

Worker InformationAssigned Task Priorities and Overtime NameSkill Status Priority 1 Priority 2 Priority 3Overtime

Adam Herrez Documentation Specialist Onproject 47.8

David LewisIT SpecialistOn project 2..8

Jane HodgesSoftware EngineerOn project 3..0

Omar MosaTest EngineerOn project 4..0

Sally Nicoles Network SpecialistOn project 25.8

Tea DominqueSoftware EngineerOn project 35.0

Task Hours Report

TaskHours worked this week Hours worked so far Planned totalhours

2 / 60 / 310 / 240
3 / 63 / 63 / 240
4 / 78 / 153 / 120
7 / 8 / 8 / 40

All Tasks: 209 Task Status Report

Task #1 is: 100% complete

Task #2 is: 100% complete

Task #3 is: Working and is 24.4% complete Task #4 is: 100% complete

Task #7 is: Working and is 12.45% complete

Project Status Report
The Project % complete / 54.73%
Actual Cost / $31131
Planned Value / $31304
Earned Value / $27365

------< END OF WEEK : 6 >------