13 April 2015

Dear

Re: Wharncliffe Gardens – heating and hot water upgrade works (contract P133b)

We have been appointed by CityWest Homes to carry out the upgrade works which will be starting on Tuesday 7 April and are planned to take one year to complete. We would like to take this oppportunity to introduce ourselves as the main contractor for the these works and to inform you of some important information.

Site office

For the first three weeks we will be constructing the site compound next to Castleford Court, at the end of Henderson Drive. We will also be using the area next to the boiler rooms and childrens play area for storing of waste material. This will only be used when the ground works are being carried out (for about three months).

Project Plan

·  April to July– will involve renewing the district pipe work around the estate. Please see the drawing on the reverse of this letter to give you an idea of where pipe runs are located.

·  April/May – start of individual surveys to properties requiring works. There will be a chance to discuss individual issues and to explain the works in further detail.

·  May to April 2016 – flat works including replacing radiators, renewing mains water service risers, and converting the cold water tank and cylinder to a single HIU (heat interface unit.)

Useful Contacts

·  Russell Jackson is your Site Manager and is responsible for any concerns you may have with regards to the works being carried out. He will be on-site from for the duration of the contract from 7 April. He can be contacted on 07535 357 683

·  Tammy Chughtai is your Watret Resident Liaison Officer (RLO) and is your first point of contact and she can be contacted on 07957 471 914

·  Or you can email

·  Information will be displayed about the project on the resident notice board, along with important dates and any bulletins.

Road Clearance and Traffic Management - Important Information

We have tried our best to keep parking disruption to a minimum. However, we do require that the entrance to the site compound is clear of vehicles at all times throughout the duration of the contract. Large lorries will be delivering various materials and waste clearing will take place over the duration of the project.

Repair call outs

Please continue to report any problems with your heating and hot water to the repairs call centre on 0800 358 3783 or to the out of hours emergency number on 020 7286 7412.

In-flat Surveys

We will start in-flat surveys from 20 April. To make an appointment for the survey (which will take about 40 minutes), please contact Tammy our RLO on the telephone above, visit the site compound after 20 April or contact us via the project email.