Sample PMP Exam Questions for Review
- For project integration to be the most effective, it usually requires a focus on:
- The personal ambitions of team members
- Regular updates to the project plan
- Effective communications at key interface points
- Effective internal controls
- The Project Management Body of Knowledge (PMBOK) requires the creation of lessons learned; which of the following is the BEST use of lessons learned?
- Historical information for future projects
- Planning record for the current project
- Input for presentations to key project stakeholders regarding project status
- Audit record to be used to address future questions about the current project’s deliverables
- The triple constraint includes:
- Time, cost, quality, customer satisfaction, effort
- Time, effort, quality, resources, technology
- Time, scope, quality, cost, customer satisfaction
- Effort, scope, quality, cost, customer satisfaction
- A major disadvantage of the projectized organization structure is the following:
- Multiple boss reporting
- Redundant resources
- Deep functional expertise
- Project manager has responsibility without authority
- Integration is the responsibility of the:
- Project team
- Project manager
- Management
- Stakeholders
- The customer requests a change to the project which doesn’t affect the timeline and is simple to complete; what should the project manager do FIRST?
- Make the change
- Request permission to make the change from the change control committee
- Evaluate each of the other triple constraints
- Inform the sponsor of the change being made
- The benefit of project management is:
- Executive identification of problems so customer’s needs can be addressed quickly
- Early identification of problems so the project manager can quickly address them
- Standard methodology that is used the same way on every project
- Early identification of problems so the customer can be notified quickly
- Typically in a projectized organization structure, employees assigned to a project receive their performance evaluations from:
- Functional team lead
- Project manager
- Shared between the project manager and line manager
- Line manager
- Project managers typically have the most authority in which type of organization structure?
- Classical
- Projectized
- Strong matrix
- Weak matrix
- The reporting level of the project manager depends least on:
- The dollar value
- The customer
- The location
- The risk
- Often in a matrix organization teambuilding is difficult because the ______?
- Team is technically focused
- Teams are made up of multiple functional resources
- Team members each have different roles and responsibilities on a project
- Teams are too large
- During the project planning phase, the project manager determines additional resources are required; from whom should the project manager request these resources?
- Project manager
- Line manager
- Customer
- Steering committee
- Which organization structure is best for managing complex projects requiring resources from multiple functions?
- Projectized
- Line
- Matrix
- Functional
- Project management is least appropriate in which industry:
- High technology
- Defense
- Repetitive manufacturing
- Hybrid industries
- Informal project management best refers to which of the following:
- Effective communication, cooperation, teamwork and trust
- Project management methodology clearly defined and followed throughout the organization
- Customer-led approach
- Project management maturity
- Conditions which must be met by the project alternatives are referred to as:
- Objectives
- Requirements
- Constraints
- Risks
- Increased competition often leads to which of the following:
- Executive meddling
- Organizational restructuring
- Project management maturity
- Hard-nosed tactics
- Which of the following is an advantage of the classical form of organization?
- Multiple boss reporting
- Easier budgeting and cost control
- Innovation
- Multiple communication channels
- If a team member adds functionality to a product without prior approval, which they indicate does not impact time, cost or quality, what should the project manager do first?
- Request the team member remove the new functionality as it wasn’t authorized
- Ask the project office to assess the value of the new functionality
- Ask the member how they know there is no time, cost or quality impact
- Request the customer to review the change and approve a change order
- Which of the following is the least important factor in influencing the selection of an organization form?
- Complexity of projects
- Level of experience with project management
- Amount of authority management is willing to delegate
- Company’s product lines
- Employees reporting to multiple bosses occurs when:
- Projects are over budget
- Functional requirements are not clearly understood
- Activities are integrated across multiple functions
- Executives interfere with the project manager’s responsibilities
- In a projectized organization, project success depends mostly on which of the following:
- Line manager keeping his promises to the project manager
- Project manager’s technical knowledge
- Identifying all project stakeholders
- Shared accountability between line managers and project manager
- A project is plagued by changes to its scope; who has the primary responsibility to decide if these changes are necessary?
- Project team
- Project manager
- Steering committee
- Stakeholder
- As a new project manager, you have been asked to plan a new project; it would be best to rely on _____ to improve your project’s chance of success?
- Your experience
- Your training
- Historical information
- Project management methodology
- Typical concerns an employee might have in a matrix organization include all of the following, except:
- Who will do their evaluations
- Reporting to multiple bosses
- Team member commitment
- The next project
Answers: c,a,c,b,b,c,c,b,b,c,b,d,c,c,a,b,a,b,c,d,c,c,c,c,d