MILITARY ANYBODY’S* CONTINUING AIRWORTHINESS MANAGEMENT EXPOSITION

*Insert Name of Approved Organization

Cover Page

MILITARY ANYBODY'S*

CONTINUING AIRWORTHINESS MANAGEMENT EXPOSITION (CAME)

*Insert Name of Air Platform(s) (Including Aircraft Mark Number)

Approval No: XXXX

The MAA CAMO desk officer will issue the approval number once the organization has submitted its application for approval (MAA Form 2).

Address: This should be the CAMO’sheadquarters

Telephone Number:

Facsimile Number:

Email Address:

Document Ref Number: (Reference number to assist in correspondence)

This Page Should be Deleted from the CAME Submitted to the MAA

NOTES.

1.All material contained within this document is for guidance purposes only. It sets out a template that the MOD CAM may follow in order to define their organizationandthe procedures used for the management of continuing airworthiness. The content should be expanded as required toreflect the CAMO procedures and identify who is undertaking the activity.

2.Where the CAMO is conducting an activity that is not in compliance with the MRP then a waiver, exemption or Alternative AMC (AAMC) must be applied for, and approved by the MAA, in accordance with MAA 03. Failure to do so will delay an initial approval or invalidate an existing approval. Where a waiver, exemption or AAMC has been granted, this must be clearly articulated and referenced in the CAME.

3.A CAMO which is responsible for multiple aircraft types and marks may submit a single CAME, providing it details all the aircraft being managed (by serial number) and clearly defines how/what activity is conducted for each type/mark.

4.When determining the content of the CAME the MOD CAMshould take into account the requirement of the Acceptable Means of Compliance (AMC) and Guidance Material (GM) associated with the relevant MRP RAs and use the principle of “Who, What, Where, and How”. This will ensure that for each paragraph heading the MOD CAM articulates:

a.What activates are being done.

b.Who is doing them.

c.What they are being carried out in accordance with, this may be MRP RAs, Topic 2(N/A/R)1 leaflets, AESO, AERO or local orders.

5.Bulleted lists, rather than extensive paragraphs, describing the activity are acceptable.

6.After completing the CAME the organization should completea Compliance Check List (CCL), available from the MAA website. The completed CCL should then be included as an appendix in Part 5 of the CAME.

7.MAA CAMO approval staff will reviewthe CAME and supporting documentation and conduct an on-site visit,in order to confirm that the CAMO is in compliance with the MRP Part M regulation. This process will be required before an initial approval is issued and may be required for a change to an existing approval.

8.All text in red within this specimen document template should be deleted prior to submission to the MAA.

9.Any queries with this document should be addressed to: .

This Page Should be Deleted from the CAME Submitted to the MAA

Contents.…

Cover Page

Contents.…

Amendment Record

Distribution List

Abbreviations Used

PART 0GENERAL ORGANIZATION

0.1Corporate Commitment by the Delivery Duty Holder (DDH) or Accountable Manager (Military Flying) (AM(MF))

0.2General Information

0.2.1Description of the Organization

0.2.2Aircraft Managed

0.2.3Type of Operation

0.2.4Scope of Work

0.3Management Personnel

0.3.1Delivery Duty Holder

0.3.2Ministry of Defence Continuing Airworthiness Manager (MOD CAM)

0.3.3Quality Manager

0.3.4Deputy Continuing Airworthiness Manager (DCAM)

0.4Manpower Resources

0.5Training Policy

0.6CAMO Facilities

0.7CAMO Meetings

0.8Change Procedures

PART 1CONTINUING AIRWORTHINESS PROCEDURES

1.0Continuing Airworthiness Procedures

1.1Develop and Control a Maintenance Programme

1.2Modifications and Repairs

1.2.1Modifications

1.2.2Aircraft Repairs

1.3Maintenance

1.4Application of SI(T)

1.5Management of Faults Reported

1.6Scheduled Maintenance, SI(T) and Service Life Limited Parts

1.7Continuing Airworthiness Records

1.8Weight and Moment

1.9Occurrence Reports

PART 2QUALITY SYSTEM

2.0General Information

2.1Integration with other Quality Systems

2.2Monitoring of CAMO Activities

2.3Monitoring of Contracted Maintenance

2.4Monitoring Compliance

2.5Audit Personnel

2.6Audit Reporting

2.7Post Audit Follow-up and Rectification Actions

2.8Audit Plan

2.9Quality Review Meetings

2.10CAMO Procedures

PART 3CONTRACTED MAINTENANCE AND SUB-CONTRACTED/DELEGATED MRP PART M ……….

3.0General Information

3.1Contractor/Delegated Organization Selection

3.2Advising the MAA of Changes to Maintenance Support or Delivery of MRP Part M

3.3Contracted Maintenance Organizations

3.4MRP Part M Sub-contractors and/or Delegated Organizations

PART 4AIRWORTHINESS REVIEW PROCEDURES

4.1Baseline Military Airworthiness Review (BMAR)

4.2Airworthiness Review (AR) and Certification

4.3AR Staff

4.4AR Process

4.5Civil Oversight

4.6Invalidation of Military Airworthiness Review Certificate (MARC)

PART 5APPENDICES

5.1Compliance Check List

5.2Resource Matrix

5.3CAMO Meeting Agendas and Terms of Reference

5.4Sample Documents

5.5Quality System Audit Plan

5.6Copy of Contracts with Contracted Maintenance Organizations

5.7Copy of Contracts for Sub-contracted/Delegated MRP Part M

5.8AR Process Templates

5.9As Required

Ver 4 20150401Page 1

MILITARY ANYBODY’S* CONTINUING AIRWORTHINESS MANAGEMENT EXPOSITION

*Insert Name of Approved Organization

Amendment Record

AMENDMENT NO: / DATE / AMENDMENT DETAILS / AMENDED BY / DATE OF INCLUSION

Distribution List

COPY NUMBER / HOLDER

The document should include a distribution list to ensure proper distribution of the exposition and to demonstrate to the MAA that all personnel involved in continuing airworthiness have access to the relevant information. This does not mean that all personnel have to be in receipt of an exposition but that a reasonable amount of expositions are distributed within the organization(s) so that all personnel have quick and easy access to it.

Reference should also be made to the location of the e-copy of the CAME if held within MOSS.

Abbreviations Used

List all of the abbreviations used in the CAME.

Ver 4 20150401Page 1

PART 0GENERAL ORGANIZATION

Reference:

RA1016: Roles and Responsibilities: Continuing Airworthiness Management Organizations (CAMOs).

0.1Corporate Commitment by the DeliveryDuty Holder (DDH) or Accountable Manager (Military Flying) (AM(MF))

The Duty Holder confirms that this CAME and any associated manuals define the organizations compliance with MRP Part M and will be complied with at all times.

[ENTER AIR PLATFORM’S NAME]

CONTINUING AIRWORTHINESS MANAGEMENT EXPOSITION

The Duty Holder’s exposition statement should embrace the intent of the following paragraph, which may be used without amendment. Any modification to the statement should not alter the intent.

This Exposition defines the organization and procedures upon which the Sub Part G approval is based.These procedures are approved by the undersigned and must be complied with, as applicable,in order to ensure that all the continuing airworthiness tasksof[Quote CAMO’s Name]fleet of aircraft are carried out on time and to an approved standard.

It is accepted that these procedures do not override the necessity of complying with any new or amended regulation published from time to time where these new or amended regulations are in conflict with these procedures.

It is understood that the MAA will approve this organization whilst the MAA is satisfied that the procedures are being followed and the work standard is maintained. It is understood that the MAA reserves the right to suspend, vary or revoke the Subpart G CAMO approval of the organizationif the MAA has evidence that procedures are not followed and the standards not upheld.

Signed......

Dated.

Duty Holder and ……[Quote Position]….

For and on behalf of ….[Quote Organization’s Name]…

Note: Whenever the DH is changed, the new DH should sign the CAME statement at the earliest opportunity as part of the continuing approval of the CAMO. Failure to carry out this action within a time period not exceeding 30 days from changeover invalidates the CAMO approval.

0.2General Information

Reference:

RA1016: Roles and Responsibilities: Continuing Airworthiness Management Organizations (CAMOs).

0.2.1Description of the Organization

The CAMO is structured under the management of the DDH or AM(MF),[Name AppropriateDH].For the complete management structure refer to the organizations management chart in paragraph 0.2.3. Personnel will be familiar with those parts of the exposition that are relevant to their tasks.

Insert a brief description of the organizationhere.

0.2.1.1Relationship with Other Organizations

Insert details of those organizations involved in the delivery of continuing airworthiness and/or maintenance of the aircraft and its components, including Service organizations, contractors and sub-contractors.

Details of specific contracts and or JBAs/SLAs should be included in Part 3 of the CAME, with a cross reference to the relevant element included here.

0.2.1.2Organization Chart

Insert an organizational chart, defining the associated chains of responsibility within the CAMO and linkage to the DH construct. For MRCO platforms this must clearly demonstrate the links between the DDH or AM(MF), MOD CAM and CAMO QM and their civilian equivalents. This chart should reflect all elements conducting CAMO activity on behalf of the MOD CAM.

0.2.2Aircraft Managed

This paragraph should list the serial number andtype, mark or build standard of allaircraft managed by the CAMO.

The list of applicable aircraft must be updated as aircraft are added to, or removed from the military register either through disposal or sale. It must also be updated whenever the MOD CAM relinquishes or assumes responsibility for a particular serial number of aircraft.

If the CAMO has responsibilities for aircraft listed in this CAME, but for which there may be different DHs responsible, then the relevant DH must be stipulated against each tail number.The responsibilities of the relevant DHs must be reflected throughout this CAME.

0.2.3Type of Operation

The active[Enter Air Platform Name]fleet operates on military duties in the United Kingdom and internationally in the [Enter Aircraft Primary Roleseg combat missions, transport (personnel/cargo), SAR, surveillance etc]. The aircraft are authorised for operations in line with international protocols by the Secretary of State (S of S) for Defence through registration on the UK Military Aircraft Register.

0.2.4Scope of Work

[Enter Air Platform Name]CAMO will ensure the continuing airworthiness management of its aircraft by compliance with MAA Regulatory Publications (MRP)in accordance with the procedures detailed within this CAME and associated orders, as follows:

Insert details of the relevant orders, procedures or manuals which define how continuing airworthiness management is achieved here, eg Topic 2(N/A/R)1, AEROs, AESOs, etc

0.2.4.1Maintenance Facilities

Briefly outline the range of work carried out by the maintenance organizations at each site, as a minimum this should include details of the following:

0.2.4.1.1Aircraft

Insert details of the forward and depth activities that are carried out at each site.

Insert details of the applicable design organization.

0.2.4.1.2Engines

Insert detail of the engines fitted to each mark of aircraft.

Insert details of the applicable design organization.

0.2.4.1.2Propellers

If applicable:

Insert details of the propellers fitted to each mark of aircraft.

Insert details of the applicable design organization.

0.3Management Personnel

0.3.1Delivery Duty Holder

References:

RA1016: Roles and Responsibilities: Continuing Airworthiness Management Organizations (CAMOs).

RA 4945(1): Role of the Duty Holder.

The duties and responsibilities associated with this post are held by [Enter Name and Title of DH].

0.3.1.1Delivery Duty Holder Roles and Responsibilities

The roles and responsibilities of the DDH or AM(MF) should be outlined here.

If the DDH or AM(MF) is not able to fulfil any of his responsibilities or there are any caveats to these responsibilities then they should be stipulated here, with reference to any associated MAA waiver, exemption or AAMC and/or higher authority acceptance.

0.3.2Ministry of Defence Continuing Airworthiness Manager (MOD CAM)

Reference:

RA 4945(2): Requirements for the MoD Continuing Airworthiness Manager (MOD CAM).

The duties and responsibilities associated with the Crown Servant post of MOD CAM are currently assumed by [Enter Name and Title of Post Holder], in support of the DH.

0.3.2.1MOD Continuing Airworthiness Manager Roles and Responsibilities

The roles and responsibilities of the MOD CAM should be outlined here.

Insert a clear statement that the MOD CAM has been assessed as being SQEP. Details of the assessment process should also be included.

If the MOD CAM is not able to fulfil any of his responsibilities or there are any caveats to these responsibilities then they should be stipulated here, with reference to any associated MAA waiver, exemption or AAMC and/or higher authority acceptance.

0.3.3Quality Manager

Reference:

RA 4951(1): Establishing a Quality System.

The duties and responsibilities associated with this post are currently assumed by [Enter Name of Post Holder]in support of the DH.

0.3.3.1Quality Manager Roles and Responsibilities

Details of the QM roles and responsibilities should be outlined here. This should include the links between the MOD CAM and the DH and how independence from the activity subject to audit will be achieved.

Insert a clear statement that the QM has been assessed as being SQEP. Details of the assessment process should also be included.

If the QM is not able to fulfil any of his responsibilities or there are any caveats to these responsibilities then they should be stipulated here, with reference to any associated MAA waiver, exemption or AAMC and/or higher authority acceptance.

0.3.4Deputy Continuing Airworthiness Manager (DCAM)

Reference:

RA 4945(2): Requirements for the MoD Continuing Airworthiness Manager (MOD CAM).

If applicable:

The duties and responsibilities associated with this post are currently assumed by [Enter Name of Individual],who has been assessed as being SQEP,in support of the MOD CAM.

0.3.4.1DCAM Roles and Responsibilities

If applicable:

Outline the roles and responsibilities of the DCAM.

Insert a clear statement that the DCAM has been assessed as being SQEP. Details of the assessment process should also be included.

If the DCAM post has been established, but the individual is not able to fulfil any of his responsibilities or there are any caveats to these responsibilities then they should be stipulated here, with reference to any associated MAA waiver, exemption or AAMC and/or higher authority acceptance.

0.4Manpower Resources

Insert details of any resource analysis that has been conducted to determine the manpower requirements for the CAMO.

Identify allposts and/or organizations conducting CAMO activity on behalf of the MOD CAM, including details of the activity being carried out by them, including sub-contracted or delegated activity. This may take the form of a matrix, which may be included in A3 Landscape using a Section Break or as an appendix in Part 5 of the CAME, with a cross reference to it included here.

Example Resource Matrix:

Aw Resp / Organization 1 / Organization 2 / Organization 2 / Etc / CAME Ref
Post (a) / Post (b) / Post (c) / Post (d) / Post (e) / Post (f) / Etc
Develop Maint Prog / Task 1.1 / X / X / X / 1.1.1
Task 1.2 / X / X / X / X / 1.1.2
Etc / X / X / X / X / Etc
Mods & Repairs / Task 2.1 / 1.2.1.1
Task 2.2 / X / X / 1.2.1.2
Etc / X / X / X / Etc
Etc

Where CAMO tasks have been sub-contracted or delegated to other organizations (or other CAMOs) then the other organizations have to be identified and a clear reference to any contractual arrangement, SLA/JBA or appropriate order (AESO, Topic 2(N/A/R)1), etc must be included. This will include, for example, PT personnel, contractor personnel, squadron personnel who are conducting CAMO activity. This information may be included in Part 3 of the CAME, with a cross reference to it inserted here.

0.5Training Policy

Reference:

RA 4945(3): Qualification of Personnel.

Insert details of how the training, qualification standards and competence for allpersonnel conducting CAMO activity, including PT, squadron and contractor staff (as detailedat para 0.4 above),will be delivered, assessed and recorded by the MOD CAM. It should also include how the need for recurrent training is assessedand undertaken and how this is recorded and follow-up performed.

0.6CAMO Facilities

Reference:

RA 4943(1): Provision of the CAME.

Office accommodation should be such that the incumbents, whether they be continuing airworthiness management, planning, technical records or quality staff, can carry out their designated tasks in a manner that contributes to good standards. Office accommodation should also include an adequate technical library and room for document consultation.

This paragraph should:

a.Specify the layout of premises (this could be a floor plan or general description).

b.Detailthe office accommodation for: planning, technical records, quality, technical reference area and storage.

c.Make e a definitive statement that the facilities provided meet the CAMO requirements. If facilities are deemed not to be suitable then relevant mitigation action and the proposed corrective action needs to be detailed.

If CAMO activity is conducted at a number of sites, then details of the facilities available for the completion of CAMO activity at each site must be included. This includes PT, Squadron, contractor/sub-contractor sites and office space.

0.7CAMO Meetings

Insert details of any specific meetings that have been established by or are attended by the MOD CAM, or his nominated representative. This detail should include frequency and purpose of the meeting. Agenda and terms of reference for these meetings may be included as an appendix in Part 5 of the CAME, with a cross reference to it included here.

0.8Change Procedures

Once an organization has been approved any subsequent change to the CAME must be agreed by the MAA, unless the change is classed as an indirect approval[1]. In such instances the DDH OR AM(MF) is required to submit a further MAA Form 2 and amended CAME, to the MAA, to enable the MAA to determine continued compliance with CAMO requirements, to approve the change prior to incorporation and to make any necessary amendments to the MAA Approval (MAA Form 3) that may be appropriate.

0.8.1Continued Validity of Approval

Reference:

RA 4954: Continued Validity of Approval – MRP Part M Sub Part G

The CAMO approval will remain valid for an unlimited period provided that:

  1. The CAMO remains in compliance with this CAME.
  1. The CAME remains in compliance with the MRP.
  1. The MAA being granted access to the CAMO.
  1. The approval not being surrendered or revoked. Upon surrender or revocation, the approval certificate shall be returned to the MAA.

0.8.2CAME Review

The CAME will be reviewed, by the MODCAM, or his nominated representative, at intervals not exceeding 12 months, or more frequently when significant changes occur which affect the content of the CAME.

Insert details of how these reviews will be conducted, including cross reference to any associated procedures.