EXAMPLE – DELETE BEFORE SUBMITTING REPORT
Contract Name: New Link Road / Contract No:123/12 / Reporting Period:31Mar 2015 - 31 Mar 2016
Contractor: XYZ Construction / Contact person: Jim Smith, Contract Manager, XYZ Construction, , 0444 444 444
Instructions for completing Industry Participation Plan report
This is the recommended template for reporting.
Enter additional lines where required.
Reports should include all contracts over $250,000 with contract values below this figure entered as a consolidated one line item.
The estimated breakdown of source is calculated by where the product was manufactured, produced or fabricated, not the location of the contractor.
Reports are required annually (from the date construction commences) and at Practical Completion, unless a variation is agreed upon.
Email report to
Goods and Services Contracts
Contract number or reference / Contract description / Contractor / Anticipated contract duration / Location of contractor / Total contract value / Committed costs for this reporting period / Breakdown of source for total contract value (estimated %) / Overseas content description
WA / Other Australia / Overseas
PW 12343 / Civil and concrete works / Concrete Works Ltd / 6 months / Mandurah, WA / $550,000 / $200,000 / 80% / 20% / Some imported cement
HE 345 / Rail inspection services / Railtrack Pty Ltd / 3 months / Perth, WA / $500,000 / $500,000 / 60% / 40% / Specialist professional expertise
PP 1295 / Supply of IT equipment and hardware / IT Specialists Company / n/a / Perth, WA / $600,000 / $300,000 / 30% / 70% / Majority of IT equipment manufactured overseas
Total / $1,650,000 / $1,000,000
Comments: / (Any considerations that should be understood when reviewing this report OR feedback on local industry capability or limitations)
Other Local Benefits (if applicable)
(These may include research and development, technology transfer, strategic alliances with local suppliers, regional development, indigenous programs, community support initiatives, environmental programs, contributions towards such initiatives as training and skills development programs)
Details / Location (specify region, if applicable) / Committed costs: / Breakdown of source for committed costs (estimated %)
WA / Other Australia
Donation to community environmental group / Geraldton / $10,000 / 100%
Total / $10,000 / 100%

MAIN ROADS Western AustraliaPage 1 of 4

Industry Participation Plan (IPP) Report

INDUSTRY PARTICIPATION PLAN REPORT
Contract Name: / Contract No: / Reporting Period:
Contractor: / Contact person:
Goods and Services Contracts
Contract number or reference / Contract description / Contractor / Anticipated contract duration / Location of contractor / Total contract value / Committed costs for this reporting period / Breakdown of source for total contract value (estimated %) / Overseas content description
WA / Other Australia / Overseas
Total / $1,650,000 / $1,000,000
Comments: / (Any considerations that should be understood when reviewing this report OR feedback on local industry capability or limitations)
Other Local Benefits (if applicable)
(These may include research and development, technology transfer, strategic alliances with local suppliers, regional development, indigenous programs, community support initiatives, environmental programs, contributions towards such initiatives as training and skills development programs)
Details / Location (specify region, if applicable) / Committed costs / Breakdown of source for committed costs (estimated %)
WA / Other Australia
Total

MAIN ROADS Western AustraliaPage 1 of 4

Industry Participation Plan (IPP) Report