APPENDIX B
PAGE 1
IAPCS VERSION 5a 3/17/2005 15:32:19
INTEGRATED AIR POLLUTION CONTROL SYSTEM COSTING PROGRAM------
Gascoyne CFB
USER INPUT SUMMARY
------
BOILER SIZE: 175. MW TANGENTIALLY FIRED, DRY BOTTOM
CAPACITY FACTOR: 90.0 % 310. DEG.F
CONSTRUCTION STATUS OF CONTROL SYSTEM: NEW
COAL CLEANING LEVEL: RUN-OF-MINE SORTED AND SCREENED
COAL CHARACTERISTICS AT THIS CLEANING LEVEL:
HHV (BTU/#): 5749.0
SULFUR CONTENT (%): 1.00
ASH CONTENT (%):12.09
COST ($/TON): .00
CHLORINE CONTENT (%): .00
MOISTURE CONTENT (%): 6.00
VOLATILE MATTER CONTENT (%):36.20
FIXED CARBON CONTENT (%):48.70
ASH CHARACTERISTICS AT THIS CLEANING LEVEL:
NA20 CONTENT (%): .90
ALKALINITY (%): 5.10
FE2O3 CONTENT (%):20.20
CONTROL SYSTEM CONFIGURATION:
1 - SELECTIVE NONCATALYTIC REDUCTION
2 - ATMOSPHERIC FLUIDIZED BED (AFBC)
3 - LIMESPRAY DRYING (LSD)
4 - FABRIC FILTER (FF)
Warning: Control devices should be entered in the
correct gas path order from the boiler to the stack.
Results for this run may not be correct.
ECONOMIC PREMISES (TVA/EPRI):
+ EPRI
1 PAGE 2
INTEGRATED AIR POLLUTION CONTROL SYSTEM COSTING PROGRAM
------
USER INPUT SUMMARY (CONTINUED)
------
PARAMETER FILE USED: C:\OLDCOM~1\D\DONS\POWERP~1\IAPCS_5A\GSCYNCFB.EPR
BATCH DATA FILE USED: C:\OLDCOM~1\D\DONS\POWERP~1\IAPCS_5A\GSCYNCFB.EPR
THE FOLLOWING CHANGES WERE MADE TO THE PARAMETER FILE FOR THIS RUN:
NEW VALUE DESCRIPTION
------
59.00 SO2 Removal Efficiency %, (LSD)
1 PAGE 3
UREA-BASED SNCR SYSTEM
IN THE SNCR SYSTEM, UREA IS INJECTED INTO
THE UPPER FURNACE USING WALL INJECTORS.
NOx REDUCTION EFFICIENCY IS 50.00 % AT A
N:NOx STOICHIOMETRIC RATIO OF 1.13 YIELDING
AN AMMONIA SLIP RATE OF 8.94 PPM
OR 4.47%.
SPRAY DRYING ABSORBER
OVERALL STOICHIOMETRIC RATIO 1.45
SPRAY-DOWN TEMPERATURE 175. DEG F
OVERALL SO2 REMOVAL EFFICIENCY 59.0 %
NUMBER OF OPERATING DRYER UNITS 3
NUMBER OF SPARE DRYER UNITS 0
DESIGN L/G .197 GAL/1000 CU FT
AVERAGE PRESSURE DROP 2. IN H20
FLUE GAS TREATED 100.00%
FABRIC FILTER
THE FABRIC FILTER IS DESIGNED TO REMOVE 99.7 % OF THE
PARTICULATE LOADING WITH AN AIR-TO-CLOTH RATIO OF ***.
.0 % OF THE FLUE GAS IS BYPASSING THE FABRIC FILTER.
THE FABRIC FILTER REFLECTS A REVERSE AIR CLEANING
CONFIGURATION AND TEFLON-COATED FIBERGLASS BAGS.
FANS
THE TOTAL SYSTEM PRESSURE DROP IS 10.0 IN. H20.
THE SYSTEM REQUIRES 3 FAN(S) RATED AT 995. HP EACH.
1
PAGE 4
BOILER/SYSTEM PERFORMANCE
------
0 PARASITIC DEMAND (W/O CONTROL)...... -4.5%
STEAM CYCLE HEAT RATE...... 8277.0 BTU/KWH
BOILER THERMAL EFFICIENCY...... 79.2%
BOILER GROSS HEAT RATE...... 10451.8 BTU/KWH
BOILER NET HEAT RATE W/O CONTROL SYSTEM.. 10000.0 BTU/KWH
BOILER NET HEAT RATE W/ CONTROL SYSTEM... 11004.0 BTU/KWH
HEAT INPUT...... 1750.0 MMBTU/H
COAL USE...... 152.2 TONS/H
ANNUAL COAL CONSUMPTION...... 1.1999E+06 TONS/YR
IAPCS ENERGY PENALTY...... 1004.0 BTU/KWH
IAPCS ENERGY PENALTY...... 10.0 %
SYSTEM NET GENERATION...... 159.0 MW
SYSTEM MATERIAL BALANCE
(100% CAPACITY CONDITION)
------
AIR
UNCONT- HEATER
ROLLED EXIT
+ LSD FF
------
FLUE GAS, 1000 LB/H : 4269. 4285. 4426. 4426.
FLUE GAS, 1000 ACFM : 1428. 1432. 1241. 1241.
TEMPERATURE,DEG.F : 310. 310. 175. 175.
MOISTURE, LB/H : 301671. 303133. 444466. 444466.
ALKALINITY, LB/H : 1740. 2473. 2267. 7.
PARTICULATE, LB/H : 34111. 51. 296. 1.
SO2, LB/H : 6473. 617. 253. 114.
NO2, LB/H : 2489. 1050. 1050. 1050.
CO2, LB/H : 620231. 568791. 568791. 568791.
EMISSION SUMMARY
------
PERCENT
POLLUTANT LB/HR REDUCTION LB/MMBTU PPM(V)
------
PARTICULATE 1. 99.9 .001
SO2 114. 98.2 .065 12.
NO2 1050. 57.8 .600 229.
CO2 568791. 8.3 325.023
1
PAGE 5
INSTALLED CAPITAL COSTS JUNE, 1995
------
TOTAL WEIGHTED AVERAGE RETROFIT FACTOR: 1.00
FABRIC FILTER------$ 3779800
RETROFIT FACTOR: 1.00
FF AND DUCTING------$ 3318600
FF ASH DISPOSAL------$ 461300
------
LIMESPRAY DRYING------$ 21861300
RETROFIT FACTOR: 1.00
ATMOSPHERIC FLUIDIZED BED (AFBC)------$ 209287300
RETROFIT FACTOR: 1.00
STEAM GENERATOR------$ 41857300
PM CONTROLS------$ 17915400
STEAM/FEED WATER/COND.----$ 29802800
STEAM TURBINE------$ 21543600
COAL HANDLING/PREP.------$ 18515400
LIMESTONE/MISC. EQUIP.----$ 79652800
------
1 PAGE 6
SELECTIVE NONCATALYTIC REDUCTION------$ 1846400
RETROFIT FACTOR: 1.00
AIR HEATER MOD(SNCR)------$ 770200
NH3 STORAGE (SNCR)------$ 432500
NH3 INJECTION (SNCR)------$ 475500
CONTROLS/MISC. (SNCR)-----$ 168200
------
FANS------$ 808100
RETROFIT FACTOR: 1.00
TOTAL DIRECT CAPITAL COSTS W/O SCOPE ADDERS>$ 237582900
TOTAL DIRECT CAPITAL COSTS WITH SCOPE ADDERS>$ 237582900
DIRECT COSTS INCLUDE SALES TAX OF .0%
INDIRECT AND STARTUP COSTS------$ 198088804
GENERAL FACILITIES (10.0%)...$ 23758301
ENGINEERING (10.0%)...... $ 23758301
PROJECT CONTINGENCY (17.5%)..$ 41681400
PROCESS CONTINGENCY (27.0%)..$ 64095501
TOTAL PLANT COST (TPC)...... $ 390876403
INTEREST DURING CONSTRUCTION (10.4%)...... $ 24812701
TOTAL PLANT INVESTMENT ( 3.0yr)...... $ 415689100
ROYALTY ALLOWANCE ( .4%)....$ 1055700
PREPRODUCTION COSTS ( 4.8%)..$ 11433000
INVENTORY CAPITAL ( 1.5%)....$ 3614900
INITIAL CATALYST ( .0%).....$ 78700
LAND ( 1.6%)...... $ 3800300
*************
TOTAL CAPITAL REQUIREMENT>*$ 435671700*
*************
TOTAL SYSTEM COST>$ 2489.55/KW
1 PAGE 6
ANNUAL OPERATING COSTS JUNE, 1995
------
INFLATION RATE...... 5.0%
BOOK LIFE ...... 30.0 YEARS
DISCOUNT RATE...... 11.5%
DEPRECIATION METHOD...... 3
1=accelerated, 2=straight line, 3=straightline based on ACRS class
CALCULATED CAPITAL CARRYING CHARGE FACTOR...... 0.1655
CALCULATED O&M LEVELIZATION FACTOR...... 1.6116
NOTE: CAPITAL CARRYING CHARGE FACTOR AND O&M
LEVELIZATION FACTORS WERE CALCULATED FROM THE
ECONOMIC FACTORS LISTED ABOVE AND OTHER FACTORS
LISTED IN THE ECONOMIC SECTION.
ITEM QUANTITY RATE ANNUAL COST
======
OPERATING AND SUPERVISORY LABOR
+______
SYSTEM .162E+06 MANHR 25.86 $/HR $ 4187500
MAINTENANCE LABOR .919E+07 $ .40 $ 3677700
MAINTENANCE MATERIAL .919E+07 $ .60 $ 5516500
PERCENT OF TPC = 2.35
ADMIN. & SUPPORT LABOR .787E+07 $ .30 $ 2359600
CONSUMABLES
+______
COAL USE .120E+07 TONS .00 $/TON $ 0
SOLIDS DISPOSAL, DRY .299E+06 TONS 12.19 $/TON $ 3646000
WATER .949E+06 K GAL .79 $/K GAL $ 747600
ELECTRICITY .139E+09 KWH 65.63 mil/KWH $ 9090800
LIMESTONE .128E+06 TONS 19.69 $/TON $ 2525900
LIME .353E+03 TONS 72.19 $/TON $ 25500
UREA .721E+04 TONS 483.02 $/TON $ 3484400
0
FIXED COMPONENT .175E+06 KWY 89.95 $/KWY $ 15741300
VARIABLE COMPONENT .138E+10 KWH 14.15 mil/KWH $ 19520200
TOTAL FIRST YEAR O&M EXPENSE $ 35261500
LEVELIZED CARRYING CHARGES 435671700 $ 16.55 % $ 72101800
BUSBAR COST OF POWER $ 107363300
LEVELIZED FIRST YEAR O&M 35261500 $ 1.61 $ 56827200
LEVELIZED CARRYING CHARGES 435671700 $ 16.55 % $ 72101800
LEVELIZED ANNUAL REQUIREMENTS $ 128929000
FIRST YEAR BUSBAR COST OF POWER 77.82 MILLS/KWH
LEVELIZED ANNUAL BUSBAR COST OF POWER 93.45 MILLS/KWH
COST/TON OF PARTICULATE REMOVED 958.86 $/TON
COST/TON OF SO2 REMOVED 5143.43 $/TON
COST/TON OF NOX REMOVED 22721.13 $/TON
1