PBR REGISTRATION overview
Any owner or operator of a nonmetallic mineral processing plant (rock crushing plant) that opts to operate under a PBR needs to meet all the requirements set forth in Sections 795–799 of IDAPA 58.01.01, Rules for the Control of Air Pollution in Idaho (Rules). These rules include requirements to use best management practices and specifies monitoring and recordkeeping. The current rules can be accessed on the Department of Administration’s website at When registered with a PBR, a Permit to Construct is not required.
Rock crushing plants that operate or may be operated at a single location or site for more than twelve (12) consecutive months do not qualify for a PBR and must obtain a permit. The Permit to Construct application for rock crushers can be obtained from the DEQ website at
pbr registration instructions
- Registration Form:Complete the attached PBR registration. This registration covers only one rock crusher plant. Owners that operate more than one plant at a time need to register each plant individually. Serial numbers are required for crushers and screen decks; however, if the equipment does not have a serial number, put “N/A” in the Serial No. column.
- Portable Equipment Relocation Form:Complete the Portable Equipment Relocation Form (PERF). An electronic copy of the PERF can be obtained from the DEQ website at It is important to be aware that in addition to being submitted with this PBR registration, a PERF must be completed and filed at DEQ at least 10 days in advance of relocating any of the equipment covered in this registration.
- Fees:In accordance with the Rules for the Control of Air Pollution in Idaho (IDAPA 58.01.01.800), DEQ cannot process this registration unless it is accompanied by a two hundred fifty dollars ($250) registration fee. Thecurrent rules can be accessed on the Department of Administration’s website at
- Mail or Submit:Please mail or submitthe completed PBR registration, PERF form, and the PBR registration fee of two hundred fifty dollars ($250) to the address below. PBR processing cannot commence without payment.
Idaho Department of Environmental Quality
Attn: Air Quality Program
1410 North Hilton
Boise, ID 83706-1255
- Payment: Payments can be in the following formats.
If paying with a check, make the check payable to the Idaho Department of Environmental Quality, and send or include it with the completed application to the address above.
If paying with a credit card or E-check, payment can be made at (Note: Convenience fee of 3% applies to credit card payments, $5 to E-check payments.)
If paying by bank wire transfer, contact Katie Bennett, DEQ Fiscal Office at or by phone at (208) 373-0446.
The Department will acknowledge registration in writing within fifteen (15) days.
Please see instructions on page 1before filling outthe form.
GENERAL INFORMATION
Company Name:Mailing Address:
City: / State:
Zip Code: / County:
General Nature of Business & Products:
Contact Name, Title:
Phone: / Cell:
Email:
Owner or Responsible Official Name, Title:
Phone:
Email:
Proposed Initial Plant Location:
Nearest City: / Estimated Startup Date:
County:
Reason for Application: / Register an unpermitted/unregistered source
Cancel a permit and obtain a PBR
Add, remove, or edit equipment listed on an existing Permit By Rule, Facility ID No.
If the equipment included in this registration is currently permitted, you must request cancellation of the current permit(s) by completing the following table:
PERMITS TO BE CANCELLED
PermitType(PTC, Tier II) / Permit No. / Permit Issuance Date
Comments:
EQUIPMENT INFORMATION
Include in the tables below all the equipment covered by this PBR including new equipment, existing equipment from a previous registration, and equipment to be removed from a previous registration:
Note: If the equipment does not have a serial number, put “N/A”in the Serial No. column.
ROCK CRUSHERS AND GRINDING MILLS
Crusher/Grinding Mill Type
(jaw, cone, rod mill, etc.) / Crusher Classification (Check one) / Manufacturer / Serial No. / Date of
Manufacture / Maximum Throughput Capacity
(tons per hour) / Equipment Action
(Check one)
Primary / Secondary / Tertiary / New / Existing / Remove from Existing
SCREEN DECKS
Manufacturer / Physical Size(length x width)
(feet x feet) / No. of Decks / Serial No. / Date of Manufacture / Equipment Action
(Check one)
New / Existing / Remove from Existing
ELECTRICAL GENERATOR(S)
Manufacturer(Caterpillar, Onan, etc.) / Rated Output
(kW) / Fuel Type
(Grade 1 or 2 Fuel Oil) / Equipment Action
(Check one)
New / Existing / Remove from Existing
$250 PBR registration fee enclosed
Certification of Truth, Accuracy, and Completeness (by Responsible Official)
I hereby certify that based on information and belief formed after reasonable inquiry, the statements and information contained in this and any attached and/or referenced document(s) are true, accurate, and complete in accordance with IDAPA58.01.01.123124.
Responsible Official Signature
/Responsible Official Title
/Date
Print or Type Responsible Official NamePage 1