-----Original Message-----
From:
Sent: 18 May 2009 13:10
To: Tina Rowley
Subject: RE: West Oxfordshire Core Strategy So Far - Interim Position

Hi Tina,

I respond to each of your additional questions below.

Q.You have referred to the Thames Water business plan 2010-15. Do you have a

schedule of proposed Thames Water schemes in West Oxon that you could

forward please?

A.Minor upgrades to Witney and Woodstock Sewage Treatment Works are proposed

between 2010 and 2015 in our business plan submission to Ofwat (our

regulator). However The Final Determination our Business Plan is not due

until later this year so we wont know whether we have the funding secured

to deliver these projects until then.

Q.You referred to the Brize Norton SPS and Carterton STW - what is the

difference please?

A.The asset referred to as Brize Norton SPS is a sewage pumping station. We

have a number of pumping station located all around the sewage network for

the purpose of pumping sewage. Carterton STW is the sewage treatment works.

Q.There is reference to the Chipping Norton reservoir site - I assume this is

Tank Farm?

A.As far as Thames Water are aware this is just know as Chipping Norton

Reservoir. There is a tank on the site so we are presuming it may be known

locally as Tank Farm.

CARTERTON

Q.If the District Council were to support further growth at Carterton (ie

1,000+ houses over and above provision identified in the Core Strategy So

Far document) am I right to assume that the lack of sewerage capacity is

not an objection in principle but more a matter of timing and funding for

the upgrades required? As there is no provision in your current business

plan could additions be made? Or is it a matter of any future development

of this scale being identified for a time period post 2016 because of the

infrastructure needing to be funded and implemented (funding by Thames

Water and/or developers)?

A.Thames Water will not be able to obtain additional funding in the business

plan 2010 to 2015 as our plan has already been submitted to our regulator

for a decision but we may have the opportunity to seek funding for the

period of 2015 to 2020 through our next business plan review known as

PR014.

As there are capacity constraints with the local sewerage network and

treatment works with associated potential amenity impact, if the

additional 1000 dwellings are allocated and the site(s) comes forward

ahead of any programmed infrastructure by TW, then planning permission

should only be granted where the developer(s) funds the appropriate

infrastructure improvements, with the infrastructure improvements completed

prior to occupation of the development(s).

If this level of growth is the preferred option then the bullet points

above should be clearly laid out in the Core Strategy for the policy on

growth for Carterton.

I hope the above is of assistance.

Kind regards

MARK

Mark Mathews

Senior Planner

Thames Water Property Services

-----Original Message-----
From:
Sent: 06 May 2009 09:59
To: Tina Rowley
Subject: West Oxfordshire Core Strategy So Far - Interim Position

Hi Tina,

I set out our comments on the different sites below.

If you have any queries please do not hesitate to contact me.

Kind regards

MARK

Witney

Q.As you know the Council has indicated a preference for about 1,000 new

homes and employment development to the west. In response to consultation,

a proposal has been received for about 450 new homes on the eastern side of

the town which it is argued could be in addition to major development to

the west (or north). As regards the northern area, the agents are arguing

for a major development of up to 1,600 dwellings with supporting

facilities. Their submitted statement says: 'Although the site is some

distance from the Thames Water WWTW at Ducklington and gravity drainage

would not be feasible, it will be feasible to provide a pumping station on

site with a rising main to pump the sewage to the existing Dark Lane

Pumping Station. Thames Water has previously indicated this would need to

be upgraded with a new rising main to take the additional sewage flow

onwards to the WWTW. The estimated cost will be in the region of

£1million'.

Do you have any comments on the above in relation to feasibility and

timing? Would development in the North Witney area involve upgrading

existing sewers through the historic part of the town? Does the WWTW have

sufficient capacity to serve significantly more than 3,000 dwellings at

Witney during the years 2006-2026?

SEWAGE

Witney STW.

At present, based on the existing EA consent, Witney STW has capacity toaccommodate an extra 8000 Population Equivalent. However, when the newEnvironment Agency effluent consent becomes effective the works willrequire upgrades to treat the same incoming flow to a higher quality.

There is a project planned in AMP5 (our business plan period 2010 to 2015)

that will provide the capacity to meet the new consent when it comes in.

This same project will also look to provide room for growth according to

the growth projections current at that time. Capacity at the works is

therefore unlikely to be an issue if our plans are approved by Ofwat.

Northern Development Area (1,600 dwellings).

To drain this development, potentially a new Sewage Pumping Station (SPS)

to pump to Dark Lane SPS could be feasible. Dark Lane SPS will require an

upgrade to accommodate the flows. This has not been specifically included

in our final business plan submission to Ofwat and therefore it will have

to compete for growth funding against other growth risks across Thames

Water's catchment. A study to review rising main routes, costs,

timescales etc would be needed. The existing rising main does not appear

to pass through the historic (conservation) areas of Witney.

Eastern Development Area (450 dwellings).

This development would drain to Cogges SPS which also has no spare capacity

and is also not identified in the final business plan. Local sewer

upgrades are likely to be required.

Western Development Area (1000 dwellings plus employment).

It is unlikely that this level of development could be accommodated within

gravity network. Development could connect directly to Ducklington Lane

SPS but upgrades are likely to be required to do this, or, potentially

there may be an option for a new sewer to be pumped direct to the STW.

WATER

Due to the complexities of water networks it is difficult to predict

exactly the needs of new developments without detailed locations, numbers

and phasing information. It will require computer modelling funded by

developers before these answers can be provided

Carterton

SEWAGE

Q.As mentioned in the consultation document, Carterton Town Council is

seeking further substantial growth in the town. We have received the

attached proposal from Savills (first attachment) for about 1,000 new homes

on land between the town and Brize Norton village.

A.This development would drain to Brize Norton SPS which is currently under

capacity. Therefore SPS and network upgrades are likely to be required. No

specific provision is made for this in our final business plan submission.

Q.Land to the north of the town has also been put forward for consideration

but no details are provided. Bearing in mind your comment about a

requirement for significant wastewater infrastructure upgrades, could you

please clarify what would be required for an extra 500 dwellings above

commitments (as set out in the Core Strategy consultation document) and for

an additional 1,000 dwellings above that level. Are there any implications

for Thames Water if those extra 1,000 dwellings were to the north, east or

west of the existing town boundaries?For further context you might wish to

look at the housing land assessment for Carterton published in conjunction

with the Core Strategy So Far consultation document - see

A.The terminal SPSs are overwhelmed in wet weather, and therefore which ever

development comes forward network upgrades will be required. Caterton STW

will also require an upgrade. Development to the south of the town would

enable a direct connection to the STW.

WATER

Due to the complexities of water networks it is difficult to predict

exactly the needs of new developments without detailed locations, numbers

and phasing information. It will require computer modelling

Chipping Norton

Q.Taking into account your comments on wastewater and cleanwater please see

the second attachment (extract from submitted RPS document)which proposes

up to 400 new homes plus employment development to the east of the town.

Our assessment for Chipping Norton (same website link as above) suggested a

less extensive area for development may have potential. Do you have any

further comments to make please?

SEWAGE

Chipping Norton drains from East to West. Sewers on the eastern fringe are

at the head of the catchment and are small. Flows from 400 homes exceeds

the maximum theoretical capacity of any one of these sewers. A modelling

study would be needed to determine the impact and the most appropriate

solution.

WATER

Significant investment is due to take place at the Chipping Norton

reservoir site in the next AMP period which would negate its release for

development. Due to the complexities of water networks it is difficult to

predict exactly the needs of new developments without detailed locations,

numbers and phasing information. It will require computer modelling

Mark

MARK MATHEWS

Senior Planner

Thames Water Property Services Ltd