Piney Point Village

Batch # 1 Progress Report

for MAY 2013

BATCH # 1 PAVING & DRAINAGE
IMPROVEMENTS PROJECT

HEDWIG ROADWAY

IMPROVEMENTS

HARRIS COUNTY, TEXAS

Weekly Progress Report

HDR| Engineering Inc.

Project No.10-041

Week Ending

JUNE 14, 2014

Submitted to

Piney Point City Council

4635 Southwest Freeway, Houston TX 77027-7169

(713) 622-9264. Fax (713) 622-9265. www.hdr.com

Page 2 of 4

Hedwig Roadway Improvements

Project Progress Report for

Week ending June 14, 2014

June 8, 2014 to June 14, 2014

Activity/Status

HEDWIG ROADWAY IMPROVEMENTS

MOBILIZATION:

·  Continue delivering the 72-inch RCP.

PAVING ITEMS:

·  Continue to cut and remove sections of Hedwig road from the bridge to the north for storm sewer line installation (west side of Hedwig Road).

DRAINAGE ITEMS:

·  Completed placement of the 6’ X 6’ concrete box culverts.

·  Continue placement of the 72-inch RCP Installed 219.5 LF for a total to date of 444.5 LF. Out of 934 LF. (48% completed)

·  Installed 8’ X 4’ conflict junction box at Hunters Park.

WATER ITEMS: AAA Paving

·  This period no work was performed on this aspect of the project at this time.

TREE PROTECTION:

·  Installed the tree fencing around the trees on Hedwig Rd.

SUPPLEMENTAL ITEMS:

·  Installed a casing pipe and a new 8-inh sewer lines through the conflict box at Hedwig Court.

June 8, 2014 to June 14, 2014

Activity/Status

HEDWIG ROADWAY IMPROVEMENTS

Contractor is placing the new 72-inch RCP on Hedwig road. View to the south.

The contractor is installing the fence post for the tree protection fencing. View to the south.

The contractor is placing the tree protection fencing around the trees on Hedwig Road. View to the south.

The contractor is setting the 78-inch RCP in the ditch for the new storm line on Hedwig Road. View to the north.


Next Week’s Planned Activities

June 15, 2014 to June 21, 2014

Batch # 1 Paving & Drainage IMPROVEMENTS

MOBILIZATION:

·  Continue to deliver 72-inch RCP.

PAVING ITEMS: AAA Paving

·  Continue to remove the existing roadway and base material.

DRAINAGE ITEMS: AAA Paving

·  Continue placement of the Junction boxes for the new storm line.

·  Continue the placement of the 72-inch RCP.

WATER ITEMS:

·  This period no work was performed on this aspect of the project at this time.

TREE PROTECTION:

·  Initiate placement of the Tree Protection.

SUPPLEMENTAL ITEMS:

·  This period no work was performed on this aspect of the project at this time.

\

Next Week’s Planned Activities

June 15, 2014 to June 21, 2014

Batch # 1 Paving & Drainage IMPROVEMENTS

Setting the 72-inch RCP down Hedwig Rd. Safety trench box install to keep the pipe trench from caving in on workers. View to the north.

.

Note: Hedwig road is now one way to the north and has been for over a week. A number of drivers continue to drive south bound. PLEASE STOP. This is dangers to other motorist and the construction workers on site.

Memorial Village Police Dept. has been ask to help with this problem. This is a contraction zone area please follow the signs.

Page 2 of 4