General Services Department
Property Control Division
Building Services Division
Facility Max Close Out Phase
Project Abstract
10/8/2009
FacilityMax Executive Governance / Steering Committee
1
1
Project benefits, milestones achieved and/or accomplishments:
Benefits
The benefits of implementing the FacilityMax project include:
- Increase efficiency and productivity through the implementation of modules that meet BOSOMM business processes and requirements
- Replace legacy end-of-life, non-supported systems
- Implement redundant hardware
- Implement reporting tool
- Implement central repository
- Improve service delivery to constituency
- Realize a reduction in error rates
Milestones Achieved and/or Accomplishments
•Initiation Phase:
–Project Management Plan Developed
–Purchase FacilityMax Software
•Planning Phase
–Determined Implementation Priority
–Identified Resource Requirements: Technical Support , Vendor Expertise, Training and Security
–Developed As-Is and To-Be Work Process Flows for Business re-Engineering
–Developed Implementation Plan documents, Training Plan Project Schedule and Work Breakdown Structure,
•Implementation Phase
•Develop/Build
•Set-up Database
•Input Data
•Train End Users
•IV&V
•Implement Reports
•Test, User Acceptance
•Move to Production
•Stabilization Period/Monitor and Control
Next Steps
•Close
•Develop DoIT Closure Report
•Project Closure Archive
•IV &V Close out report
•Post Mortem
Certification History (Include any previous project or phase certifications)
Date
/ Amount / Funding Source(s) (use specific citations to laws, grants, etc.)May 28, 2007 / $378,269.00 / Property Control Division
Capital Project Administrative Fund (15-3B-10 Capital Projects; Administrative Fees NMSA 1978)
May 28, 2007 / $434,600.34 / Building Services Division
HB2 General Fund – Operating Budget
Oct 21, 2009 / $-0-
Technical Architecture Review:
- Architectural Design Review was presented to DoIT and verbal approval was received.
Proposed Project Phasing / Budget
Phase / Summary of Phase / BudgetInitiation / Formal authorization to start project or project phase. Business needs and system requirements are documented and solution options are evaluated. / $333.6
Planning / Involve all identified stakeholders in planning and organizing a successful project. Identify, define and mature the project scope, project cost and project schedule. Identify and/or resolve dependencies, requirements, risks, assumptions, constraints, and strategies. Plan methods for monitoring and controlling the activities thru the project life. / $129.2
Implementation/ Execution / Complete the work defined in the Project Management Plan. Complete software installation, set up database and input data, train end users and sys admin, test, user acceptance conduct IV&V / $266.7
Monitor and Control / Perform processes to observe project execution so that potential problems can be identified in a timely manner and corrective action can be taken, when necessary, to control the execution of the project.
Close / Formally terminate all activities of a project or a project phase and hand off the completed product to others. / $-0-
1