Top of Form
HomeSee All Services
The form available on this page is not saved and submitted to MIDC online.
If you need to submit the forms online to MIDC, please register here or login using your login credentials.
On this page, you can fill the form and print it for submitting to MIDC physically.
Plot Details
Fields marked with (*) are mandatory.
Applicant Information
* / Name / : / Enter valid nameEnter Name of Applicant
Address / : / Upto 500 characters.
State / : / / District / : /
City/Town / : / Invalid name / PIN / : /
Contact Phone / : / Invalid Phone No. / * / Contact Mobile / : / Please enter valid mobile number
Education Qualification / : / / Special Category / : /
* / Contact Email / : / Invalid Email / Preference Category / : /
Registered Office Details
* / Company Name / : / Enter valid nameEnter Company Name
Address / : / Upto 500 characters.Enter valid Address
State / : / / District / : /
City / Town / : / Invalid name / PIN / : /
Phone / : / Invalid Phone / Fax / : / Invalid Fax
Website / : / Invalid URL / * / Constitution Type / : /
* / Contact Email 1 / : / Invalid Email / Contact Email 2 / : / Invalid Email
Note: Contacts will receive email alerts on Government of Maharashtra Queries & Processing at the above email addresses.
Plot Details
Plot Location / : / / Key Person Responsible For Management? / : /
District of present unit / : /
* Industrial Area of present unit / : /
Please select the Industrial Area
Note:- Please enter plot number in the format "Block Number-Unit Number." Use "-" as separator between the Block Number and the Unit Number.
Mention plot no. with no block number as : "123"
Mention plot number with block number alloted as : "C-123"
For multiple adjacent plots, please mention all the plot numbers separated by a "," as : A-1,A-2,A-3,A-4,A-5,A-6,A-7
* Present Property No. (Plot/Shed/Gala) / : /
Enter valid Plot No. Special Characters are not allowed. / * Area in m2 / : / Enter numeric or decimal value upto 50000000.00.
Product manufactured
Raw Material
Employment Details
Entrepreneurs profile
Approval already taken by the enterprise
Equity Details
Self/ promoter capitals Value(In Lacs) / : / Enter Valid Promoter Capital Value / Self/ promoter capitals % / : / Enter numeric or decimal value upto 100.
Secured Loans in value(In Lacs) / : / Enter Valid Secured Loan Value / Secured Loans in % / : / Enter numeric or decimal value upto 100.
Unsecured Loan in value(In Lacs) / : / Enter Valid Unsecured Loan Value / Unsecured Loan in % / : / Enter numeric or decimal value upto 100.
Foreign equity (in % ) / : / Enter Valid Foreign equity
Plot/Unit Contact Information
Unit Phone No. / : / Invalid Phone / Unit Fax No. / : / Invalid Fax
Unit Email Address / : / Invalid Email
* Proposed no. of workers - direct employment / : /
Enter valid Plot No. Special Characters are not allowed. / * Will labour contractor be engaged? / : / Please mention whether labour contractor be engaged.
* Pollution category of Industry / : / Please select the category of pollution / * Power Requirement / : / Please mention whether there is requirement for power.Enter valid Plot No. Special Characters are not allowed.
* Is boiler being installed? / : / Please mention whether boiler is installed. / * Built up area (in sq. mtrs.) / : / Please enter numbers onlyEnter built up area
* Project Investment (in Cr.) / : / Please enter numbers onlyEnter investment in plant & machinery / * Size of Industry / : /
* Stage / : / Select stage of industry / * Availbility of Own Land / : / Please mention whether own land is available.
* Type of Proposed / Existing Land / : / Please mention type of land proposed. / * Zone of Proposed / Existing Land / : / Please mention zone of land proposed.
* Water Requirement (in cubic mtr / day) / : / Please enter numbers onlyEnter water requirement / * Requirement of Water Reservation / : / Please mention zone of land proposed.
* Type of employees existing/proposed / : / Please mention type of employment of employees existing/ proposed. / * Finance Requirement for Project / : / Please mention whether finance is required.
* Interested in availing Incentives from GoM / : / Please mention whether interested in availing incentives from GoM.
* / Type of Industry/Activity / : / Details, If others Enter valid Type Of Activity
Main Manufacturing Activities / : /
EM / IEM / LOI Acknowledge Number / : /
Date of Acknowledgement / : / Invalid date format
APPENDIX IX - Forms
Form No. 1
Form for Application for Development and to Erect a Building
(On Rs.100 Stamp) As stipulated from time to time by Suptdt. of Stamps
To,
The Executive Engineer
Sir,
I hereby give notice that I intend to carryout development in the site to erect/ to reerect/ to demolish/ to make material alteration in the building on/ in Plot No.. , at Industrial Area.
I forward herewith the following plans and statements (Item 1to 6 ) in quadruplicate, wherever applicable, signed by me and
(Name in block letters)*the Licensed Surveyor/ Engineer/Structural Engineer/ Supervisor or
Architect Licence No. *who have prepared the plans/design and a copy of other statements/ documents as applicable.
1. Items
1. Agreement to Lease / Deed of Possession
2 Possession receipt
3 Drawings in metric system which should include Block Plan. Typical Floor Plan, Elevation Plan etc. An AutoCAD drawings CD should be submitted along with drawings. If the drawings are prepared in Pre DCR utility then also CD should be submitted to this office.
Block Plan of company should give the details of main entrances, other entrance to plot, surrounding of plot like any other company, road, etc. Marginal space, approach roads around the plant, capacity of underground water storage tank and the details like transformer yard, utility block, raw material and finish goods, storage, tank farm area, storage of hazardous gases, etc. e.g. details of Basement LPG, A-class petroleum products, LDO etc.
Elevation Plan and Typical Floor Plan showing exits, Fire escapes, travel distance along the travel line, terrace level water storage, location of fire duct, fire extinguishers, hydrant system, sprinkler system, alarm system etc. Details of Basement, Sub Basement, their ventilation system and exits.
4 Form of Supervision from Architect Refer MIDC D.C.Rules : APPENDIX IX - Form No. 2
5 Form of appointment of Structural Engineer Refer MIDC D.C.Rules : APPENDIX IX - Form No. 11
6 Form of acceptance by Structural Engineer Refer MIDC D.C.Rules : APPENDIX IX - Form No. 12
7 Form of supervision by Structural Engineer Refer MIDC D.C.Rules : APPENDIX IX - Form No. 13
8 MPCB Consent (if applicable)
9 Letter of Extension of Time Limit (if applicable)
10 Fire NOC
11 LOI from Director of Ind. regarding IT Part/Units (if applicable)
I request that the proposed development/Construction may be approved and permission accored to me to execute the work.
Signatue of Licensee/ Lessee
Copyright © 2013 Maha-E-Biz ® All Rights Reserved.
This site is best viewed with Internet Explorer 6.0 or higher at a minimum screen resolution of 1024x768
Bottom of Form
Form No.1(Prescribed under Rule 3 of Maharastra Factories Rules, 1963)
Application for permission to construct new factory, to extend existing factory
and to take into use an existing building as a factory
UTN :
Factory Status :
1 Full name of the factory (in English) :
Postal address of the factory :
2 Location of the factory
Province :
District :
Town or village :
Nearest police station or steamer ghat :
3 Particulars of the plants to be installed :
Other Information
Architect's name :
Architect's address :
Is shared premises? :
1 GENERAL
Have the site and plans of your factory building/extension been
approved by the Municipality or the local health authorities?
If so, please send a copy of the approval letter.
:
i)
:
Are the necessary drawings as mentioned in the General Note
submitted in duplicate with the principal dimensions shown in
the drawings?
(Drawings should be self-explanatory.)
ii)
iii) Is Statistical Form attached, submitted, duly filled in for all
work-rooms, godowns, offices etc., which are proposed to be
constructed or extended?
:
iv) Has the work commenced? :
v) Will be the total maximum number of workers
employed per day (including all shifts) in the entire
factory?
:
Male Female Total
vi) What will be maximum number of workers working
in the entire factory at any one time ?
Male
:
Female Total
vii)
:
Are all work-rooms not more than 18 metres wide?
Note :- If not, provision of efficient forced draught ventilation
will be insisted upon in respect of any such work-room and
details of this, viz., capacity of the forced draught fans,
resultant air changes per hour, proposed to be obtained
Should be furnished.
Page 1 of 8 07/03/14 05:50
This document was created using an EVALUATION version of ActiveReports. Only a licensed user may legally create reports for use in
production. Please report infractions or address questions to . Copyright © 2002-2011 GrapeCity, inc. All
rights reserved.
vii)
:
Are all work-rooms not more than 18 metres wide?
Note :- If not, provision of efficient forced draught ventilation
will be insisted upon in respect of any such work-room and
details of this, viz., capacity of the forced draught fans,
resultant air changes per hour, proposed to be obtained
Should be furnished.
viii)
:
Are all work-rooms with windows on both the outer (longer)
walls?
Note :- If not, provision of efficient forced draught ventilation
will be insisted upon in respect of any such work-room and
details of this, viz., capacity of the forced draught fans,
resultant air changes per hour, proposed to be obtained should
be furnished.
ix)
:
Are there any hot processes or those giving off fumes and / or
dust proposed to be carried out?
If so, please indicate how the nuisance is proposed to be
eliminated or minimized?
2 Roof
i) Type of roof :
:
Material to be used for roof covering (It should be noted that
the minimum height from floor to the roof should not be less
than 3.75 metes)
Note :- Galvanised iron sheet or asbestos cement sheet is not
acceptable as roof material unless it is covered with tiles or a
false ceiling of heat resisting material is provided below or at
increased minimum heights as approved by the Chief
Inspector of Factories.
ii)
3 Walls
i) What will be the material used for the construction of the walls? :
ii) Will the walls be plastered smooth inside?
Note :- C.G.I. and A.C. sheets are not acceptable as wall
material, either in cladding or louvre forms unless they are
at such heights from any working levels as approved by the
Chief Inspector of Factories.
:
4 Floor
i) What will be the material used for flooring? :
5 (Please fill in the attached statistical Form in respect of every work-room, office,godown etc.)
Note :-
i) Sill height of windows at working level should not exceed 1 (one) metre.
ii) Please state whether all the windows are fully openable. If not, what is the percentage of such
windows are openable?
6 Doors
i) Is the minimum size of every door affording exit from
work-room, office etc. (195 centimeters x 90 centimeters)
Page 2 of 8 : 07/03/14 05:50
This document was created using an EVALUATION version of ActiveReports. Only a licensed user may legally create reports for use in
production. Please report infractions or address questions to . Copyright © 2002-2011 GrapeCity, inc. All
rights reserved.
i) Is the minimum size of every door affording exit from
work-room, office etc. (195 centimeters x 90 centimeters)
:
ii) Are all the doors affording exit from work-rooms, office etc.
(except those of the sliding type) opening outwards or in the
directions of the nearest exit?
:
7 Emergency Exits
Are at least two exits provided for every work-room, office etc.
situated apart and conveniently accessible in case of an
emergency? [vide Rule 70(1)(a)]
Is any part of the factory building above or below the level of
the ground floor?
[vide Rule 70(1) (c), (d), (e) and Rule 70(2)]
ii)
i)
:
:
If so, is it provided with two or more separate and substantial
stairways of prescribed type which offered direct access to the
ground level?[vide Rule 70(1) (c), (d), (e) and Rule 70(2)]
:
8 Latrines and Urinals
i) Are these in accordance with the requirements of section 19
read with rules 45 to 53 ? :
i) (a) Is separate enclosed accommodation provided for males
and females? :
i) (b) Please state the number of Latrines provided for
:
i) (c) Please state the number of Urinals provided for Males:
:
Existing Proposed
Male
Female
Existing Proposed
Note :- The above information should clearly show the existing and the proposed latrines and urinals
accommodation.
iii) Are glazed tiles or similar impervious material used in laying
the floors and walls up to a height of one Meter of the
latrines and urinals and the sanitary blocks?
[vide Section 19 (2) (b)]
:
Note :- Basket-type latrines are not permitted.
iv) Are latrines of :
ii) Is the proposed accommodation approved by the Health
Department?
:
Are the latrines and urinals connected to sewage system as
required under Rule 50?
v)
:
If no drainage system exists, is an efficient system of septic
tanks provided?
vi) : Page 3 of 8 07/03/14 05:50
This document was created using an EVALUATION version of ActiveReports. Only a licensed user may legally create reports for use in
production. Please report infractions or address questions to . Copyright © 2002-2011 GrapeCity, inc. All
rights reserved.
viii) Has provision been made for trade waste disposal? :
Note :-
1) Latrines and urinals communicating with work-room, office etc. Cannot be accepted [vide Section
19(1)(c)].
2) It is in the management's own interest to distribute the latrines and urinals over different areas of large
factories rather than concentrating them in one single block.
If no drainage system exists, is an efficient system of septic
tanks provided?
vi) :
Is sufficient number of water taps provided near this
latrines?
vii) :
9 Wash Places
Are the proposed wash places in accordance with the
requirements of section 42 read with rule 74?
i)
:
Is separated enclosed accommodation provided for males
and females?
ii (a) :
Please state the number of proposed taps on stand pipes, wash basins and bath-rooms for the use of
males and females separately.
ii (b)
Existing Proposed
Stand pipes
Wash basins
Bath-rooms
M F
M F
M F
M F
M F
M F
Note :- 1) The above information should show clearly existing and proposed accommodation.
2) Wash places located in the vicinity of latrines and urinals are not accepted
[vide Rule 69(2)].
3) It is in the management's own interest to distribute the latrines and urinals over different areas of large
factories rather than concentrating them in one single block.
10 If you factory is situated in a common compound covered under Section 93 of Factories Act,
1948, please fill in the form attached to this Questionnaire.
1 Name of the owner of the compound :
Address of the owner of the compound :
Maximum number of workers working at a
time in all the factories situated in the
compound :
:
Males :
Females :
Number of latrines provided in the compound :
Males :
Females :
2
3
APPENDIX
Page 4 of 8 07/03/14 05:50
This document was created using an EVALUATION version of ActiveReports. Only a licensed user may legally create reports for use in
production. Please report infractions or address questions to . Copyright © 2002-2011 GrapeCity, inc. All
rights reserved.
i) Is cloak-room provided for workers? If so, state the area. :
Number of wash places provided in the
compound :
Maximum number of workers working at a
time in all the factories situated in the
compound :
:
Males :
Females :
4
5
Note :- Separate enclosed accommodation shall be provided for female workers.
Note :- It would be preferable, if in addition to supplying information under items (2) to (5) above you obtain a certificate
to that effect from the owner of the compound and attach a copy thereof.
6 Is no objection letter from the owner of the
compound, allowing to start or extend a
factory for the purpose under reference
obtained?
If so, please attach a copy.
:
11 Cloak Room
Is separate cloak-rooms provided for female workers? If so,
state the area.
ii) :
iii) Will lockers be provided for workers? :
Are the arrangements made for drying of wet clothing?
(Please see Rule 75)
iv)
:
12 Canteen
i)
:
Are the plans of the canteen submitted in duplicate to the Chief
Inspector of Factories for approval?
(Applicable to factories where more than two hundred and fifty workers are ordinarily employed.)
:
Is proposed canteen in accordance with the requirements of
section 46 read with rules 79 to 85?
ii)
:
Is the floor area of the dining hall calculated at the rate of 1 sq.
metre per dinner for 30 per cent of the maximum number of
workers working at any one time?
iii)
Please state maximum number of workers working at any time and the floor area of the dining hall in
each section.
iv)
Page 5 of 8 07/03/14 05:50
This document was created using an EVALUATION version of ActiveReports. Only a licensed user may legally create reports for use in
production. Please report infractions or address questions to . Copyright © 2002-2011 GrapeCity, inc. All
rights reserved.
Maximum number of workers Floor area of the dining hall
Male
Female
v) Is separate enclosed accommodation provided in the dining hall
for female workers? :
vi) Are doors and windows of the Canteen made fly-proof? :
Is the proposed Canteen situated at a distance of not less than
15 metres from latrines,urinals, boiler house, coal stock, ash
dumps or any other source of smoke or obnoxious fumes?
:
vii)
13 Shelters, Rest Rooms and Lunch Rooms
(Applicable to those factories wherein more than 150 workers are ordinarily employed.)
Note :- It should be noted that the provision of shelter and lunch room required under section 47 is distinct
from dinning hall of the Canteen required under section 46
i) Are the plans of the proposed work submitted in duplicate to
the Chief Inspector of Factories for approval? :
ii) Is the proposed work in accordance with the requirements of
section 47 read with rule 86? :
iii) Is the proposed shelter, rest room and lunch room conveniently