ELECTRICAL TESTING AND AUTOMATION DIVISION MONTHLY ACTIVITY REPORT

MONTH: September YEAR: 2007 / Page No. 2 of 9

I.  ET & A METERING / PROTECTION / TESTING / COMMISSIONING SECTION.

A.  PERFORMANCE INDICES: -

Sr. No. / INDICES /
This month Sept 07
/ Sept 06 / YTM- FY 07 / YTM- previous year / Target
1 / Protection Performance Index (%) / 100 % / 100 % / 98.58 % / 99.0% / 98.9 %
2 / Protection Diagnostic testing Index (%) / 3.92 % / 4.19 % / 30.18% / 33 % / 50.00 %
3 / Equipment Diagnostic testing Index (%) / 1.47% / 2.16 % / 19.69% / 27 % / 50.00 %
4 / Energy meter Diagnostic testing Index (%) / 55.79% / 55.02 % / 55.79 % / 55.02 % / 100 %
5 / External Customer Complaint Resolution Time (Avg.) in Days / 2.44 / 1.71 / 2.40 / 2.75 / 3.00
6 / Customer Complaint Satisfaction Index (on the scale of 0 – 5) / 4.88 / 4.45 / 4.60 / 4.52 / 4.65

B.  ACCEPTANCE TESTING IN LAB:-

ETA LAB / TOTAL / ACCEPTED / REJECTED / REMARKS
No. of Relays/jobs Tested in Relay Lab. / - / - / -
No of Meters in Meter (Saki + Trombay) Lab. / 20 / 20 / 0
No. of CT / PT tested in HT Lab. / - / - / -
No. of Instruments Tested in HT/ RLY Lab. / - / - / -
No. of Oil Sample Tested in Oil Testing Lab. / - / - / -
Calibration of Testing instruments / - / - / -

C.  MAJOR COMMISSIONING: -

1 / Energy Meters Commissioning / Meters /
Commissioned In this month
/ Cumulative up to this month
Whole Current / 0 / 0

CT Based

/ 0 / 0
TVM / 0 / 23
2 / Consumer Sub Stations Commissioning / ·  6/9/07:Deemed University (BARC), 3 way RMU, CT/PT unit
·  7/9/07: Gold Star (Seepz), 3 way RMU, CT/PT Unit
·  14/9/07: JM House, 3 way RMU, CT/PT Unit, 1250KVA transformer, Feeder Pillar
·  18/9/07: Godrej, 3 way RMU
·  22/9/07: Dawn Mills, 3 way RMU
·  24/9/07: Fiat, 3 way RMU
·  22/9/07: New flair relay type 22D received and tested OK. To replace old flair relays shortly, Old flair relays were malfunctioning and hence unreliable.
·  ICICI, LT breaker relay type STU33 replaced with STU34 and neutral CT added, To prevent tripping in case of unbalance current
3 / Equipment Commissioning. / ·  Trombay A :-
·  24/9/07: Coal yard, 6.6 kV Swgr re-commissioned at new location ( New coal yard control room)
·  30/9/07: 22 kV-14 nos. & 110 kV-01 nos. TPCD ABT meter commissioning.
·  Trombay Stn B G/S:- 30/09/07, Unit-6, 2 nos. ABB make 6.6 kV , SF6 filled Ckt. Bkr. Retro-fitted & commissioned on Station Bus # 6A
·  Dharavi R/S:- TPC-D Meter commissioning on 2 Nos 22 kV fdrs, 2 Nos. 33 kV BMC # 1 / 2 fdrs
·  Borivli R/S:- Total 12 Nos. TPC-D Meters commissioned on 22 kV & 33 kV Feeders.
·  Kalyan R/S:-
1.  03 no. Polycrete CT’s commissioned on 22kV Transfer bkr-01.
2.  20 No. Satec meters commissioned on 22 & 110kV feeders.
3.  Under TPC-D metering, 01 No. ABT meter commissioned at Central Railway Chola & 02 Nos. at Ordinance Factory Ambernath.
4.  110kV Bus Section breaker Commissioned at Bhivpuri along with the modifications in Bus Fault Ckt.
·  Borivli R/S:- 110kV Bus Section breaker Commissioned at Bhivpuri along with the modifications in Bus Fault Ckt.
4 / Protection System / relays Commissioning. / ·  Salsette R/S:-
1.  09/09/07, 220 kV KS 3 and KS 4 Main 2 distance relay lock out relay changed from hand reset to self reset, Required to facilitate A/R operation.
2.  20/09/07, 2 kV Devidayal feeder TSR relocated, Safer and better movement in the relay panel. Better view and approach to wiring.
·  Saki R/S: - Saki 22 kV U/F load shedding relay wiring and setting changes, For getting better data records of frequency related faults from the Micom relay.
·  Dharavi R/S:- ICT # 8 NGT N E/F relay is wired to operate Gr-B (220 kV Group – B, 110 kV Group – B & 33 kV trip unit), The modification is required to isolate high resistance fault from ICT to 33 kV switchgear.
·  Borivli R/S:- 22 kV Feeders IND-1, IND-2, IND-3, IND-4, IND-5, IND-6, TC-1, TC-2 and 33 kV F1, F5, F2 & F4 feeders, CT wiring of protection & metering circuit to modified to shift SCADA meters on protection core & TPC-D meters on 0.5 class CT core.
5 / Metering activities / ·  Commisisoning of MSEDCL's ABT meters in series with existing ABT meters at Saki.
·  Addittional 2 nos feeders at 33 KV points for REL were commissioned at Borivali.
·  A Mishra & D Dey visited Elster Factory at Daman for ABT meter inspection.
·  Total 132 nos meters were commissioned for TPC's Direct feeders as per MERC directive.
·  MSEB data collection for calculating UI charges.
·  BEST, REL & RCF data collection for calculating the co-incident MD.
  1. MAJOR OCCURRENCES & INVESTIGATION: -

DIVISION / OCCURRENCES / INVESTIGATION
Dharavi R/S / ·  29/09/07, ICT # 8 tripped on RADSB Relay giving shutdown to 33 kV BS II , Relay Testing done. ICT min test (IR, Mag Balance), 33 kV Cable Megger carried out Nothing abnormal found.
·  29/09/07, ICT # 8, 33 kV ICT # 8 LBBU operated while charging ICT # 8 giving shut down to 33 BS II, 33 kV cable from ICT # 8 to Switchgear has developed a high resistance fault. NGT N E/F Relay operated (time delay – 2 sec.) which trips only 33 kV bkr. The relay has initiated 33 kV LBBU. As 33 kV bkr was already open, LBBU protection operated which in turn operated ICT Gr-A, Gr-B and 33 kV Bus-fault lockout. NGT N E/F relay is wired to trip ICT Gr – B.
Distribution / ·  1/9/07, Kamala Mills, DT-2, Moisture absorbed on the bakelite sheet in LT Panel incoming Cable compartment, which resulted in a 3 phase short. LT Panel replaced.
·  10/9/07: Hindustan Composite, 3 Panel Board, Moisture absorbed in PT panel and the entire panel generally. PT fuse shattered. After cleaning, heating and hipoting, switchgear was taken back into service
·  15/9/07, Pkt-10, ABB RMU, Cable termination failed on R phase. Same RMU Blue phase cable termination had failed last month. Cable shifted to a spare outlet.
·  19/9/07, Raghuvanshi Mills, 2 MVA Emco make Transformer-2, Due to overloading, all the LT outgoing cables from the transformer burned, resulting in phase to phase short on the transformer. Transformer R phase become defective. Transformer-3 (1250KVA) which was kept out was taken into service. Transformer-2 was replaced with 1250KVA transformer.
·  22/9/07, Sanskruthi, 1250 KVA Transformer, Moisture absorbed in HT cable box of Transformer, resulting in flash over and bushings were damaged. After cleaning and replacing bushing, Transformer was taken back into service on 27/09/07.

E.  FAULTS / ABNORMALITIES DETECTED DURING DIAGNOSTIC TESTING:-

Total No of faults detected. : - 1 nos.
DIVISION / SIGNIFICANT DEFECTS DETECTED
Distribution / ·  20/09/07, Raghuvanshi, Transformer-2, Buchholtz was not working. Relay replaced

F.  FACTORY INSPECTION /ACCEPTANCE TEST :-

Sr. No. / FACTORY / DIVISION / EQUIPMENT & FINDINGS / LEARNINGS
1. / Vitrum IT park / Mr S R Pillai attended Third Party Meeting of Vitrum IT park on 19/09/07
2. / Huphen Electrical at Nashik / Mr. S H Mhatre – For inspection of 11 kV CT/PT panel.
3 / Mr. A M Z half day WLSG Workshop

G.  COST SAVING :-

Relay Lab : Relay Lab : - Nil

HV Lab: -

H: - COST OF POOR QUALITY / REWORK : NIL

Division

/ Description of poor quality / rework / No. of man hours spent

I: - NDB PARAMETERS

New

/ Different / Better
Total 132 nos meters were commissioned for TPC's Direct feeders as per MERC directive. / 220 kV KS 3 and KS4 manual reset lock out relay replaced by self reset lock out relay to facilitate A/R operation / ·  Trip Supervisory Relay of 22 kV Devidayal feeder at Salsette relocated from hinged arrangement to surface mounting.
·  22 kV U/F load shedding relay wiring and relay setting modified. This will improve frequency disturbance data retrieval.

J.  MAN POWER DEVELOPMENT / ADMINISTRATION:-

Mr. S R Pillai attended
·  Consumer coordination meeting on 13/09/07.
·  Meeting with Ormazabal on 17/09/07
Mr. A M Zulphikari was deputed to Haldia for 13 days for commissioning.

II.  ET & A SCADA SECTION

NAME: SCADA SECTION

A: - PERFORMANCE INDICES

INDICES /
This month Sep ‘07
/ Sep ‘06 / YTM- FY 08 / YTM- prev. year / Target
Availability Index (%)
Overall
T&D
LDC / 99.84%
99.74%
99.985 / 99.4% / 99.78% / 99.63%
/ 99.6%
Occasions for which system was manned / Date / No of Hours / Reasons and action taken
1.  / Nil

B: - COMMISSIONING & OTHER ACTIVITIES

Station / Activity / Equipment / Scheme /
Condition based Maintenance-status / Back ups / CBM / Target for 2nd Trimester(Upto Nov 07)
31% / 32% / 66.66%
/
CBM activity in Sept 07 / Maintenance activity completed for Vikhroli & Chembur. /
Modifications / Two calls for Database modification for Dharavi.
Project activities / ·  A meeting was convened with T & D to discuss the concept notes on Malad, Versova RTU replacement & Dharavi SCADA System replacement. Meeting with AREVA regarding this has been arranged.
·  Discussed the requirement of Receiving station Simulator with the division, shall be finalised after discussing with AREVA.
Distribution Automation / Training for Operation Engineers of DA System was conducted at Borivali & Central Mumbai was conducted by ABB Engineers.
Commissioning-LDC SCADA / Commissioning of gateway RTUs at 5 nodal points for LDC has been completed.
Scheme for new IP Addressing for CCR & LD nodes has been finalised & is in the process of implementation.
CA, PA & CI tasks / Nil
EPM process benchmarking / Benchmarking questionnaire has been deviced for SCADA EPM process & are being sent for feedback to the benchmarking partners.
Comments given by the Process auditors for the SCADA EPM Processes are being addressed.
C: –MAJOR FAILURES, PROBLEMS & INVESTIGATION
Breakdown calls in Sep ‘07 / Calls attended by TPC / Calls attended by NELCO / Calls attended by TPC & NELCO
10 / 7 / 3 / -

Concern: Maintenance & Security related issues to be addressed in view of the theft at one of the DA locations.

Manday Expert Advice from NELCO: Two Manday expert service of NELCO Engineers was availed on 28-09-07 to put the newly supplied 9.1GB SCSI Harddisk by CMC online at Parel Receiving Station.

Reasons for delay in resolving the Breakdown Calls:Nil

Call No / Complaint logged / Call Closed / Station Name / Reason for delay

D: - TRAINING / INSPECTIONS / DEPUTATION / SEMINARS / GENERAL TOPICS ETC.

A one day workshop was arranged at Dharavi on BSC concepts & implementation, at Dharavi . Mrs B. S Pisolkar attended the same.

DATE: 03-10-07 Sr. Mgr (SCADA)

III.  ET & A COMMUNICATION SECTION.

1.  COMMUNICATION AVAILABILITY:-

Communication System Indices / September 07(%) / September 06 (%) / YTM FY 2008 / YTM FY 2007 / Target for the FY 2008
Protection Channels / 100 / 100 / 99.93 / 99.88 / 99.9
Data channels / 99.99 / 96.81 / 99.91 / 99.21 / 98.0
Voice system / 100 / 97.55 / 99.91 / 99.34 / 99.0

% availability =

2. MAJOR INVESTIGATION & OCCURRENCES: -
Date / Division / Station / OCCURRENCES / INVESTIGATION / Down Time
Nil
Jobs that had taken more time than the standard time
Date / Division/ Station / System / Channels affected / Down Time
Nil

3.  BREAKDOWN MAINTENANCE ACTIVITIES : -

Date / Division / Description / Resolution time
19/9/07 / BKC / BKC – Dharavi fibre got cut. The same was repaired. / 3 hrs
20/09/07 / Trombay / Telephone exchange network dialling had failed. The CPU card at Trombay exchange was reset. The system was normalised after transfer from CPU – A to CPU – B / 1 hr
21/09/07 / Vikhroli / Vikhroli – Salsette fibre got cut. The same was repaired. / 3 hrs 30 min

4.  COMMISSIONING / PROJECT ACTIVITIES : -

Date / Division / Description
Commissioning
12/09/07 / Borivli / ADSS cable termination was completed at Borivli TPC and Borivli MSEB ends
12/09/07 / Borivli / Overhead joint respliced at T # 5 on Bo – Bo line
17/09/07 / Borivli / Installed Ebang multiplexer at Borivli TPC and Borivli MSEB
22/09/07 / Borivli / Extended data connectivity to MSEB Borivli through Ebang. Installed DCU, Netbox and checked loop test.
26/09/07 / Borivli / Commissioned channel for ABT metering at MSEB Borivli. The meter was made to communicate with the master at Load Despatch.
26/09/07 / Backbay / Additional extensions were configured, facilities were programmed for each extensions and connected direct lines.
26/09/07 / Carnac / Boss – Secretary feature was activated for VP - HR
Planning & Designing
24/09/07 / Carnac / Data connectivity requirements for BEST feederwise metering scheme was finalised.

5.  RETROFITTING JOBS: -

Date / Division / Description
Nil

6.  Condition based maintenance (April 2007- March 2008)

CBM indices / YTD Completion / YTD Target / Target for the FY 2008
Percentage (%) / 0 / 50 / 100
Location completed / Nil

7. ADMINISTRATION AND MAN POWER DEVELOPMENT.

Date / Name / Description
Nil

8. COST OF REWORK FOR POOR QUALITY OF RECEIVED MATERIAL EQUIPMENT

Nil

AGM(ET&A)