MEETING NOTES

Project:Renovation of LandaPark Bathhouse – 0606 A1

Date:October 16, 2007, 1:30 pm

Location:LandaParks & Recreation conference room

Persons Present:Reuben Pinkson, Fisher*HeckMary Quinones, City of New Braunfels

Gail Nelson, Kegley Int.Tony Caiger, Kegley Int.

Sammy Villegas, MJ BoyleManny Madrid, Robles Service Group

JJ Perez, MLP VenturesStacy Laird, City of New Braunfels

Gregory Schmidt, City of New BraunfelsRobin Kunkel, City of New Braunfels

Andy Garza, AMG ContractorsRusty Carey, Campell Floors

Purposeof Meeting: Pre-bid Conference

  1. Meeting commenced with introductions of all attendees.
  1. Solicitation Information

1. Bidding closes on October 26, 2007 at 3:00pm.

2.Bids may be submitted to the City Secretary’s Office for time stamping.

3.All bids must include the Enterprise Owner Information form & conflict of interest questionnaire.

  1. Project Scope
  2. Protection of the existing Park environment is a high priority. All staging areas will be coordinated with the Parks Department.
  3. Scope to include the renovation and remodeling of the restrooms, shower, dressing, training room, and offices.
  4. Scope to include new storage rooms.
  5. Exterior of building will be modified in order to provide better ventilation of building.

5. LandaPark has high expectations that the project will stay on schedule.

  1. Current Project Schedule
  1. The project completion date is May 1st, 2008.
  2. City Council will review the recommended award for approval. The City Council meets on the 2nd & 4th Monday each month.
  1. Bathhouse Walk-Thru Comments
  2. Fisher Heck will verify with owner that the existing lockerswill be removed by the owner prior to the commencement of work by the contractor.
  3. The contractor will need to contact New Braunfels Utilities in order to shut off the water to the building prior to any plumbing work being done. The bathhouse currently does not have its own water shut off.
  4. Contractors may have additional walk-thrus with subcontractors, however, they must coordinate those visits with the Parks Department.

If any of the above items are in error, please send written clarification within 10 working days, else this report will remain as written.

Completed by:Reuben G. Pinkson III

Cc: Reuben Pinkson, Fisher*Heck ArchitectsJim Heck, Fisher*Heck

Stacy Laird, City of New BraunfelsMary Quinones, City of New Braunfels

Robin Kunkel, City of New Braunfels

File

H:\My Documents\Pre-Bid Minutes Bathhouse.doc

915 S. ST. MARY’S STREET SAN ANTONIOTEXAS78205 TEL 210.299-1500 FAX 210.299.1622 FISHERHECK.COM