Installing Cabling: Procedures

Installing Twisted-Pair Media

Topology

Ensure the topology chosen is appropriate for the transceiver in question, bus for TP/XF-1250 channels and either bus or free topology for TP/FT-10 channels.

Cable Choice

Only use the transceiver manufacturers recommended cable types. Do not mix cable types on the same segment apart for stubs for TP/XF-1250 segments.

In the case of link powered segments, ensure that the cable type chosen and the channel link power loading delivers the correct supply voltage to link powered devices over all temperatures.

Cable Length
Bus Topology (TP/XF-1250 & TP/FT-10)

Ensure that the cable length for the main run and stubs do not exceed the maximum recommended length.

Free Topology (TP/FT-10)

Ensure that the maximum total length of cable does not exceed the maximum recommended length for the cable type in question.

Extending Distances

Only use physical layer repeaters or routers to extend segment lengths. Do not exceed one physical layer repeater per segment.

Cable Termination

Ensure that the correct segment termination method is used. Doubly terminate TP/XF-1250 and TP/FT-10 segments in bus topology. Use single point termination for TP/FT-10 segments in free topology. Only use the recommended termination network.

Link Power Supplies

Locate the link power supply for a segment so that the voltage to link powered devices is kept within specification. Typically it helps to install the link power supply in the middle of the segment.

Node Count and Distribution

For TP/XF-1250 and TP/FT-10 segments, ensure that the node count and distribution complies with that specified in the Junction Box and Wiring Guidelines and the transceiver users guides.

For TP/FT-10 segments using free topology, ensure that the node count and maximum node to node distance is not exceeded.

Cable Shield Termination

When using shielded cable, for all transceiver types, terminate the shield using the RC network shown below:

Cc = 0.1 mF, 10%, Metalized Polyester, ³ 100V

Rb = 470kW, 1/4W, ±5%

Ground the cable shield at least once per segment, and preferably at each node. Grounding the shield at every node (using the shield grounding circuit shown) will assist in suppressing 50/60Hz standing waves.

Building Entrance Protection

For inter-building communications, shielded cable and lightning protection should be used. Full details can be found in the FTT-10A users guide.

The following diagram illustrates the concept:

Network Isolation Rating

If the network cabling requires a specific isolation rating, do not degrade the isolation rating by running network cabling in the same trunking or partition as other cables. Use a separate cable tray.

Radiated Noise Sources

Avoid running network cabling in close proximity or in parallel to mains or other cabling which may be a noise source, i.e. mains cabling carrying high current triac controlled loads.

RF & Magnetic Fields

Do not install devices close to high RF or high magnetic fields such as linear motors unless they are specifically designed to be installed in such an environment.

Testing

Once the segment cable and termination is in place, check the termination impedance using an AC bridge.

Once you have physically and logically installed all devices on each channel, use a protocol analyzer to check that the error rate is less than the acceptable limit for each channel type and that the actual throughput matches the estimated throughput.

For link power segments, check the supply voltage at the furthest devices from the link power supply and ensure that it meets the recommended limits when the devices are active and in worst case current consumption conditions.

Installing Power Line Channels

Legislation

Ensure that the transceiver choice meets local legislation.

Pre-Installation Check

For commercial installations, verify that the installation is suitable for use with power line transceivers using PLCA-xx prior to physically installing the devices. This entails checking for injection loss, attenuation, signal-to-noise ratio, phase relationship, and error rates between all required points in the building. Details of how to perform these tests can be found in the relevant transceiver user’s guide. Due to the nature of the mains network, carry out pre-installation tests over a suitable period to access the full building characteristics over all times of day and days of the week.

For domestic installations, it may be unnecessary to perform a pre-installation check.

Node Count and Distribution

With power line networks it is very difficult to provide general numbers for node counts and distribution as installation-specific factors affect these parameters. However, a maximum number of 500 devices per sub station would be starting point.

Termination

In the case of unpowered media, long haul situations, or lightly loaded conditions, you may need to include bus topology termination for the segment. Details of suitable termination networks can be found in the relevant transceiver user’s guide.

Filtering

Due to the open nature of power line communications, you may need to filter the incoming mains supply to suppress unwanted incoming signals or to suppress local communication signals from escaping the building.

You may also need to filter noise from old equipment that may be in use within the building. Commercial filters are available for this purpose. Noisy equipment should show up during the pre-installation check.

Phase Coupling

If phase-to-phase communications are required, you will need to install some kind of phase coupling mechanism. Details of suitable coupling circuits may be found in the relevant transceiver users guide or Echelon power line application notes. Do not rely on the installations natural phase-to-phase signal coupling.

Testing

Once you have physically and logically installed all devices on each channel, use a protocol analyzer to check that the error rate is less than the acceptable limit for each channel type and that the actual throughput matches the estimated throughput.

Domain ID

Ensure that a unique 6 byte domain ID is used for the network.

Installing RF Media

Legislation

Ensure that the transceiver choice is meets local legislation and that any necessary licenses have been obtained.

Pre-Installation Check

You may need to perform a pre-installation check to ensure that the transceiver will work over the required range and environment.

If possible, find other local RF sources, such as paging systems, and ensure that they will not have any affect on the proposed installation.

Installation

Only use the manufacturer’s recommended aerial configurations.

Testing

Once you have physically and logically installed all devices on each channel, use a protocol analyzer to check that the error rate is less than the acceptable limit for each channel type and that the actual throughput matches the estimated throughput.

Domain ID

Ensure that a unique 6 byte domain ID is used for the network.

Other Media

Installation

Follow the transceiver manufactures specifications and advice with regard to media length and node distribution.

Node Count and Distribution

Do not exceed the transceiver manufacturer’s recommended node count and node distribution specifications.

Testing

Once you have physically and logically installed all devices on each channel, use a protocol analyzer to check that the error rate is less than the acceptable limit for each channel type and that the actual throughput matches the estimated throughput.

IP Channels

Physical installation

Do not install IP-based devices without first contacting the local IS administrator.

Ensure that the maximum distance from the device to the hub, and maximum node-to-node distances are not exceeded.

Address

Determine whether static or dynamic (DHCP) IP addressing will be used. If in doubt, contact the local IS administrator.

Bandwidth

Ensure that, if necessary, the devices have their bandwidth clipped (QOS), consult with the local IS administrator to see if this is necessary.

Logical Connectivity

Contact the local IS administrator to have any intermediary firewalls or routers opened up.