SWAMP Calculation Worksheet
Basic Instructions Sheet
Date: Date form was prepared.
Response Required By: Date response is required.
From: Individual or company submitting analysis worksheet.
Subject: Subject or project of analysis worksheet.
OPZ Status: Status of project (i.e.: concept, sketch, final, permit).
Project Number: DPW Project number of proposed project.
Permit Number: DPW Permit number of proposed project.
Sub-Division Number: Sub-division number of project.
Project Size: Size of project; either in number of lots or square feet.
Size of Site: Size of site; either in acres or zoning.
200 Scale Map: Department of Public Works official 200 scale map
Tax Map: Tax map of development
Block: Block to be developed.
Parcel: Parcel to be developed.
Water Master Plan Change Required: Will the project require changes to the Water Master Plan?
Sewer Master Plan Change Required: Will the project require changes to the Sewer Master Plan?
Project Type: Determine if the project is either residential, or Commercial/Industrial/Towncenter/Mixed-Use/Other.
Location: Determine if the project is County-Wide, National Business Park/Russett/Corridor Market Place, or Mayo. Select County-wide if project is not in National Business Park/Russett/Corridor Market Place or in Mayo.
Calculate Flow Based On: Choose weather the calculations should be based on the use or the zoning of the project.
Use: If Use is selected then the Facility description and the Number of units need to be completed.
Zoning: If Zoning is selected then zoning and total area (acres) needs to be completed.
Requested Water Analysis
Water Service Area: Choose which water service area services the project location.
Maximum First Floor Elevation within the project: The maximum elevation of the first floor within the project.
Fire Flow Requirement: Required water flow of fire hydrant. (See Appendix1)
Water Connection Point(s): Location of nearest fire hydrant, and the size of the connecting water main.
Other Projects Affected or Required to Complete: List other projects that will be affected by or need to be completed before this project.
Comments of Concerns: Any comments or concerns in about the water system raised by the project.
Requested Sewer Analysis
Sewer Service Area: Choose which water service area services the proposed project location.
Sewer Connection Point(s): Location of nearest manhole to proposed project.
Other Projects Affected or Required to Complete: List other projects that will be affected by or need to be completed before this project.
Comments of Concerns: Any comments or concerns in about the sewer system raised by the project.
APPENDIX 1
FIRE FLOW RATES
RESIDENTIAL: (1)
SINGLE FAMILY (2): 1,000 GPM AT 20 PSI RESIDUAL
TOWNHOUSES (R-5): 1,500 GPM AT 20 PSI RESIDUAL
GARDEN TYPE APARTMENTS (R-15): 2,000 GPM AT 20 PSI RESIDUAL
HIGH RISE APARTMENTS (R-22): 2,500 GPM AT 20 PSI RESIDUAL
COMMERCIAL: (1)
REGIONAL SHOPPING CENTERS (C-3): 3,000 GPM AT 20 PSI RESIDUAL
INDUSTRIAL (1): 3,000 GPM AT 20 PSI RESIDUAL
INSTITUTIONS: (1)
HOSPITALS: 2,500 GPM AT 20 PSI RESIDUAL
SCHOOLS: 2,500 GPM AT 20 PSI RESIDUAL
OFFICE BUILDING COMPLEX (1): 3,000 GPM AT 20 PSI RESIDUAL
(1) ABOVE FIRE FLOWS TO BE USED IN THE ABSENCE OF SITE SPECIFIC DATA FROM FIRE UNDERWRITERS OR CONSTRUCTION PLANS WHICH WOULD PERMIT A DETERMINATION OF FIRE FLOW REQUIREMENTS USING INSURANCE INDUSTRY STANDARDS (INSURANCE SERVICE OFFICE – ISO). CONSIDERATION WILL BE GIVEN TO REDUCING THE REQUIREMENT WHERE PROPOSED CONSTRUCTION INCLUDES SPRINKLER SYSTEMS; REFER TO CURRENT ISO RECOMMENDATIONS.
(2) CONSIDERATION WILL BE GIVEN TO REDUCING THE REQUIREMENT TO 750 GPM WHERE IT CAN BE DEMONSTRATED THAT 1,000GPM IS TECHNICALLY UNFEASIBLE.