VALUEENGINEERING
WORKBOOK INSTRUCTIONS
GeneralInstructions:
Completeeachpageclearly, legibly,andneatlywithadarkpencilorblackpen. Inmostcasesthisworkbookwillbereproducedas isandnotretyped.
Instructions for Completing VE Study Identification
Thisisoneoftwopagesusedtoidentifytheprojectandserveasan introductiontoit.Byreadingthispage,aninterestedpartyshouldbeabletounderstandthegeneralnatureandscopeofthe project.
- VE TEAM MEMBERS
- This areaisusedtorecord the name,title,agency,andtelephone number ofeach team member.
- PROJECT DESCRIPTION
- Length- Infeetormiles
- Cost-Estimatedtotalprojectcost
- TypeofFunds-ArethereFederal,State,and/orLocalfunds intheproject? Listtheirclassification:construction,maintenance, local,etc.
- Design Speed - Miles per hour
- ProjectedTraffic-Averagedaily traffic{ADT}anddesign hourlyvolume {DHV}
- ProjectedAwardDate-Anticipated lettingdate
- MajorProjectElements-Describewhattheprojectenta.ils.Whatis involved? Givea verbal, non-technical description ofwhatis included in this project. This description, followedbyalistingofmajorcomponentsmaybeusefulto individuals reviewingthis workbook. Forexample:Grading,Drainage,Paving,Structures,Utility relocation,etc.
- ROUTE CONDITION I GEOMETRY
- Itisoftenusefultoknowtheconditionoftheadjacentsegments,andthetotalroute.Forexample: sufficiency rating, tangent section, rolling terrain,roadwaycross-section,lackof shoulders, etc.
INDOT VE - 1 SHEET ___ OF __
Value Engineering - Study Identification
Des & Contract Number:Route Number:
Location:Date:
VE TEAM MEMBERS
Name: / Title: / Organization: / Telephone:PROJECT DESCRIPTION
Length:Cost:
Design Speed:Projected Traffic:
Projected Award Date:Type of Funds:
Major Project Elements:
ROUTE CONDITION / GEOMETRY
Adjacent Segments: / Overall Route:InstructionsforCompletingInvestigationPhase–Sources:
- AUTHORIZING PERSONS
Listhere the personswhowill havetoapprovetheVErecommendations.Thisinformationwillbeusefulinensuringthattherecommendations are presentedina manner tailoredtothe unique habitsandattitudes thatmaygovernfinal acceptance.
- PERSONAL CONTACTS
List here fill thepeoplefromwhomyouseekadviceand informationregardingthestudy. Maintainandaddtothislistasthestudyprogresses. Under "Notes," summarize the informationobtained.
- DOCUMENTS/ABSTRACTS
Listallthe referencematerialused inthestudy,i.e.,standardspecifications,AASHTO Guides, Statestandards,Means construction costs,AASHTO Green Book,etc. Briefly notethekindof informationcontained inthem.
INDOT VE - 2 SHEET__ OF __
Investigation Phase - Sources
Des & Contract Number:Route Number:
Location:Date:
APPROVING / AUTHORIZING PERSONS
Name: / Position: / Telephone:PERSONAL CONTACTS
Name: / Telephone: / Notes:DOCUMENTS / ABSTRACTS
Reference: / Notes:InstructionsforCompletingInvestigationPhase-CostModel:
- PrepareaCOSTMODELforyourproject.
- COST OF SIGNIFICANT BID ITEMS
- It isoftentruethat20percentofaproject'selementsconstitute80percentofitscost.
- PrepareaCOSTMODELof allofthemajoritemsinyouproject.UsingaBarChartformat,showthecostofeach itemstartingwiththehighestcost itemfirst. Tentotwentyprojectcostelementsare desired. Combine and/orbreakdowncostelementstoachieve this numberof elements.
- Drawahorizontallinetoshowthe80percentcostsplitoftheproject items. Thiswill indicatetotheteamthoseprojectelementsdeservingthemostattention.
- Ifsome lowcostprojectelementsareusedrepeatedlythroughoutyour organization,theymayproduce positive, organization-widesavings. Listthemon the costgraph,otherwise they will be ignored in the study.
INDOT VE - 3 SHEET __ OF __
Investigation Phase - Cost Model
Des & Contract Number:Route Number:
Location:Date:
Instructions for Completing Information Phase – Function Analysis:
Thisiswherethe conventionallistingofprojectitemsandcostsistransformedintoalistingofprojectFUNCTIONSandtheirrelativecosts. Keepinmindthattheobjectiveofthe investigationphaseistoidentify thosefunctional areasthathavethegreatestopportunityforvalueimprovement. Thelistingonthispageisanotherstep toensurethatthefunctionswiththe"best"potentialforsavingsare examinedfirst. Inthetitle block,identify theFUNCTIONof yourtotalprojectusingoneverbandanoun.
AssignaLETTERtoeachprojectcostitem.Next,entera"Two-Word" definition(ActionVerb& DescriptiveNoun)thatexpressesthefunctionofeachitemlisted. Entertheitem'scostasshownintheCostModel. Inmakingout thislist,itemssatisfyingthesamefunctionshouldbegrouped together.
- OTHER ITEMS
- Listanyadditionalitemsthatmighthavea potentialforsubstantialsavings.ifconsideredonaprogram-widebasis.Enterthe''Two-Word" definitionthatexpressesthefunctionofeachitemlisted. Entertheitem'scost.
- WORTH
- WorthistheleastcostthattheVEteambelievescanaccomplishthesamefunction.Considerafunctionalcomparativeforeachitemlisted.Thisshouldbealesscostlywayofperformingthe samefunction,irrespectiveofitsprojectapplication. Usethe"comment"columntoidentifythefunctionalcomparativeorothermeanstakentoachieveworth. Thiswillshowyouifthereisanysubstantialcostdifferencebetweenthedesigncostanditsworth.Someexamplesare:
ITEMFUNCTIONCOSTWORTHCOMMENT
A. / Bridge / Cross Obstacle / $215,000 / $115,000 / UseCulvf3rtB. / CulvertPipe / ConveyFluids / $100,000 / $20,000 / Useopen ditch
C. / Slopewidening / EnhanceSafety / $125,000 / $55,000 / GuideRail
D. / TrafficLight / ControlVehicles / $75,000 / $10,000 / StopSigns
Thesizedifferencebetween·thedesign costandtheworth ofthefunctionalcomparativeisanindicationofvalueopportunity.
INDOT VE - 4 SHEET __ OF ___
Investigation Phase - Function Analysis
Des & Contract Number:Route Number:
Location:Date:
Item / Basic / Function:No. / Description: / Verb: / Noun: / Cost: / Worth: / Comments:
1
2
3
4
5
6
7
8
9
10
11
12
13
InstructionsforCompletingInvestigationPhase–FASTDiagram:
TheFAST diagram is a graphic representationofthefunctionallogic applied totheoriginaldesign.TodevelopaFASTdiagram, onehastoaskthequestions,HOW is thebasic function (verb)(noun) actually accomplished,orHOWisitproposedto beaccomplished? Theanswer,expressedasaverbandanouniswritteninthe nextblocktotherightofthescopeline.
Theprocess is continuedto the right byasking HOW.foreachnewfunctionon the diagram. Theprocessisrepeated until theanswerfallsoutside the scopeofthestudy.TochecktheanswerstotheHOWquestions,askthe question WHY asyouproceedbackwardthroughtheFAST diagram, startingontheright sideandproceedingtothe leftuntilyouhaveexceededthescopeofthe study(reachedafunctionwith ahigherorderthanthebasicfunction).
Theline offunctionsyouhavedeveloped iscalledthecriticalpath. IfoneoftheRequiredSecondary functionsistakenaway,theBasicFunction ofthesystemcannotbesatisfied. IfafunctioncanbetakenawaywithoutaffectingtheperformanceoftheBasicFunction,thenthefunctionremoved isnotcritical,butmaybeasupporting function.
- SUPPORTING FUNCTIONS
- Functions that happenallthetime,atthesametime,orarecausedbythecritical functions are supporting functions. They result fromthe particular method chosenbythedesignerforaccomplishingthe Basic Function. All the time functions areshownabovethe critical pathlineand same time and caused by functions are shown belowtheline.
- TheFASTdiagramcanbeusedto identifyandvisualizehigh-costfunctions byincludingthefunctionalcost ineachofthecriticalandsupportingfunctionblocks.
SCOf'E OF STllbV
INDOT VE - 5 SHEET ___ OF ___
Investigation Phase - FAST Diagram
Des & Contract Number:Route Number:
Location:Date:
InstructionsforCompletingSpeculation–Brainstorming:
ThissheetisusedfortheSPECULATIONCREATIVEPhaseoftheVEJobPlan.
BRAINSTORMoneachofthefunctionsfrom theFunctionAnalysissheet. Putdownasmanyideasaspossible. Useas manysheetsasnecessary. Donotlimit yourideas.
Writedownallideas. Rememberthenumber oneruleofbrainstorming,DO NOTJUDGE!
Speculation Phase
Objective:Task:
-Generatelargenumbersofideas- Speculateonfunctions
-Don'tdiscuss
KeyQuestions:Techniques·
-Whatelsewillperformthe function?- List everything
Whereelsemaythe function be done?- Be imaginative
-Howelsemaythefunctionbedone?- Use creative techniques
- Defer judgment
- Do not criticize
- Be courageous
INDOT VE - 6 SHEET ___ OF ___
SPECULATION PHASE - BRAINSTORMING
Des & Contract Number:Route Number:
Location:Date:
Item:Function:
InstructionsforCompletingEvaluationPhase:
ThissheetisusedfortheEVALUATION PhaseoftheVEJobPlan.Considerfirstthosefunctionsthathavethegreatestpotentialsavings.TwoEvaluationmethodswillbeused.
- FEASIBILITY EVALUATION
- ReviewthecreativeideasyouhavedevelopedinyourBrainstormingsessionandcross out thosealternativesthattheteambelievesare unrealistic and,therefore,unacceptable. CAUTION-Beabsolutelysureeveryoneagreestheideashouldbedropped.
- SUITABILITY EVALUATION
- Recordalloftheremaining ideasforeachfunctionthathavenot beencrossedoutand listtheiradvantagesanddisadvantages. Listtheideasforthatitemnumberingconsecutively(A-1,A-2,A-3;B-1,B-2,B3;etc.)
- Rateeachideafrom"poor"to"outstanding"(1to10).TheratingisusedtoguidetheteamduringtheDevelopmentPhaseensuringthebestideasaredevelopedfirst.
EVALUATIONPHASE
Objective·Task:
-Evaluate alternatives- Speculateonevaluationcriteria
-Evaluatealternatives
-Selectthebestalternatives
Key Questions:Techniques:
-Howmighteachideawork?
-Whatwillbethe cost?
·-Willeachideasatisfy thefunction?
-Whatisthebetteralternative?
-Whatare thechancesofsellingtheidea?
-Weighalternatives
-Chooseevaluationcriteria
-Refineideas
-Placedollarvalueofeachidea
INDOT VE - 7 SHEET __ OF __
Evaluation Phase
Des & Contract Number:Route Number:
Location:Date:
ItemNo. / Creative Idea
Listing / Idea
Advantage / Evaluation
Disadvantage / Idea
Rating
Instructions for Completing Evaluation Phase - Matrix Analysis:
Thisis anoptionalworksheetfor theEVALUATIONPhase. It is aMatrixAnalysisFormthatyoucanuseto assign numerical ratingstothe subjective analysisyou carried out onFormVE-7. Itpermitstheteamparticipantstoweighandratevariousaspectsof eachalternative,whileremainingfreeofanybiasor predisposition aboutthe alternativeasawhole.
TheMatrixAnalysis is usedtocompareavarietyofalternativesaffectingasingleprojectfunction. It isespeciallyuseful wherethere isnoclearconsensusamongtheVEteam.
- OBJECTIVES OR CRITERIA
Listall the design objectivesorperformance criteria that apply totheproject under study. Weighthemfrom 1to 10accordingtotheirrelevanceorimportance (10 = highand1 = low. Enter this weight in the horizontal line ofboxes.
- ALTERNATIVES
- ListtheORIGINAL itemandallthealternativesfromFormVE-7thatyouwantto compare. Ratehoweachofthe alternatives satisfieseach objective or criterion, i.e.,1 = poor and 5 = superior. Enter the rating foreachalternativeinthetoppart ofthe box.
- TO ELIMINATE BIAS, it is essential to WORK DOWN each column, rating each alternative according to the same objective or criterion.
- Multiply the rating by the weight for each combination. Enter the weighted rating in the lower part of the box.
- Addtheweightedratingsforeach alternative togetherand enter itstotalscorein the Totals column.
- Rankthealternatives accordingtothetotalscore(1 = highest, 2 = secondhighest,etc.). Now determinehow the alternatives shouldbeused and how they might bemodifiedto improvethe product.
INDOT VE - 8 SHEET __ OF ___
Evaluation Phase - Matrix Analysis
Des & Contract Number:Route Number:
Location:Date:
EVALUATION CRITERIA
WEIGHALTERNATIVES:
5 Superior
4 Good
3 Average
2 Fair
1 Poor
1 Poor
ALTERNATIVES / WEIGHT / TOTALS
Instructions for Completing Development Phase – Recommendation:
- Onceyou identifythe projectelementsand/orfunctionalareasthatcanbemodified,developeachareaintoaworkablealternative solution.Complete FormVE-9for each recommended alternative. Donotshowany calculations orsketchesonthissheet. Attachallbackupcalculationsheetsusedto developthe idea.
- Keep inmind;thedecisionmakerswhowillbereviewingthese itemsarenotfamiliarwiththeteam'sworkthisweek.Developyouralternatives ina logicalandcomplete fashion showingallcalculationsfordocumentationandlistingallassumptionsmade.
- Thejustificationarea iswhereyoumuststateyourreasonsformakingthechange.Remember,you must"sell"youridea. Becomplete.Useadditionalsheetsofpaper ifnecessary.Anticipatepossiblereasonstorejectyour ideaandprovideadequateresponsesto counter theseobjections.
- Costsusedonthissheetshould includeboth initialandfuturecosts. Detailedcostcalculationsshouldbeshownonseparatesheets. Futurecostsarethesumof lines6and8on the life cycle cost analysis worksheet(seeFormVE-9D).
INDOT VE - 9 SHEET ___ OF __
Development Phase - Recommendations
Des & Contract Number:Route Number:
Location:Date:
Original Design (Sketch attached?
Proposed Change (Sketch attached?)
Justification (Describe advantages/disadvantages, reasoning, and compliance with
standards and requirements)
Life Cycle Cost Summary(Present Worth Method) / Initial Cost / Future Cost / Total Cost
Original Design
Proposed Change
Savings
Instructions for Completing Development Phase – Sketches:
- Having identified which functional areas can be changed, make a SIMPLE SKETCH of the project element as designed and as proposed. Be sure to include enough information to clearly identify the proposed changes.
HINT:Aclear,easyto understandsketchisthebestsalestool.
INDOT VE - 9A SHEET ___ OF __
Development Phase - Sketches
Des & Contract Number:Route Number:
Location:Date:
Original Design
Recommended Design
Instructions for Completing Development Phase – Calculations:
- Show sufficient calculations to enable all reviewers to analyze your proposed changeand determine that it is a workable and realistic alternative. Calculations should show technical data only. Reserve cost calculations for the cost worksheet. Be sure to identify and explain all assumptions you made if specific data is not available.
- Includeasmanysheetsas necessary.
INDOT VE - 9B SHEET __ OF __
Development Phase - Calculations
Des & Contract Number:Route Number:
Location:Date:
Instructions for Completing Development Phase - Cost Worksheet:
- Amajorelement in "selling"yourrecommendations involves showingthattheyarenotonlyviable engineering alternatives, but thattheywill result in aCOST SAVINGS. This sheetallowsforacomparisonofthecostsfor the variousproposed alternatives to their original costs.
- Beasdetailed in your costsas possible. Usethesame unit costsforboththeoriginalandproposedestimateforeachitemofconstruction.Listany assumptions madeandindicatewhereyourcostswereobtained.
- Item: Thisistheitemofconstruction,suchas;fill,concrete,24"RCP,etc.Unit: This iswhat unitsexpresstheitem,suchas;CY,LF,SF,EA,etc.
- The unit costs for this worksheet should either be pulled from the Stage 1 estimate, or the average price for the item in Bid Tabs Express
INDOT VE - 9C SHEET __ OF ___
Development Phase - Cost Worksheet
Des & Contract No.:Route Number:
Location:Date:
Construction Element / Orig. / Cost / Prop. / Cost# of / Cost / / Total / # of / Cost / / Total
Item / Unit / Units / Unit / Cost / Units / Unit / Cost
Instructions for Completing Development Phase - Life Cycle Cost:
This sheet is used to determent an item's LIFE CYCLE COST using the Present Worth method.
This worksheet is NOT required for each alternative, only those that evaluate costs other than initial construction costs.
Single payment factors and uniform series factors can be found in Chapter 50 (Figure 50-2C) of the Indiana Design Manual (IDM).
- Estimate the Economic Life for the Item (10, 15, 20, 35, 50, etc. - Years)
- Determine the Discount Rate to be Used (4% Interest Table from Figure 50-2C in the IDM)
- List Initial Cost
- List and Determine the Present Worth of all Future Single Costs
- List and Determine the Present Worth of all Future Annual Costs
- Sum the Costs to Determine the TOTAL Future Costs Include this Cost on Sheet VE-9
INDOT VE - 9D SHEET __ OF ___
Life Cycle Cost Analysis - Present Worth Method
Des & Contract No.:Route Number:
Location:Date:
Discount Rate:Economic Life: __ Years
Original / Design / Alt. / No.1Cost / PW / Cost / PW
1. Initial Cost:
Single Expenditures: (i.e., stage
Construction, Major Maintenance)
a. Year ____ PWF ______
b. Year ____ PWF ______
c. Year ____ PWF ______
d. Salvage / Unused Service Life
Year ____ PWF ______
2. Future Single Costs:
Annual Costs:
a. General Maintenance
PWF ______
b. Other Annual Costs
PWF ______
3. Future Annual Costs
4. Total Future Costs: (2 + 3)
5. Total Life Cycle Costs: (1 + 4)
Instructions for Completing Development Phase - Summary of Cost Savings:
- This sheet provides a summary of all your recommended alternatives and their cost savings. List each of your proposed alternatives and its cost savings.
- The TOTAL projected project savings should also be shown on this sheet to indicate the maximum potential savings. In determining the TOTAL savings, remember that some recommendations may overlap and therefore FULL credit cannot be taken for each. Use an asterisk in the last column to indicate which proposals are included in the TOTAL.
INDOT VE - 10 SHEET ___ OF ___
Development Phase - Summary of Cost Savings
Des & Contract Number:Route Number:
Location:Date:
Original / Proposed / Initial / Future / TotalIdea / Description / Design / Change / Cost / Cost / Cost
No. / Cost / Cost / Savings / Savings / Savings
Instructions for Completing Development Phase - Executive Summary:
Theexecutivesummaryshould includeaconcise,abstractoftheVEstudy. Itshouldbeconfinedtoonepageifpossible. This willserveasa summary document for theprojectandyourrecommendations. Itistheexecutiveactiondocument fromtheteamtothedecisionmakers,highlightingthestudyandrecommendations. Asa minimum itshouldinclude:
- General
- Project description including thetotalestimatedconstructioncostSiteanddateoftheVEstudy.
- Results Obtained
- Numberofrecommendations
- Totalprojectedsavings
- Savingsasapercentoftheprojectcost
- Highlights
- Summarize significant recommendations (if many)orallrecommendations (if few).
- Constraints
- Identifyanyconditions(political,social,orsite)that influencedtheteam'srecommendations.
INDOT VE - 11 SHEET ___ OF ___
Development Phase - Executive Summary
Des & Contract No.:Route Number:
Location:Date: :
Introduction:
Study Results:
Constraints:
Highlights:
Resources
Economic Analysis:
FHWA Value Engineering Final Rule: