The Sector
Brief analysis of:
- The relevant sector, its present state and future plans;
- its role in the economic and social development of the national economy;
- its relevance and importance of the project to the sector and the economy.
The Project
Objectives and Scope
- Project objectives and benefits;
- Project concept;
- Project scope;
- Existing facilities.
- Implementation Plan.
Project Location
- Geographical location - advantages and disadvantages;
- Infrastructural support facilities.
- Any adverse physical conditions.
Technical Evaluation and Engineering Characteristics
- Details of technical studies and their state of readiness;
- Specifications and architecture;
- Data, site investigation, site survey, geology, hydrology, traffic details;
- Project design;
- Any adverse physical conditions;
- Construction material;
- Physical, hydrological or climatic constraints;
- Operation and maintenance.
Utilities
- The assessment of the present and future availability of power, water supply, communications and other services to the project.
Construction Material
- Project requirement;
- Type, sources, quality, quantity and prices;
- Availability.
Manpower, Training and Technical Assistance
- Total manpower requirements by various categories;
- Source and cost of manpower;
- Training needs;
- Need for technical assistance.
Environmental Aspects
- Effects of the project on environment and ecology.
Project Cost Estimates
- Detailed item-wise breakdown of cost estimate in local and foreign currencies and in US Dollars equivalent;
Basis of cost estimate and provision for contingencies (both price and physical contingencies);
- Procurement procedure, international competitive bidding/selective tendering.
Financing Plan
- Details of funds committed;
- Terms and conditions of credits, etc;
- Existing financing gap, if applicable.
- Proposed IDB Financing.
The Executing Agency
- Legal status, objectives and functions;
- Organization and management;
- Staff and personnel policies;
- Budgeting and accounting;
- Past performance and future outlook;
- Project monitoring.
Project Implementation
- Relationship between borrower and executing agency;
- Need for consultancy and supervisory services during implementation;
- Modes of procurement and contracting;
- Implementation schedule.
- Disbursement projections in tabulated form;
- Assessment of operation, maintenance and surveillance requirements during the life of the project;
Economic Justification
- Basic assumptions;
- Economic Rate of Return;
- Sensitivity Analysis;
- Social and other non-quantifiable benefits.
Conclusion and Recommendations
- Technical soundness of the project proposal;
- Importance of the project to the national economy;
- Benefits accruing as a result of establishing the project.
- Recommended IDB loan financing along with its terms and conditions.
Annexes
List of Annexes, more commonly referred to:
- Map of country with project location (where necessary);
- Layout of the project;
- Detailed project cost breakdown;
- Organization chart of the executing agency;
- Project implementation bar chart;
- Schedules of repayment of loans and service fee;
- Economic Rate of Return calculation;
2-4-B BREAKDOWN OF COST ESTIMATES
1. The undernoted costs should be expressed in local currency while summary of the main items given in equivalent US dollars:
/ Foreign Currency Cost / US $ Equiva-lent / Local Currency Cost / US $ Equiva-lent / Total Local Cost / Total Equiva-lent /
(i) LAND
Area of land acquired and unit cost
Cost of land
Land development costs
Others (Please specify)
Sub-Total
(ii) CIVIL WORKS
(a) Main building & structures
- Covered Area
- (Sq.Metres)
- cost
(b) Boundary wall/fencing
- Running Metres
- Cost
(c) Cost of electrification and/
or plumbing may be shown
separately if not already
included in above costs.
(d) Auxiliary buildings
- Please specify type
- Covered area (Sq.Metres)
- Cost
(e) Gate house
- Built-up area
- Cost
(f) Other items (if any)
Please specify with details of construction and costs.
(g) Approach roads (where
applicable)
- Length (metres)
- Cost
(h) Internal roads (where
applicable)
Sub-Total of Construction
Costs:
Add (where applicable):
- Architect Fees
- Fees for Supervision
of construction.
TOTAL COST OF BUILDING & OTHER CONSTRUCTION:
(iii) MACHINERY AND EQUIPMENT
(a) Imported, CIF cost of machinery/equipment and spares.
(b) Customs duty and other surcharges
(c) Clearing and forwarding costs
including port charges,
handling and internal
transportation to site.
Sub-Total of Delivered Cost of Machinery/Equipment to Site
(d) Erection & Installation Costs:
- Foreign erection fees
and costs
- Local erection costs
Sub-Total Erection Costs
(e) Local Equipment Cost
(a to e) TOTAL COST OF INSTALLED TOTAL MACHINERY AND EQUIPMENT
(iv) TECHNICAL KNOW-HOW FEES, ETC.
Cost of know-how fees,
(lump sum, where applicable) or
engineering consultancy fees.
Please specify and
give details of costs.
(v) FURNITURE & FIXTURES
- Include cost of furniture,
fixtures and other office
equipment.
(vi) VEHICLES
- Number, type and cost
(vii) OTHER EXPENSES
- Administrative expenses
- Expenses related to project
implementation like procurement negotiation visits, etc.
- Project commissioning
expenses (please specify)
- Other (please specify with
costs)
(viii) FINANCIAL CHARGES DURING CONSTRUCTION
- Under this heading include
interest charges payable to
other financiers of the
project and other related
costs.
SUB-TOTAL (i) to (viii)
Add: - Physical
contingency(%)
- Foreign currency
- fluctuation (%)
- Price contingency (%)
FIXED COST OF PROJECT: