MEETING MINUTES

Minutes for Date: 29 November 2005

Persons Attending:

NameTitle E-mailPhoneWk Phone Absent/Present

Sam Swafford Project Manager 763-5849none

Josh SimmonsProject Leader 960-9309none

Kenneth AyersTechnical 215-3570914-3188

Kent HainesData 874-0929624-1405

Charles CampbellAsst. Project

Raymond MayneAsst. Data 784-0240785-1355

Reason for Meeting:

Weekly development meeting.

Events of Note in Meeting:

1) Reminded group members to complete weekly Evaluations.

2) Coding will begin immediately on the final product.

PROBLEMS:

Minutes for Date: 22 November 2005

Persons Attending:

NameTitle E-mailPhoneWk Phone Absent/Present

Sam Swafford Project Manager 763-5849none

Josh SimmonsProject Leader 960-9309none

Kenneth AyersTechnical 215-3570914-3188

Kent HainesData 874-0929624-1405

Charles CampbellAsst. Project

Raymond MayneAsst. Data 784-0240785-1355

Reason for Meeting:

Weekly development meeting.

Events of Note in Meeting:

1) Reminded group members to complete weekly Evaluations.

2) Deliverable will be posted a few days late due to a death in group member’s family.

3) Josh will complete the Software Estimation document

PROBLEMS:

Project Manager suffered a death in the family. Tasks were delegated to individual team members but there was little success in accomplishing tasks.

Minutes for Date: 15 November 2005

Persons Attending:

NameTitle E-mailPhoneWk Phone Absent/Present

Sam Swafford Project Manager 763-5849none

Josh SimmonsProject Leader 960-9309none

Kenneth AyersTechnical 215-3570914-3188

Kent HainesData 874-0929624-1405

Charles CampbellAsst. Project

Raymond MayneAsst. Data 784-0240785-1355

Reason for Meeting:

Weekly development meeting.

Events of Note in Meeting:

1) Reminded group members to complete weekly Evaluations.

2) Data Administrator will verify consistency of Data Dictionary versus the project documents prior to Deliverable 9.

PROBLEMS:

Minutes for Date: 8 November 2005

Persons Attending:

NameTitle E-mailPhoneWk Phone Absent/Present

Sam Swafford Project Manager 763-5849none

Josh SimmonsProject Leader 960-9309none

Kenneth AyersTechnical 215-3570914-3188

Kent HainesData 874-0929624-1405

Charles CampbellAsst. Project

Raymond MayneAsst. Data 784-0240785-1355

Reason for Meeting:

Weekly development meeting. Addressing communication and deliverable issues

Events of Note in Meeting:

1) Reminded group members to complete weekly Evaluations.

2) Technical Leader will make final modifications to UI Navigation Prototype for Deliverable 8.

PROBLEMS:

1) Group members are failing to meet team internal deadlines.

2) Group members are submitting documents which show that instructions given are not being read/followed.

Minutes for Date: 4 November 2005

Persons Attending:

NameTitle E-mailPhoneWk Phone Absent/Present

Sam Swafford Project Manager 763-5849none

Josh SimmonsProject Leader 960-9309none Kenneth Ayers Technical Leader 215-3570 914-3188

Kent HainesData 874-0929624-1405

Charles CampbellAsst. Project

Raymond MayneAsst. Data 784-0240785-1355

Reason for Meeting:

Weekly development meeting. Addressing communication and deliverable issues

Events of Note in Meeting:

1) Reminded group members to complete weekly Evaluations.

2) Requirements will be modified, changing the platform from Windows environment to “Windows operating system capable of supporting JRE 1.4 or later”

3) Strongly remind group members to meet the team deliverable deadline on the Sunday prior to the actual deadline.

PROBLEMS:

1) None

Minutes for Date: 25 October 05

Persons Attending:

NameTitle E-mailPhoneWk Phone Absent/Present

Sam Swafford Project Manager 763-5849none P

Josh SimmonsProject Leader 960-9309none P

Kenneth AyersTechnical 215-3570914-3188 P

Kent HainesData 874-0929624-1405 P

Charles CampbellAsst. Project A

Raymond MayneAsst. Data 784-0240785-1355 P

Reason for Meeting:

Weekly development meeting.

Events of Note in Meeting:

1) Reminded group members to complete weekly Evaluations.

2) Noted that Charles Campbell has moved to Orlando and will continue working with the group via email.

3) Project Leader will begin creating a Navigational Prototype with components stubbed out.

PROBLEMS:

1) None

Minutes for Date: 17 October 05

Persons Attending:

NameTitle E-mailPhoneWk Phone Absent/Present

Sam Swafford Project Manager 763-5849none P

Josh SimmonsProject Leader 960-9309none A

Kenneth AyersTechnical 215-3570914-3188 A

Kent HainesData 874-0929624-1405 P

Charles CampbellAsst. Project A

Raymond MayneAsst. Data 784-0240785-1355 A

Reason for Meeting:

Weekly development meeting.

Events of Note in Meeting:

1) Reminded group members to complete weekly Evaluations.

2) Project Manager will send email to Asst. Data Administrator requesting corrections be made to Use Case Diagram to remove password and system administration portions of the Use Case.

3) Upon completion of the corrections to the Use Case Diagram, Data Administrator will make appropriate changes to Data Dictionary.

4) User Interface Prototype has been completed and is under review by Project Manager.

PROBLEMS:

1) None

Minutes for Date: 11 October 05

Persons Attending:

NameTitle E-mailPhoneWk Phone Absent/Present

Sam Swafford Project Manager 763-5849none P

Josh SimmonsProject Leader 960-9309none P

Kenneth AyersTechnical 215-3570914-3188 P

Kent HainesData 874-0929624-1405 P

Charles CampbellAsst. Project P

Raymond MayneAsst. Data 784-0240785-1355 P

Reason for Meeting:

Weekly development meeting.

Events of Note in Meeting:

1) Reminded group members to complete weekly Evaluations.

2) As there is no deliverables for next week, Project Leader and Project Manager will begin working on Design Document as time permits.

3) Technical Leader has completed a rough draft of the User Interface Prototype. Will be reviewed by Project Manager.

4) Verification has been recieved that there will be no security requirement for the project.

5) Errors noted by the client in the ERD will be corrected by the Data Administrator.

PROBLEMS:

1) None

Minutes for Date: 4 October 05

Persons Attending:

NameTitle E-mailPhoneWk Phone Absent/Present

Sam Swafford Project Manager 763-5849none P

Josh SimmonsProject Leader 960-9309none P

Kenneth AyersTechnical 215-3570914-3188 P

Kent HainesData 874-0929624-1405 A

Charles CampbellAsst. Project P

Raymond MayneAsst. Data 784-0240785-1355 P

Reason for Meeting:

Weekly development meeting. Verified individual understanding of Deliverable Four (cont.)

Events of Note in Meeting:

1) Covered Deliverable Four requirements.

2) All team members were reminded to complete the weekly Evaluation for Deliverable Four prior to 11 October 05.

3) Responsibility for the User Interface Prototype will be shifted from Josh Simmons to Ken Ayers.

4) Due to communication difficulties between team members, Project Administrator will contact team members via phone in the event a backup will have to complete a task.

4) Responsibility for the Activity Chart will be shifted from Josh Simmons to Sam Swafford to allow the Project Leader to focus on drafting the Design Document.

PROBLEMS:

1) Question was raised as to whether our use case diagrams should reflect password protection.

2) The requirements document instructions list a Class Diagram as part of the document but no team member has been able to locate the example which is supposed to be provided.

Minutes for Date: 27 September 05

Persons Attending:

NameTitle E-mailPhoneWk Phone Absent/Present

Sam Swafford Project Manager 763-5849none P

Josh SimmonsProject Leader 960-9309none P

Kenneth AyersTechnical 215-3570914-3188 P

Kent HainesData 874-0929624-1405 P

Charles CampbellAsst. Project P

Raymond MayneAsst. Data 784-0240785-1355 P

Reason for Meeting:

Weekly development meeting. Verified individual understanding of Deliverable Four.

Events of Note in Meeting:

1) Covered Deliverable Four requirements.

2) All team members were reminded to complete the weekly Evaluation for Deliverable Three prior to 4 October 05.

PROBLEMS:

1) Question was raised as to whether or not the system should be password protected.

Minutes for Date: 20 September 05

Persons Attending:

NameTitle E-mailPhoneWk Phone Absent/Present

Sam Swafford Project Manager 763-5849none A

Josh SimmonsProject Leader 960-9309none P

Kenneth AyersTechnical 215-3570914-3188 P

Kent HainesData 874-0929624-1405 P

Charles CampbellAsst. Project P

Raymond MayneAsst. Data 784-0240785-1355 P

Reason for Meeting:

Weekly development meeting. Verified individual understanding of Deliverable Three.

Events of Note in Meeting:

1) Covered Deliverable Three requirements.

2) Project Plan drafts completed by Project Leader and Project Manager. Project Manager will consolidate the drafts into a final draft.

3) Risk assesment postings from the bulletin board will be compiled by Technical Leader, Data Administrator and Assistant Data Administrator. Project Manager will review and post to the group website.

4) All team members were reminded to complete the weekly Evaluation for Deliverable Two prior to 27 Sept 05.

PROBLEMS:

None

Minutes for Date: 13 September 05

Persons Attending:

NameTitle E-mailPhoneWk Phone Absent/Present

Sam Swafford Project Manager 763-5849none P

Josh SimmonsProject Leader 960-9309none P

Kenneth AyersTechnical 215-3570914-3188 P

Kent HainesData 874-0929624-1405 P

Charles CampbellAsst. Project P

Raymond MayneAsst. Data 784-0240785-1355 P

Reason for Meeting:

Weekly development meeting. Verified individual understanding of Deliverable Two.

Events of Note in Meeting:

1) Covered Deliverable Two requirements.

2) Project Plan will be created by Project Manager and reviewed by Project Leader.

3) Group members will post shall lists and risk assessment bullets to the group bulletin board. Project Manager will compile the risks into the appropriate format for submission.

4) Project Leader reported back on possibility of using Eclipse as a uniform IDE. All team members have or will install Eclipse and use it for development. In the event problems are encountered with Eclipse which cannot be mitigated, the team will revert to JBuilder.

5) All team members were reminded to complete the weekly Evaluation for Deliverable One prior to 20 Sept 05.

PROBLEMS:

1) Project Leader noted that we need clarification as to whether the project required a system which can read any of the three languages given or is the group to chose a single language.

2) Kent Haines noted that the group needs to perform an RE interview with the client (professor). Project Leader and Project Manager will request an interview.

Minutes for Date: 6 September 05

Persons Attending:

NameTitle E-mailPhoneWk Phone Absent/Present

Sam Swafford Project Manager 763-5849none P

Josh SimmonsProject Leader 960-9309none P

Kenneth AyersTechnical 215-3570914-3188 P

Kent HainesData 874-0929624-1405 P

Charles CampbellAsst. Project A

Raymond MayneAsst. Data 784-0240785-1355 P

Reason for Meeting:

Initial project planning meeting. Verified individual understanding of Deliverable One.

Events of Note in Meeting:

1) Decision was made by Project Leader to code the project in Java.

2) Decision was made to allow team members to choose individual IDE’s to work with; this may become an issue if compatibility becomes a problem.

3) Project Leader will investigate the possible value of the team utilizing Eclipse for the project and report back at the next meeting.

4) Project Leader placed a team deadline of 12:00 pm Mondays for all deliverables so that himself and the Data Administrator have sufficient time to perform Quality Control prior to the client imposed Tuesday deadlines.

5) All team members were reminded to complete the weekly Evaluation for Deliverable One prior to 13 Sept 05. Team members were also tasked to begin creating “Shall lists” to be used in development of the project specifications.

PROBLEMS:

1) Project Leader noted that we need clarification as to whether changes to the specifications and project plan must be approved by the Instructor.