MISSOURI DEPARTMENT OF TRANSPORTATION
AVIATION SECTION
CONSTRUCTION PLANS CHECKLIST
(Airport Name) / (Project Number)COVER SHEET
Included Correct N/A
1. Airport name
2. Airport location
3. Owner/Sponsor name
4. MoDOT project number
5. Brief description of project
6. Index of drawing sheets
7. Location map (airport & major highway access)
8. Date
PROJECT LAYOUT PLAN
1. Table of quantities (matches proposal form in the
project manual)
2. Airport layout
3. Site plan
4. Specific improvement notes
5. General construction notes
6. Earthwork table
SAFETY AND PHASING PLAN
1. AC 150/5370-2 “Operational Safety on Airports
During Construction
2. Table of standards (safety areas, object free areas,
obstacle free zones…)
3. Site access
4. Haul routes and staging areas
5. Form 7460-1 Airspace notifications
6 Stock piles
7. NOTAM issuance including navaid shutdowns
8. Sequence of construction
9. Pavement closures and threshold displacements
10. Temporary marking and lighting
11. Barricade requirements
12. Traffic control
13 Environmental issues
14. Security issues
TYPICAL SECTIONS
Included Correct N/A
1. Design criteria matches engineer’s report
2. Runway and/or taxiway width
3. Safety area width
4. Primary surface width
5. Pavement section and thicknesses
6. Transverse slopes for pavement sections
(taxiways have constant cross-slope)
7. Transverse slopes for safety area grading
(constant cross-slope off pavement edge)
8. 1½” pavement edge drop-off
9. Base width beyond pavement edge
10. Depth and density requirements for subgrade
under paved areas
11. Stationing for each typical section
12. Edge drains
RUNWAY PLAN AND PROFILE
1. Horizontal and vertical scale
2. Maximum longitudinal grades
3. Maximum allowable grade change
4. Minimum vertical curve lengths
5. Minimum allowable distance between points of
intersection
6. Minimum line of sight
7. Runway/taxiway separation
8. Fillet dimensions
9. Type of pipe, length, and flow-line grades
10. Flared ends
11. Edge drains, outlet pipes, and splash pads
12. Turnarounds provided
TAXIWAY PLAN AND PROFILE
1. Horizontal and vertical scales
2. Maximum longitudinal grades
3. Maximum allowable grade change
4. Minimum vertical curve lengths
5. Minimum allowable distance between points of
intersection
6. Runway/taxiway separation
7. Fillet dimensions
8. Type of pipe, length, and flow-line grades
9. Flared ends
10. Edge drains, outlet pipes, and splash pads
GRADING AND DRAINAGE PLAN
Included Correct N/A
1. Contour lines
2. All areas will drain properly
3. No ditches in the safety areas
4. Direction of flows indicated
5. Erosion control measures
6. Rock lining at outlet pipe ends
7. Rock lining in steep ditches, which are susceptible
to high erosion
8. Shoulder width is adequate to support footings
for PAPI’s, REIL’s, and runway hold signs
PAVEMENT JOINT PLAN
Chapter 5 - Pavements For Light Aircraft (AC 150/5320-6D):
1. Jointing details1 (reference figures 5-3).
A. Expansion Joints
Type "B" Thickened Edge
B. Contraction Joints
Type "C" Hinged
Type "D" Doweled
Type "E" Dummy
C. Construction Joints
Type "F" Doweled
2. Joint layout patterns1
3. Odd shaped slabs are reinforced
1Since the tension ring design is not used, the general recommendations of Table 3-10A and the joint layout pattern in Figure 3-43 may be employed for light load rigid pavements; however, the consultant should use the joint designations, steel sizes, and spacing as defined in Chapter 5.
PAVEMENT MARKING AND SIGNING PLAN
Runway markings:
1. Runway threshold markings1
2. Runway designation markings1
3. Runway centerline markings1
4. Runway aiming point marking1
5. Runway touchdown zone markings1
6. Runway threshold bar1
7. Demarcation bar1
8. Arrows and arrowheads1
9. Chevrons1
10. Runway holding position markings on runways2
Included Correct N/A
Taxiway markings:
1. Taxiway centerline markings1
2. Runway holding position markings on taxiways2
Runway signing:
1. Non-lighted guidance signs
1All runway and taxiway markings on light colored pavements should be outlined with a 6” black border.
2All hold lines regardless of pavement type shall be outlined in black per Figure B-1 of AC 150/5340-1H.
LIGHTING PLAN
1. Threshold lights
2. Runway lights
3. Taxiway lights (main connector to apron is lighted)
4. Lamp wattage specified for each type light fixture
5. REIL’s
6. PAPI’s (site survey drawing submitted showing
obstacle clearance surface is free of obstructions)
7. Wind cone (clears Part 77)
8. Rotating Beacon (clears Part 77)
9. Apron lights (clear Part 77)
10. Cable type and size
11. Electrical duct
12. Vault and equipment
13 Wiring schematic
14. Cable trench
15. Cable splices
16. Cable/duct markers
CROSS SECTIONS
Runway:
1. Original cross-sections shown
2 Proposed cross-sections match typical sections
3. Elevations at critical points
4. Horizontal and vertical scale
5. Stations for each section
6. Quantities for the cuts and fills
7. Sections wide enough to show all grading
requirements including Part 77 surfaces
Included Correct N/A
Taxiway:
1. Original cross-sections shown
2. Proposed cross-sections match typical
sections
3. Elevations at critical points
4. Horizontal and vertical scale
5. Stations for each section
6. Quantities for the cuts and fills
7. Sections wide enough to show all grading
requirements
MISCELLANEOUS
1. Clearing and grubbing
2. Demolition
3. Apron tie-downs
4. Fencing
5. Entrance road
6. All items listed on the most recent 5010 Safety
Inspection Report have been addressed
7. There are no modifications to standards
ADDITIONAL COMMENTS: