PRELIMINARY PROJECT REPORT (PPR)

INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP)

BLOCK: BORIO

DISTRICT: SAHEBGANJ

PIA

WATERSHED CELL CUM DATACENTER (WCDC)

SAHEBGANJ

NAME OF THE PROJECT: IWMP-I/11-12

YEAR: 2011-2012

SUBMITTED TO

DEPARTMENT OF LAND RESOURCES

MINISTRY OF RURAL DEVELOPMENT

GOVERNMENT OF INDIA

NEW DELHI

JHARKHANDSTATE WATERSHED MISSION- SLNA

DEPARTMENT OF RURAL DEVELOPMENT

4TH FLOOR, FFPBUILDING, DHURWA, RANCHI- 834004

TELEPHONE/ FAX: 91 - 651-2403017, 2401974

E-MAIL:

PROJECT PROPOSAL FOR

INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP)

BLOCK: BORIO

DISTRICT: SAHEBGANJ

SUBMITTED BY

WATERSHED CELL CUM DATACENTER (WCDC)

SAHEBGANJ

DEPARTMENT OF LAND RESOURCES

MINISTRY OF RURAL DEVELOPMENT

GOVERNMENT OF INDIA

NEW DELHI



Format for Preliminary Project Report

I.Institutional Structures.

I. A. State Level Nodal Agencies

I. B. District Level Watershed Units

II.Selection of Watershed Projects

III.Profile of the each selected watershed project

IV.Agro-climatic condition of project area.

V.Demography & land distribution

VI.Livelihoods

VII.Expected project out comes

VIII.Mandatory certificates

IX. Status of on-going projects

X.Abstract of project proposed for sanction

I. Institutional Structures

I. A. State Level Nodal Agencies (SLNAs):

Table-PPR 1: Details of SLNA

1 / 2 / 3 / 4 / 5 / 6
Sl.No. / State / Type of SLNA# / Date of Notification / Date of MoU with DoLR / Total no. of members of SLNA
1 / Jharkhand / Jharkhand state Watershed Mission (No. 103/2009-10 dated 17/7/2009, Registered Under society registration Act 21 of 1860, ) / 4673 Dated
20-06-09 / Under Process / 19 including (CEO)

Whether it is a Department /Mission/ Society/Authority/Others (pl. specify)Society(contd.)

Table-PPR 1: Details of SLNA (Contd.)

7 / 8
Chairperson / CEO
Name / Designation / Name / Designation / Date of Appointment / Nature of appointment / Tenure (No. of Years) / Contact Ph. No./Fax/E-Mail
Governing Body - Mr. Debashis Gupta / Development Commissioner / Mr B Nijalingappa / Chief Executive Officer
State Level Nodal Agency-JharkhandState Watershed Mission
Rural Development Department
Govt. of Jharkhand / Vide notification no. 887 dated
22-02-2010 / On deputation / 3 Years / 0651-2401974
  • ,

Executive Committee- Mr. R.S.Poddar / Principal Secretary, Rural Development

# APC/ ACS/ Dev. Commissioner/ Others (pl. specify)

$ Deputation/ Contract

Table - PPR 2: Details of functionaries in the JSWM-SLNAs*

Details of the persons engaged in the SLNA- Jharkhand State Watershed Mission funded by DoLR
Sl.No / Name & Designation / Monthly remuneration / Date of Appointment / Nature of appointment / Tenure (No. of years) / Contract Ph. No. /
E-mail / Subject of Expertise / Qualifi-cation / Experience / Role
1. / Shri Madan Sengupta
Administrative Officer / 40,000 / 26-05-2010 / On Contract / 1 Yr. / 9431114862
/ Law & Administration / M.Sc. (Geology), B.A.(LLB). / About 32 Years experince. / Administration, Supervision,EC /GB Meetings organisations etc.
2. / Shri. Narayan Kumar Mishra
Technical Expert (Agriculture /Agril. Engineering) / 50,000 / 29th May, 2010 / On contract / 1 Yr. / 9431574367, / Watershed Management, Soil and Water Conservation, GIS & Remote Sensing / Master of Engineering (Ag), B Tech (Agril. Engineering). PGDRD, NET, GATE / 12years of relevant experiences in watershed mgt. and development, agriculture dev., rural and social dev., / To give the technical assistance & Monitoring & evaluation of the projects.
3. / Shri. Anupam Bharti
Technical Expert (Livelihood) / 50,000 / 29.05.10 / On Contract / 1 Yr. / 9308351370
, / Horticulture, Rural development / M Sc (horticulture) / 10 years of relevant experience in agriculture, rural dev., horticulture, marketing, retail / To give the technical assistance & Monitoring & evaluation of the projects.
4. / Shri. Kaushlendra Kumar
Techninical Expert in CapacityBuilding (Water Management) / 50,000 / 29.05.2010 / On contract / 1 Yr. / 9431071292
/ Soil & Water Conservation and Watershed managemrnt / B Tech (Agricultural Engineering ), M Tech in Agricultural Engineering (Soil and Water Conservation) and PGDRD / 12 years of working experiences in watershed management, soil and water conservation, rural development and GIS / To give the technical assistance & Monitoring & evaluation of the projects
5. / Shri. Lakhan Lal Mahato
GIS Expert / 40,000 / 29-05-2010 / On Contract / 1 Yr. / 9470335956 / GIS & Remote Sensing / M.Tech (Remote Sensing) / 10 years
In the field of GIS and Remote Sensing / GIS, RS and Geodatabase management
6. / Smt. Jyoti Pushpa
Finance Officer / 40,000 / 24.08.2010 / On Contract / 1 Yr. / 9905582591
/ Accountancy / CA / 13 Years / Finance Management
7. / Smt. Pratibha Kumari
Accounts Officer / 35,000 / 15.09.2010 / On Contract / 1 Yr. / / Finance / M Com, MBA in Finance / 5 Yrs 6 Months / Accounts Management
8. / Smt. Shyama, Account Assistant / 25,000 / 1st June 2010 / On Contract / 1 Yr. / 9472018349 / Finance / M Com, MBA in Finance / 8 years / Accounting
9. / Shri. Ajeet Kumar Ravi
Account Assistant / 25,000 / 26th May, 2010 / On Contract / 1 Yr. / 9471764888/ / Accounts / B Com (Account Hons) / 4 years / Accounting
10. / Shri. Amit Kumar
DEO-cum-Assistant / 15,000 / 31-05-2010 / On Contract / 1 Yr. / 9308754952 / / GIS / MIS, B.Sc.(Computer Application) / About 8 Years / GIS, RS & MIS database management
11. / Shri. Amrendra Kumar
DEO-cum-Assistant / 15,000 / 29-05-2010 / On Contract / 1 Yr. / 9431184303 / / Database Admin. / MCA / About 7 Years / MIS Expert, Data Entry & Assistant
12. / Shri. Vipul Akash
DEO-cum-Assistant / 15,000 / 1st June, 2010 / On Contract / 1 Yr. / 9472741901 / / computer operator / MCA / 2 years / File dispatch and receipt
Note: 1. Total outlay per Month for 12 SLNA-JSWM staffs under IWMP is Rs. 4.00 Lakhs

R – Recurring; NR- Non-recurring

* From column no. 3, totals no. of persons, from column no. 7 to 9, totals, may be indicated for the State at the end of the table.

Table PPR-3: Details of State Level Data Cell (SLDC) functionaries

1 / 2 / 3 / 4 / 5 / 6 / 7 / 8 / 9
S. No / Total no. of the persons working in the SLNA for IWMP / Name & Designation / Qualification / Experience / Work allocation / Monthly remuneration (Rs.) / Total budget of SLDC
(Rs. In Lakh) / Funding expected from DoLR
(Rs. In Lakh)
R / NR / R / NR
1 / 1 / Shri. Vinod Kumar. V. H,
Project Co-ordinator / M Tech (Water Resources) / 6 years / Creation and updation of Geodatabase under IWMP Project using satellite data / 20,000.00
2 / 1 / Shri. Anuj Shankar,
MISState Coordinator / MCA / 4 years / Updation of all the thematic layer using MIS Software development / 15000.00
3 / 3 / Shri. Abdul Saqoor, Field Supervisor / M Sc (IT) / 5 years / Updation of data using GIS & Remote Sensing software and collection of field level data under watershed project / 10000.00
4 / Vishal Kumar
Field Supervisor / B Sc (Fisheries), MBA, Rural Management / 5 years / Updation of data using GIS & Remote Sensing software and collection of field level data under watershed project / 10000.00
5 / Ratnesh Kumar Sharma
Field Supervisor / M Sc (Math), Advance Diploma in Computer Application / 6 years / Updation of data using GIS & Remote Sensing software and collection of field level data under watershed project / 10000.00
Total / 5 / 65,000.00

Note-1. Payment of above experts / staffs is being paid by state budget of JSAC

2. SLDC has been established at JSAC. However it is planning to establish SLDC in the office of JSWM.

R – Recurring; NR- Non-recurring

* From column no. 3, totals no. of persons, from column no. 7 to 9, totals, may be indicated for the State at the end of the table.

I. B. District Level Watershed Units

Table-PPR 4: Details of functionaries in the DRDA Watershed Cell*

S. No. / Name of the District / Name of the executing Agency# / Status of Chairman @ / Date of signing of MoU with SLNA / Total no. of persons working for Watershed programme / Names & Designation / Qualification / Experience / Work allocation
19 IWMP Districts / WCDC / D.D.C / NA / 3 ( in each district) / 1. Technical Expert / Bachelor degree in the fields of agriculture/ horticulture/hydrology/soil engineering and animal husbandry with goog academic records / The candidate should have at least 5 years field / research experience in the fields of soil and water conservation/ forestry/ dry land agriculture/horticulture/ watershed management or related fields like assessment, management and mitigation of drought climatic and other associated risks, crop husbandry, crop specific technology, horticultural practices, livelihoods, animal husbandry etc / Remarks:
1. The committee will advice the district data cell for monitoring and evaluation.
2. The committee will facilitate for preparing of prospective plan
3. The committee will identify voluntary organization
2. Accountant / A serving govt. officer on deputation or a retd. Govt. officer from a finance/ accounts service / 5 years experience in related work at reputed firm/organization
3. Data Entry Operator / BSc Hons (Computer Science) or BCA or PGDCA or MCA will be preferred. / 2 years experience in field of MIS

(contd.)

11 / 12
Monthly remuneration/year in each district
(in Rs.) / Total Annual budget of Watershed Cell in each district
(Rs. In Lakh)
R / NR
1. Project Manager cum Technical Expert - 25000 / 3 Lakh
2. Accountant - 10000/1.20 Lakh
3. DEO - 7500/0.9 Lakh / 5.10 lakh / 4.00 lakh

R – Recurring;NR- Non-recurring

*From column no. 2, no. of districts; from column no. 3, no. of executive agencies; from column no. 6, no. of persons working in the executive agencies of watershed programme; from column no.7, total no. of personnel engaged in the watershed cells, from column no. 11 to 13, totals for the State may be indicated at the end of the table.

WCDC/ DRDA/Zilla Parishad (ZP)/ State Department (please specify)/ Any other (Please specify)

@collector/CEO ZP/ CDO/ DDO/ PD/ Any other (please specify)

II. SELECTION OF WATERSHED PROJECTS

Table-PPR 5: status of District-wise area covered under the watershed programme* (MIS Table-M (SP) 2)

S. no. / Names of Districts / Total micro-watersheds in the District / Micro-watersheds covered so far / Net watersheds to be covered
Dept. of Land Resources / Other Ministries/ Depts. / Total watersheds covered
Pre-IWMP projects (DPAP + DDP + IWDP) / Any other watershed project
No. / Area (ha.) / No. / Area (ha.) / No. / Area (ha.) / No. / Area (ha.) / No. / Area (ha.)
1 / SAHEBGANJ / 54 / 1,50,414 / 38 / 36,000 / 11 / 5460 / 49 / 41,460 / 5 / 1,08,954

* Fromcolumn no. 2, total no. of districts; from columns 3 to 5, the totals for the entire State may be given at the end of the table.

STATUS OF IWMP PROJECTS SANCTIONED DURING 2009-10, 2010-11 2011-12 OF RAMGARH DISTRICT

S.No / District / Block / Sanctioned Year / No. of Micro-Watershed / Treatable Area
( in Ha)
1 / SAHEBGANJ / - / 2009-10 / NIL / NIL
2 / - / 2010-11 / NIL / NIL
3 / 2011-12 / NIL / NIL
Total / NIL / NIL

Table-PPR 6: Prioritized list of projects proposed for sanction during the financial year 2011-12

S. No. / District / Name of the project / No. of micro-watersheds proposed to covered / Proposed project area (ha) / Type of project (Hilly/Desert/Others) / Proposed cost (Rs. In lakh) / Weightage under the criteria#
i / ii / iii / iv / v / vi / vii / viii / ix / x / xi / xii / xiii / Total
1 / SAHEBGANJ / IWMP / 03 / 5483.52 / OTHER / 658.02240 / 10 / 10 / 5 / 10 / 10 / 10 / 10 / 7.5 / 15 / 10 / 10 / 10 / - / 117.5

* from column no. 2, total no. of districts, from column no. 3, total no. of projects selected for sanction, from column no.4, total no. of micro-watersheds to be covered, from column no.5, total project area proposed, from column no. 7, total cost proposed, may be indicated for the entire State at the end of the table.

# Criteria and weightage for selection of watershed

S No. / Criteria / Maximum score / Ranges & scores
i / Poverty index(%of poor to population) / 10 / Above 80% (10) / 80 to 50 % (7.5) / 50 to 20 % (5) / Below 20% (2.5)
ii / % of SC/ST population / 10 / More than 40% (10) / 20 to 40 % (5) / Less than 20% (3)
iii / Actual wages / 5 / Actual wages are significantly lower than minimum wages (5) / Actual wages are equal to or higher than minimum wages (0)
iv / % of small and marginal farmers / 10 / More than 80% (10) / 50 to 80% (5) / Less than 50% (3)
v / Ground water status / 15 / Over exploited( 15) / Critical (10) / Sub critical (5) / Safe (0)
vi / Moisture index/ DPAP/DDP Block / 15 / -66.7 & below (15) DDP Block / -33.3 to -66.6 (10) DPAP Block / 0 to -33.2 (0) Non DPAP/DDP Block
vii / Area under rain-fed agriculture / 15 / More than 90% (15) / 80 to 90% (10) / 70 to 80% (5) / Above 70% (Reject)
viii / Drinking water / 10 / No source (10) / Problematic village (7.5) / Partially covered (5) / Fully covered (0)
ix / Degraded land / 15 / High – above 20% (15) / Medium – 10 to 20 % (10) / Low – less than 10 % of TGA (5)
x / Productivity potential of the land / 15 / Lands with low production & where productivity can be significantly enhanced with reasonable efforts (15) / Land with moderate production & where productivity can be enhanced with reasonable efforts (10) / Lands with high production & where productivity can be marginally enhanced with reasonable efforts (5)
xi / Contiguity to another watershed that has already been developed/treated / 10 / Contiguous to previously treated watershed & contiguity within the micro watersheds in the project (10) / Contiguity with in the micro watersheds in the project but non contiguous to previously treated watershed (5) / Neither contiguous to previously treated watershed nor contiguity within the micro watersheds in the project (0)
xii / Cluster approach in the plains (more than one contiguous micro-watersheds in the project) / 15 / Above 6 micro-watersheds in cluster (15) / 4 to 6 micro watersheds in cluster (10) / 2 to 4 micro watersheds in cluster (5)
xiii / Cluster approach in the hills (More than one contiguous micro- watersheds in the project) / 15 / Above 5 micro-watersheds in cluster (15) / 3 to 5 micro watersheds in cluster (10) / 2 to 3 micro watersheds in cluster (5)
Total / 150 / 150 / 90 / 41 / 2.5

PROJECT WISE PROFILE OF THE SELECTED WATERSHED PROJECT

Table – PPR 7: Project at a Glance

1 / Name of the State / JHARKHAND
2 / Name & type# (Hilly/ Desert/ Others) of project / OTHERS
3 / Name of the District / SAHEBGANJ
4 / Name of the Blocks / BORIO
5 / Name of Gram Panchayats / APROL / BARA RAKSO / BIRBALKANDAR / BORRIO (SANTALI) / CHASGANWAN / POAL
BANJHI SANSTHALI / BICHPURA / BISHUNPUR / BORRIO BAZAR / KHAIRWA / TELO
6 / Names & Census Code of Villages covered / SL.NO / VILLAGE NAME / VILLAGE CODE / SL.NO / VILLAGE NAME / VILLAGE CODE / SL.NO / VILLAGE NAME / VILLAGE CODE
1 / Amjani / 290020002000200273 / 22 / Dighi / 290020002000200228 / 43 / Matia / 290020002000200229
2 / Amjanipahar / 290020002000200260 / 23 / Digra / 290020002000200281 / 44 / Matia Bedo / 290020002000200284
3 / Aprol / 290020002000200263 / 24 / Digra Rakso / 290020002000200261 / 45 / Pandriya / 290020002000200059
4 / Bagduma / 290020002000200226 / 25 / Dobni / 290020002000200282 / 46 / Pathara / 290020002000200049
5 / Bandjhi / 290020002000200185 / 26 / Dumaria / 290020002000200063 / 47 / Patharghata / 290020002000200271
6 / Bara Rakso / 290020002000200213 / 27 / Gauripur / 290020002000200057 / 48 / Patlohara / 290020002000200248
7 / Batbanga / 290030003000300210 / 28 / Gorda / 290020002000200266 / 49 / Rampur Bansjori / 290020002000200080
8 / Bhurkunda / 290020002000200262 / 29 / Gorgama / 290020002000200269 / 50 / Ranchaura / 290020002000200061
9 / Bichpura / 290020002000200054 / 30 / Harinchora / 290020002000200062 / 51 / Sabaiya / 290020002000200214
10 / Binderi (Bender Kol / 290020002000200099 / 31 / Jamkundar / 290020002000200211 / 52 / Simra / 290020002000200268
11 / Birbal Kandar / 290020002000200184 / 32 / Jurul / 290020002000200050 / 53 / Telabani khaplo / 290020002000200212
12 / Borrio(Santali) / 290020002000200055 / 33 / Kadma / 290020002000200259 / 54 / Telo / 290020002000200048
13 / Bunda / 290020002000200276 / 34 / Kalkha / 290020002000200051 / 55 / Tetuliya / 290020002000200183
14 / Chapgawan / 290020002000200060 / 35 / Kandua / 290020002000200210 / 56 / Turua / 290020002000200227
15 / Chhota Bandar Kola / 290020002000200064 / 36 / Khairwa / 290020002000200079
16 / Chhota Kusma / 290020002000200249 / 37 / Kordiha / 290020002000200215
17 / Chiutiya / 290020002000200230 / 38 / Lakrakol / 290020002000200270
18 / Danowara / 290020002000200058 / 39 / Mahisol / 290020002000200267
19 / Danware / 290020002000200114 / 40 / Majhauna / 290020002000200264
20 / Ddepart / 290020002000200280 / 41 / Mangra / 290020002000200258
21 / Dhanela / 290020002000200052 / 42 / Marichak / 290020002000200265
7 / Names & Census Code of micro- watersheds / Sl. No. / Micro Watershed Code / Area of the Micro Watershed / Proposed Area to be treated / Budget (Proposed Area X 0.12)
(Rs.in Lakh) / Remarks
1 / 2A3E5e1a / 1976.58 / 1664.44 / 199.73280 / Proposed Area to be treated = PF/Others+ Rainfed+ Per.Pasture+ Cult.WL
2 / 2A3E5e1m / 2060.83 / 1885.21 / 226.22520
3 / 2A3E5e1n / 2066.76 / 1933.87 / 232.06440
TOTAL / 6104.17 / 5483.52 / 658.02240
8 / Four major reasons for selection of watershed /
  • There is acute shortage of water for drinking and irrigation
  • Preponderance of culturable and unculturable wastelands
  • The area is remote, forested, having preponderance of S.C & S.T population
  • Area is contiguous to another cluster where where IWMP is under progress and people's response towards it has been stupendous

9 / Area of the Project (ha.) / 6104.17
10 / Area proposed to be treated (ha.) / 5483.52
11 / Project cost (Rs. In Lakhs) / 658.02240
12 / Name & Address of proposed PIA / WATERSHED CELL CUM DATACENTER (WCDC)
SAHEBGANJ
13 / Any other (please specify) / -

Table – PPR 8: Details of previously identified DPAP /DDP areas proposed under IWMP (ha.) during the financial year 2011-12.

1 / 2 / 3 / 4 / 5 / 6 / 7 / 8 / 9 / 10 / 11 / 12
S. No. / Names of Districts / Name of the project proposed / Name of Block / Type of Block (DPAP/ DDP /IWDP) / Area of Block (ha.) / No. of pre- IWMP projects sanctioned in the Block / Area of sanctioned Projects / Net area to be covered / Area of the proposed project / Area proposed to be covered by schemes other than DoLR / Net balance area
1 / SAHEBGANJ / IWMP / BORIO / IWDP / NA / NA / NA / NA / 5483.52 / NA / NA

*from column no. 2, total no. of districts, from column no. 3, total no. of projects proposed, from column no.4, total no. of Blocks, from column no.6 to 12, totals, may be indicated for the entire State at the end of the table.

PPR 9: Land Use pattern to the project *

DISTRICT: SAHEBGANJ, BLOCK: BORIO
1 / 2 / 3 / 4 / 5 / 6 / 7 / 8 / 9 / 10 / 11 / 12 / 13 / 14 / 15 / 16
Wasteland
Sl. No. / Micro Watershed Code / Area of the Micro Watershed / Village Name / Geographical Area of the Village (Full/Part) / Forest Area (7+8) / RF / PF/Others / AgriculturalLand in use (10+11) / Rainfed / Irrigated Land / Permanent Pasture / Cultivable / Non Cultivable / Proposed Area to be treated (8+10+12+13) / Budget (Proposed Area X 0.12)
(Rs.in Lakh)
1 / 2A3E5e1a / 1976.58 / Bichpura / 239.73 / 0.00 / 0.00 / 0.00 / 200.76 / 183.60 / 17.16 / 3.72 / 1.41 / 33.84 / 188.73 / 22.64760
Binderi (Bender Kol / 197.96 / 188.07 / 0.00 / 188.07 / 6.82 / 6.03 / 0.79 / 3.07 / 0.00 / 0.00 / 197.17 / 23.66040
Borrio(Santali) / 172.13 / 0.00 / 0.00 / 0.00 / 165.49 / 149.70 / 15.79 / 2.67 / 0.00 / 3.97 / 152.37 / 18.28440
Chapgawan / 45.17 / 0.00 / 0.00 / 0.00 / 44.68 / 39.53 / 5.15 / 0.00 / 0.00 / 0.49 / 39.53 / 4.74360
Chhota Bandar Kola / 3.88 / 1.52 / 0.00 / 1.52 / 2.36 / 2.09 / 0.27 / 0.00 / 0.00 / 0.00 / 3.61 / 0.43320
Chhota Kusma / 0.32 / 0.00 / 0.00 / 0.00 / 0.32 / 0.28 / 0.04 / 0.00 / 0.00 / 0.00 / 0.28 / 0.03360
Danowara / 71.93 / 0.00 / 0.00 / 0.00 / 63.69 / 56.98 / 6.71 / 0.88 / 0.00 / 7.36 / 57.86 / 6.94320
Danware / 34.38 / 5.08 / 0.00 / 5.08 / 11.61 / 10.27 / 1.34 / 0.00 / 17.69 / 0.00 / 33.04 / 3.96480
Dhanela / 48.09 / 0.00 / 0.00 / 0.00 / 38.45 / 34.02 / 4.43 / 0.00 / 0.00 / 9.64 / 34.02 / 4.08240
Dumaria / 10.19 / 0.00 / 0.00 / 0.00 / 9.87 / 8.73 / 1.14 / 0.00 / 0.00 / 0.32 / 8.73 / 1.04760
Gauripur / 125.05 / 0.00 / 0.00 / 0.00 / 113.84 / 102.98 / 10.86 / 1.94 / 0.00 / 9.27 / 104.92 / 12.59040
Harinchora / 199.99 / 23.86 / 0.00 / 23.86 / 167.56 / 151.57 / 15.99 / 3.10 / 1.85 / 3.62 / 180.38 / 21.64560
Jurul / 70.19 / 0.00 / 0.00 / 0.00 / 64.62 / 57.82 / 6.80 / 0.86 / 0.00 / 4.71 / 58.68 / 7.04160
Kalkha / 52.43 / 0.00 / 0.00 / 0.00 / 45.91 / 40.62 / 5.29 / 0.64 / 0.00 / 5.88 / 41.26 / 4.95120
Khairwa / 203.22 / 0.00 / 0.00 / 0.00 / 178.20 / 161.20 / 17.00 / 3.15 / 0.00 / 21.87 / 164.35 / 19.72200
Pandriya / 89.66 / 0.00 / 0.00 / 0.00 / 82.27 / 73.61 / 8.66 / 1.09 / 0.00 / 6.30 / 74.70 / 8.96400
Pathara / 0.01 / 0.00 / 0.00 / 0.00 / 0.01 / 0.01 / 0.00 / 0.00 / 0.00 / 0.00 / 0.01 / 0.00120
Patharghata / 97.70 / 8.57 / 0.00 / 8.57 / 84.80 / 75.87 / 8.93 / 1.19 / 0.00 / 3.14 / 85.63 / 10.27560
Patlohara / 50.60 / 0.00 / 0.00 / 0.00 / 49.98 / 44.22 / 5.76 / 0.62 / 0.00 / 0.00 / 44.84 / 5.38080
Rampur Bansjori / 32.90 / 0.00 / 0.00 / 0.00 / 22.55 / 19.95 / 2.60 / 0.00 / 0.00 / 10.35 / 19.95 / 2.39400
Ranchaura / 152.59 / 14.00 / 0.00 / 14.00 / 130.30 / 117.87 / 12.43 / 2.37 / 0.00 / 5.92 / 134.24 / 16.10880
Telo / 1.21 / 0.00 / 0.00 / 0.00 / 1.21 / 1.07 / 0.14 / 0.00 / 0.00 / 0.00 / 1.07 / 0.12840
Blank / 77.25 / 0.00 / 0.00 / 0.00 / 43.10 / 38.13 / 4.97 / 0.94 / 0.00 / 33.21 / 39.07 / 4.68840
TOTAL / 1976.58 / 241.10 / 0.00 / 241.10 / 1528.40 / 1376.15 / 152.25 / 26.24 / 20.95 / 159.89 / 1664.44 / 199.73280
2 / 2A3E5e1m / 2060.83 / Amjani / 1.83 / 1.83 / 0.00 / 1.83 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 1.83 / 0.21960
Amjanipahar / 32.63 / 32.63 / 0.00 / 32.63 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 32.63 / 3.91560
Bagduma / 99.59 / 53.17 / 0.00 / 53.17 / 41.17 / 36.43 / 4.74 / 1.21 / 4.04 / 0.00 / 94.85 / 11.38200
Bandjhi / 158.64 / 6.52 / 0.00 / 6.52 / 123.93 / 112.11 / 11.82 / 2.46 / 1.47 / 24.26 / 122.56 / 14.70720
Bara Rakso / 274.62 / 122.19 / 0.00 / 122.19 / 105.75 / 95.66 / 10.09 / 4.26 / 26.04 / 16.38 / 248.15 / 29.77800
Bedo Gadra / 13.84 / 13.84 / 0.00 / 13.84 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 13.84 / 1.66080
Birbal Kandar / 125.20 / 18.58 / 0.00 / 18.58 / 65.54 / 58.64 / 6.90 / 1.94 / 27.50 / 11.64 / 106.66 / 12.79920
Bunda / 32.13 / 32.13 / 0.00 / 32.13 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 32.13 / 3.85560
Chiutiya / 55.85 / 42.65 / 0.00 / 42.65 / 12.52 / 11.08 / 1.44 / 0.68 / 0.00 / 0.00 / 54.41 / 6.52920
Ddepart / 18.45 / 17.95 / 0.00 / 17.95 / 0.50 / 0.44 / 0.06 / 0.00 / 0.00 / 0.00 / 18.39 / 2.20680
Dighi / 100.18 / 0.00 / 0.00 / 0.00 / 97.47 / 87.21 / 10.26 / 1.55 / 0.00 / 1.16 / 88.76 / 10.65120
Digra / 52.72 / 52.08 / 0.00 / 52.08 / 0.00 / 0.00 / 0.00 / 0.64 / 0.00 / 0.00 / 52.72 / 6.32640
Digra Rakso / 61.95 / 61.19 / 0.00 / 61.19 / 0.00 / 0.00 / 0.00 / 0.76 / 0.00 / 0.00 / 61.95 / 7.43400
Dobni / 196.62 / 186.65 / 0.00 / 186.65 / 6.92 / 6.12 / 0.80 / 3.05 / 0.00 / 0.00 / 195.82 / 23.49840
Jamkundar / 31.66 / 21.59 / 0.00 / 21.59 / 10.07 / 8.91 / 1.16 / 0.00 / 0.00 / 0.00 / 30.50 / 3.66000
Kadma / 134.59 / 54.98 / 0.00 / 54.98 / 73.81 / 66.04 / 7.77 / 2.09 / 0.00 / 3.71 / 123.11 / 14.77320
Kandua / 17.07 / 0.15 / 0.00 / 0.15 / 16.92 / 14.97 / 1.95 / 0.00 / 0.00 / 0.00 / 15.12 / 1.81440
Kordiha / 153.06 / 15.40 / 0.00 / 15.40 / 106.46 / 96.30 / 10.16 / 2.37 / 19.75 / 9.08 / 133.82 / 16.05840
Mangra / 36.90 / 10.97 / 0.00 / 10.97 / 25.93 / 22.94 / 2.99 / 0.00 / 0.00 / 0.00 / 33.91 / 4.06920
Matia / 121.88 / 22.75 / 0.00 / 22.75 / 95.98 / 85.87 / 10.11 / 1.89 / 0.00 / 1.26 / 110.51 / 13.26120
Matia Bedo / 53.33 / 47.83 / 0.00 / 47.83 / 4.85 / 4.29 / 0.56 / 0.65 / 0.00 / 0.00 / 52.77 / 6.33240
Sabaiya / 162.70 / 17.01 / 0.00 / 17.01 / 137.27 / 124.17 / 13.10 / 2.52 / 1.45 / 4.45 / 145.15 / 17.41800
Telabani khaplo / 0.49 / 0.49 / 0.00 / 0.49 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 0.49 / 0.05880
Tetuliya / 2.71 / 2.71 / 0.00 / 2.71 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 2.71 / 0.32520
Turua / 122.19 / 27.48 / 0.00 / 27.48 / 92.82 / 83.05 / 9.77 / 1.89 / 0.00 / 0.00 / 112.42 / 13.49040
TOTAL / 2060.83 / 862.77 / 0.00 / 862.77 / 1017.91 / 914.23 / 103.68 / 27.96 / 80.25 / 71.94 / 1885.21 / 226.22520
3 / 2A3E5e1n / 2066.76 / Amjani / 45.29 / 45.29 / 0.00 / 45.29 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 45.29 / 5.43480
Amjanipahar / 26.23 / 26.23 / 0.00 / 26.23 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 26.23 / 3.14760
Aprol / 293.60 / 15.02 / 0.00 / 15.02 / 250.33 / 228.93 / 21.40 / 4.55 / 0.00 / 23.70 / 248.50 / 29.82000
Batbanga / 267.01 / 262.87 / 0.00 / 262.87 / 0.00 / 0.00 / 0.00 / 4.14 / 0.00 / 0.00 / 267.01 / 32.04120
Bhurkunda / 46.77 / 46.77 / 0.00 / 46.77 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 0.00 / 46.77 / 5.61240
Binderi (Bender Kol / 748.92 / 680.78 / 0.00 / 680.78 / 44.18 / 39.09 / 5.09 / 11.61 / 0.00 / 12.35 / 731.48 / 87.77760
Digra / 194.87 / 191.85 / 0.00 / 191.85 / 0.00 / 0.00 / 0.00 / 3.02 / 0.00 / 0.00 / 194.87 / 23.38440
Gorda / 174.13 / 4.08 / 0.00 / 4.08 / 147.67 / 133.58 / 14.09 / 2.70 / 0.00 / 19.68 / 140.36 / 16.84320
Gorgama / 22.03 / 0.00 / 0.00 / 0.00 / 22.03 / 19.49 / 2.54 / 0.00 / 0.00 / 0.00 / 19.49 / 2.33880
Lakrakol / 10.20 / 0.00 / 0.00 / 0.00 / 10.20 / 9.02 / 1.18 / 0.00 / 0.00 / 0.00 / 9.02 / 1.08240
Mahisol / 9.59 / 0.00 / 0.00 / 0.00 / 9.59 / 8.49 / 1.10 / 0.00 / 0.00 / 0.00 / 8.49 / 1.01880
Majhauna / 5.73 / 0.00 / 0.00 / 0.00 / 5.73 / 5.07 / 0.66 / 0.00 / 0.00 / 0.00 / 5.07 / 0.60840
Mangra / 90.30 / 50.30 / 0.00 / 50.30 / 29.98 / 26.53 / 3.45 / 1.10 / 0.00 / 8.92 / 77.93 / 9.35160
Marichak / 19.84 / 0.00 / 0.00 / 0.00 / 17.58 / 15.55 / 2.03 / 0.00 / 0.00 / 2.26 / 15.55 / 1.86600
Patharghata / 51.18 / 11.62 / 0.00 / 11.62 / 38.94 / 34.45 / 4.49 / 0.62 / 0.00 / 0.00 / 46.69 / 5.60280
Ranchaura / 6.70 / 0.00 / 0.00 / 0.00 / 6.70 / 5.93 / 0.77 / 0.00 / 0.00 / 0.00 / 5.93 / 0.71160
Simra / 54.37 / 8.62 / 0.00 / 8.62 / 40.58 / 35.91 / 4.67 / 0.66 / 0.00 / 4.51 / 45.19 / 5.42280
TOTAL / 2066.76 / 1343.43 / 0.00 / 1343.43 / 623.51 / 562.04 / 61.47 / 28.40 / 0.00 / 71.42 / 1933.87 / 232.06440
GRAND TOTAL / 6104.17 / 2447.30 / 0.00 / 2447.30 / 3169.82 / 2852.42 / 317.40 / 82.60 / 101.20 / 303.25 / 5483.52 / 658.02240

Source: JSAC, Dept. of IT, Govt. of Jharkhand
Table - PPR 10: Details of Agro-Climatic Condition*

IV. AGRO – CLIMATIC CONDITION
Briefly describe the agro- climatic condition of project area including the Agro-climatic zone of project area, soil types, rainfall, major crops, etc.
1 / 2 / 3 / 4 / 5 / 6 / 7 / 8 / 9
S. No. / Name of the Project / Name of the Agro-climatic zone covers project area / Area in ha / Names of the villages / Major soil types / Topography / Average rainfall in mm (preceding 5 years average) / Major crops
a) Type / b) Area in ha / a) Name / b) Area in ha
1 / IWMP / CENTRAL AND NORTH EASTERN PLATEAU / 6104.17 / Detailed enclosed in Table-PPR-9 / Sandy loam / 2100.00 / Undulating / 1119.00 / Paddy / 2750.00
Red laterite soil / 1950.00 / moderate to steep Slope / Pulses / 575.00
Alluvial soil / 2054.00 / Oil Seeds / 350.00
Maize / 125.00
Potato / 65.00
Millets / 35.00
Vegetables / 55.00

Table-PPR 11: Details of flood and drought in the project area

1 / 2 / 3 / 4 / 5
Sl.
No. / Particulars / Villages / Periodicity / Not
affected
Annual / Any other
(please specify)
1 / Flood / No. of villages / 56
Name (s) of villages / NA
2 / Drought / No. of villages / All villages mentioned in PPR-9 / 3 to 5 yrs.

Table-PPR 12: Details of soil erosion in the project area

1 / 2 / 3 / 4 / 5
Cause / Type of
Erosion / Area affected
(ha.) / Run off
(mm/Year) / Average soil loss
Tones/ha/year)
Undulating degraded area frequented by domestic cattle / Sheet / 2100.00 / 900.00 / Na
Rill / 175.00
Gully / 580.00
Total / 2855.00

V.DEMOGRAPHY AND LAND DISTRIBUTION

Growth in population during the last three census’, per capita availability of land, sex ratio, population age group in the project area, literacy level, migration, workforce available in different sectors of the economy, demography of SC, ST, BPL and landless families in the project area in the last ten years, etc. (Attached as Ann-01and Ann-02)

Demography and Land Distribution
Population
Sl. / Name of Village / Total / Male / Female / Total SC / Total ST / Sex Ratio
Total / Male / Female / Total / Male / Female
1 / Amjani / 34 / 18 / 16 / 0 / 0 / 0 / 34 / 18 / 16 / 889
2 / Amjanipahar / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0
3 / Aprol / 1546 / 750 / 796 / 0 / 0 / 0 / 1119 / 548 / 571 / 1061
4 / Bagduma / 192 / 95 / 97 / 0 / 0 / 0 / 192 / 95 / 97 / 1021
5 / Bandjhi / 1356 / 820 / 536 / 138 / 76 / 62 / 988 / 626 / 362 / 654
6 / Bara Rakso / 741 / 369 / 372 / 23 / 13 / 10 / 521 / 260 / 261 / 1008
7 / Batbanga / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0
8 / Bhurkunda / 85 / 44 / 41 / 0 / 0 / 0 / 85 / 44 / 41 / 932
9 / Bichpura / 1597 / 795 / 802 / 57 / 29 / 28 / 531 / 263 / 268 / 1009
10 / Binderi (Bender Kol / 315 / 142 / 173 / 0 / 0 / 0 / 315 / 142 / 173 / 1218
11 / Birbal Kandar / 677 / 336 / 341 / 0 / 0 / 0 / 668 / 330 / 338 / 1015
12 / Borrio(Santali) / 2740 / 1389 / 1351 / 38 / 17 / 21 / 573 / 267 / 306 / 973
13 / Bunda / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0
14 / Chapgawan / 267 / 138 / 129 / 0 / 0 / 0 / 0 / 0 / 0 / 935
15 / Chhota Bandar Kola / 144 / 80 / 64 / 0 / 0 / 0 / 144 / 80 / 64 / 800
16 / Chhota Kusma / 280 / 152 / 128 / 80 / 45 / 35 / 0 / 0 / 0 / 842
17 / Chiutiya / 92 / 43 / 49 / 0 / 0 / 0 / 92 / 43 / 49 / 1140
18 / Danowara / 738 / 396 / 342 / 29 / 12 / 17 / 5 / 3 / 2 / 864
19 / Danware / 62 / 28 / 34 / 0 / 0 / 0 / 62 / 28 / 34 / 1214
20 / Ddepart / 229 / 103 / 126 / 0 / 0 / 0 / 229 / 103 / 126 / 1223
21 / Dhanela / 605 / 315 / 290 / 0 / 0 / 0 / 605 / 315 / 290 / 921
22 / Dighi / 335 / 179 / 156 / 35 / 16 / 19 / 258 / 138 / 120 / 872
23 / Digra / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0
24 / Digra Rakso / 58 / 30 / 28 / 0 / 0 / 0 / 58 / 30 / 28 / 933
25 / Dobni / 95 / 46 / 49 / 0 / 0 / 0 / 95 / 46 / 49 / 1065
26 / Dumaria / 424 / 209 / 215 / 0 / 0 / 0 / 411 / 202 / 209 / 1029
27 / Gauripur / 751 / 386 / 365 / 12 / 5 / 7 / 330 / 176 / 154 / 946
28 / Gorda / 702 / 351 / 351 / 6 / 2 / 4 / 663 / 336 / 327 / 1000
29 / Gorgama / 579 / 290 / 289 / 0 / 0 / 0 / 220 / 112 / 108 / 997
30 / Harinchora / 876 / 442 / 434 / 0 / 0 / 0 / 660 / 330 / 330 / 982
31 / Jamkundar / 106 / 51 / 55 / 0 / 0 / 0 / 106 / 51 / 55 / 1078
32 / Jurul / 907 / 454 / 453 / 230 / 121 / 109 / 513 / 250 / 263 / 998
33 / Kadma / 367 / 181 / 186 / 41 / 17 / 24 / 320 / 161 / 159 / 1028
34 / Kalkha / 744 / 369 / 375 / 0 / 0 / 0 / 274 / 124 / 150 / 1016
35 / Kandua / 321 / 157 / 164 / 0 / 0 / 0 / 319 / 155 / 164 / 1045
36 / Khairwa / 919 / 447 / 472 / 0 / 0 / 0 / 686 / 332 / 354 / 1056
37 / Kordiha / 378 / 196 / 182 / 0 / 0 / 0 / 367 / 190 / 177 / 929
38 / Lakrakol / 76 / 38 / 38 / 0 / 0 / 0 / 76 / 38 / 38 / 1000
39 / Mahisol / 342 / 168 / 174 / 0 / 0 / 0 / 342 / 168 / 174 / 1036
40 / Majhauna / 131 / 63 / 68 / 0 / 0 / 0 / 21 / 12 / 9 / 1079
41 / Mangra / 539 / 264 / 275 / 1 / 1 / 0 / 538 / 263 / 275 / 1042
42 / Marichak / 784 / 410 / 374 / 0 / 0 / 0 / 193 / 103 / 90 / 912
43 / Matia / 722 / 359 / 363 / 0 / 0 / 0 / 378 / 186 / 192 / 1011
44 / Matia Bedo / 100 / 44 / 56 / 0 / 0 / 0 / 100 / 44 / 56 / 1273
45 / Pandriya / 313 / 157 / 156 / 0 / 0 / 0 / 309 / 154 / 155 / 994
46 / Pathara / 1377 / 706 / 671 / 19 / 8 / 11 / 909 / 458 / 451 / 950
47 / Patharghata / 575 / 290 / 285 / 29 / 16 / 13 / 538 / 269 / 269 / 983
48 / Patlohara / 690 / 351 / 339 / 35 / 15 / 20 / 366 / 181 / 185 / 966
49 / Rampur Bansjori / 477 / 242 / 235 / 0 / 0 / 0 / 477 / 242 / 235 / 971
50 / Ranchaura / 701 / 340 / 361 / 22 / 8 / 14 / 679 / 332 / 347 / 1062
51 / Sabaiya / 368 / 185 / 183 / 0 / 0 / 0 / 368 / 185 / 183 / 989
52 / Simra / 109 / 49 / 60 / 0 / 0 / 0 / 109 / 49 / 60 / 1224
53 / Telabani khaplo / 166 / 80 / 86 / 0 / 0 / 0 / 164 / 78 / 86 / 1075
54 / Telo / 1968 / 994 / 974 / 39 / 20 / 19 / 1063 / 526 / 537 / 980
55 / Tetuliya / 133 / 69 / 64 / 1 / 1 / 0 / 132 / 68 / 64 / 928
56 / Turua / 272 / 137 / 135 / 14 / 8 / 6 / 248 / 123 / 125 / 985

Data Source: JharkhandSpaceApplicationCenter (JSAC), Dept. of IT., Govt. of Jharkhand