GENERAL REQUIREMENTSCONSTRUCTION PROGRESS DOCUMENTATION

Section 01320 - 4

Page 1 of__

Section 01320 - 4

Construction Progress Documentation

Cost-Loaded CPM

PART 1 -GENERAL

1.01summary

.AThis Section includes:

.1Part 1 – General

.a1.01 – Summary

.b1.02 – Related Documents And Sections

.c1.03 - Definitions

.2Part 2 – Products

.a2.01 - Scheduling Software

.3Part 3 – Execution

.a3.01 - CPM Progress Schedule

.b3.02- Schedule Orientation Meeting

.c3.03 - Preliminary Contract Schedule

.d3.04 - Baseline Schedule

.e3.05 - Official Progress Schedule

.f3.06 - Monthly Update of Official Progress Schedule

.g3.07 - Revised Official Progress Schedule

.h3.08 - Short Interval Schedule

.i3.09 - Recovery Schedule

.j3.10 - Cost Breakdown

.k3.11 - Time Extensions

.l3.12 - Submittal Logs

.m3.13 - Project Reports

.4Part 4 – Forms (Not Used)

1.02RELATED DOCUMENTS and sections

.ADocument 00100, Notice to Bidders

.BDocument 00700.3.24, “Official Progress Schedule”

.CDocument 00700.7.6, “Delay and Time Extension”

.DDocument 00700.8.2, “Progress Payments”

.EDocument 00700.13.6, “Recommendation for Acceptance”

.FDivision1 Section 01290, “Payment Procedures”

.GDivision 1 Section 01290.1.04, “Cost Breakdown”

.HDivision1 Section 01310 "Project Management and Coordination"

.IDivision1 Section 01315 "Project Meetings"

.JDivision1 Section 01330 "Submittal Procedures"

.KSection 01810, "General Commissioning Requirements"

1.03DEFINITIONS

.ABaseline Schedule -The Contractor’s initial CPM Progress Schedule presenting an orderly and realistic plan for completion of the entire Work of the Project. When accepted by the Owner’s Project Manager, the Contractor’s Baseline Schedule becomes the initial version of the Official Progress Schedule. The Baseline Progress Schedule is prepared in chart or graph format, consistent in all respects with the Contract Time(s) and order of Work, presented in sufficient detail to show the chronological relationship of all activities of the Project including but not limited to planned starting and completion dates of various activities, submittal of Shop Drawings and Product Data, procurement of materials and equipment, and deliveries of materials and equipment.

.BCPM Progress Schedule – The Contractor’s Progress Schedule prepared in CPM Precedence format using the scheduling software required by Section 01320.2.01, “Scheduling Software.”

.CCritical Path -The set or sequence of predecessor/successor activities which will take the longest time to complete. The duration of the critical path is the sum of the activities' durations along the path. Thus, the critical path can be defined as the longest possible path through the "network" of project activities. The duration of the critical path represents the minimum time required to complete a project. Any delays along the critical path would imply that additional time would be required to complete the project.

.DFloat – The number of work/calendar days an activity can be delayed without impacting the project completion date. The Project “owns” float.

.EOfficial Progress Schedule - The Contractor’s Progress Schedule and all revisions and updates thereto, accepted by the Owner, in accordance with the requirements of the Contract Documents.

.FPreliminary Contract Schedule - The Contractor’s CPM Progress Schedule presenting its detailed sequence of early operations including procurement of materials and equipment for a minimum of ninety (90) Days from the official Contract start date stated in the Notice to Proceed. The Preliminary Contract Schedule must also present all Milestones, sequences, and activities occurring during the entire Contract Time that are specifically required by the Contract Documents to be shown on the Contractor’s Preliminary Contract Schedule.

.GRecovery Schedule – Contractor’s detailed schedule indicating how Contractor intends to recover lost time.

.HRevised Official Progress Schedule –Contractor’s written request to revise the current version of the Official Progress Schedule. If the Owner accepts the Contractor’s request to revise the Official Progress Schedule, it becomes the new current version of the Official Progress Schedule.

.IShort Interval Schedule - The Contractor’s fourweek schedule showing the past week, the week submitted, and two weeks thereafter. The Short Interval Schedule must correlate with the current version of the Official Progress Schedule and reference the appropriate activity numbers. The Short Interval Schedule must indicate the actual start and finish dates of all activities on the Official Progress Schedule that are started or finished during the time period encompassed by the Short Interval Schedule.

.JUpdated Official Progress Schedule – The current version of the Official Progress Schedule updated to include the actual start and finish dates of activities and the percentage of completion of each activity. Actual start and finish dates must be identical to the actual start and finish dates indicated on the Contractor’s Short Interval Schedule submissions.

.KNetwork Window – Also know as “fragnets” or “hammocks”, Network Windows must be provided as needed to 'explode' a section of the Official Progress Schedule to show the effects of proposed changes or delays to the schedule.

PART 2 -PRODUCTS

2.01SCHEDULING SOFTWARE

.AContractor must use the most current version of Primavera project planning software to produce the CPM Progress Schedule. All CPM Progress Schedules must be produced using the Precedence Diagramming Method (PDM).

PART 3 -EXECUTION

3.01CPM PROGRESS SCHEDULE

.AGeneral Requirements

.1Personnel preparing CPM Progress Schedules must be qualified and experienced in using Primavera Project Planner software toprepare Critical Path Method ("CPM") schedules and must be capable of producing the schedules and reports required by this Section. Within seven (7) Days after the official Contract start date stated in the Noticeto Proceed, Contractor must submit for Owner acceptance, four (4) copies of the qualifications of Contractor’s proposed scheduler including references from the owner on the last three (3) recent projects where the proposed scheduler prepared the required project schedules.

.2Contractor must use scheduling software as required by Section 01320.2.01, “Scheduling Software.”

.3Contractor must provide Owner with four (4) copies (plots) of each schedule submission and electronic copies of the schedule data files on Compact Disks (CDs). The CDs must be permanently labeled to indicate the contents of the CD and include the submittal number and data date.

.4The Project Time for completion of the entire Project and the Milestone times must adhere to the start and finish times stated in the Contract Documents, unless Contractor formally requests and Owner’s Authorized Representative Approves in writing earlier (advanced) time(s) of completion. Approval of such request shall be at Owner's discretion and must be in the form of a Change Order.

.5Float Time is not for the exclusive benefit of either Contractor or Owner. Contractor must not include contingency activities.

.6Failure of the Official Progress Schedule to include an element of the Work required for performance of this Contract, or inaccuracy in Official Progress Schedule, will not relieve Contractor from responsibility for accomplishing all the Work required and will not constitute grounds for delay.

.7Failure of Contractor to substantially comply with requirements of this Section 01320 will constitute a failure by Contractor to prosecute Work with such diligence as will ensure its completion within Contract Time(s) and may be considered grounds for termination or other remedy by Owner pursuant to terms of this Contract.

3.02Schedule Orientation Meeting

.AWithin fourteen (14) Days of the official Contract start date stated in the Notice to Proceed, Owner’s Project Manager will conduct a Schedule Orientation Meeting to review the requirements of the Contract Documents for preparing, submitting, updating, and revising the various Project schedules. This is a separate meeting from the Preconstruction Conference and is dedicated exclusively to discussions about the scheduling requirements for the Project.

.BContractor must review the requirements of the Contract Documents related to scheduling prior to the meeting and be prepared to discuss its general approach to meeting the requirements. This meeting must be attended by:

.1Owner’s Project Manager or designee.

.2Contractor's Authorized Representative and scheduler.

.3Contractor’s QC Manager (See Section 01450.1.08.A.

.4Representatives from Subcontractors

.5Any other personnel deem advisable to attend by Owner or Contractor.

.CThe following items will be reviewed and discussed during the meeting:

.1Qualifications of Contractor’s scheduler

.2Schedule preparation and submission requirements

.3Level of involvement of Subcontractors in the schedule development effort

.4Resource loading

.5Schedule updates.

.6Schedule revisions.

.7Recovery Schedules

.8Short Interval Schedules (SIS)

.9Cost Breakdown and activity cost loading

.10Definable Features of Work (DFOW)

.11Payment for Mobilization

.12Establishing the time element of Change Orders.

.13Monthly Earnings Forecast

.14Interface Flags

.15CountyHolidays and Hours of Work

.16Technical Scheduling Requirements

.17Data exchange and communication.

3.03Preliminary Contract Schedule

.ANo later than twenty-one (21) Days after the start date for the Work stated in the Notice to Proceed, Contractor must submit five (5) prints (plots) of a Preliminary Contract Schedule.

.BThe Preliminary Contract Schedule must be a timescale, cost and resource loaded, precedence CPM diagram. The data/status date for the Preliminary Contract Schedule must be the first day of the Contract Time as stated in the NTP.

.CThe Preliminary Contract Schedule must include:

.1The Contractor’s general plan of Work in accordance with the Milestones and Project Time(s) stated in the Contract Documents.

.2Details of Contractor's planned mobilization.

.3Sequence of early operations including procurement of materials and equipment for a minimum of ninety (90) Days from the official Contract start date stated in the Notice to Proceed.

.4All mandatory activities, sequences, and durations required in the Contract Documents including but not limited to:

.aA start Milestone for the Notice to Proceed (Section 01320.3.04.B.33)

.bAn activity for verification of all existing conditions and dimensions. (Section 01725.1.04.C)

.cAn activity for installation of temporary site enclosure fence. (Section 01535.1.04.A)

.dAll pre-construction submittals.

.DOwner’s Project Manager will review the Preliminary Contract Schedule for conformance with the requirements of the Contract Documents. Owner’s Project Manager will return the Preliminary Contract Schedule with comments within twenty-one (21) Days after receipt.

.EContractor must use the Owner accepted Preliminary Contract Schedule with Owner's comments as the basis for the Baseline Schedule submission. Unless otherwise requested by the Contractor and approved in writing by the Owner’s Project Manager, the activities, durations, and logic that appear in the Owner accepted Preliminary Contract Schedule must remain unchanged in the Baseline Schedule submission.

3.04Baseline Schedule

.AWithin sixty (60) Days from the official Contract start date stated in the Notice to Proceed, Contractor must submit a Baseline Schedule presenting an orderly and realistic plan for completion of the entire Work of the Project including consideration of and compliance with all Milestones, activity sequencing, activity durations, and other scheduling restrictions imposed by the requirements of the Contract Documents. The Baseline Schedule submittal must include four (4) schedule prints (plots) and corresponding electronic data files on Compact Disks (CDs). The CDs must be permanently labeled to indicate the contents of the CD and include the submittal number and data date.

.BAll Listed sub-contractors must sign a copy of the Baseline Schedule and provide a letter transmittal indicating they have reviewed and accepted the Baseline Schedule.

.CThe Baseline Schedule submission must include and/or comply with the following minimum requirements:

.1Provide a time scaled, cost and resource loaded CPM schedule in precedence format, with the Critical Path highlighted. No more than 15% of activities can be critical or “near critical.” “Critical” is defined as having zero calendar days of Total Float, and “Near Critical” is defined as having 1-5 calendar days of Total Float.

.2Show the plan for completion of the Work for each Milestone within the time(s) specified. Each activity must be coded to its corresponding Milestone.

.3Provide a list identifying all imposed constraints (restraints). Activity constraints must be limited to constraints imposed by the Contract Documents unless otherwise specifically approved in writing by the Owner’s Project Manger.

.4Activity Calendars:

.aIndicate all activity calendars used.

.bAll activity calendar(s) must identify workdays, holidays, and shift work (by trade).

.cAll activity calendar(s) must include:

.1All work hour restrictions including but not limited to CEQA requirements, anticipated weather delays, and restriction imposed by local Governmental Agencies.

.2All workday activity calendars must have the same holidays unless approved in writing by the Project Manager.

.3All activity calendars must cover entire Contract Time.

.4The global seven-day/week activity calendar must have no non-work days.

.dEach Activity must be assigned to the appropriate Activity Calendar.

.5All completion Milestones required by the Contract Documents must be shown on the specific Milestone completion date(s) identified in the Contract Documents and must be attached to a seven-day/week activity calendar. The seven-day/week activity calendar must have no non-work days.

.6Include dependencies (relationships) and logic ties between activities.

.7Open-ended activities are not permitted.

.8Unless otherwise Approved in writing by Owner’s Project Manager, no single activity on the schedule shall have a duration longer than fifteen (15) workdays, except for fabrication, procurement, Punch List, and equipment commissioning (run-in) activities.

.9Schedules which show negative float will not be accepted by the Owner, nor will negative float be a basis for time extensions for Change Order activities, except for those activities shown on the Critical Path.

.10Float is owned by the Project. Float is administered by the Owner. No time extensions to the Contract time will be granted, nor delay damages paid, unless a delay occurs which impacts the Critical Path and consumes all available Float.

.11Activity durations shall be the total number of actual days required to perform each activity. The consideration of weather impact on completion of the Work must be included in the associated activity calendar and not included in individual activity durations.

.12No single activity shall have more than one Subcontractor responsible for its performance.

.13Each Activity will include (1) a description of what work is occurring, and where; (2) Calendar day duration; and (3) Responsibility code to identify who performs the activity.

.14For Subcontractor activities, include a responsibility code for each activity corresponding to the Subcontractor responsible for performing the Work.

.15The sum of the Subcontractor values of all activities performed by a Subcontractor must equal the Subcontract value of the Subcontract between the Contractor and the Subcontractor.

.16The cost (resource) loading of activities must be consistent with the Cost Breakdown provided under Section 01290.1.04, “Cost Breakdown.” Unless otherwise Approved by the Owner’s Project Manager, the Contractor must indicate cost resources by US dollars ($) for all cost resources. Contractor’s overhead (including general conditions costs), and profit must be proportionally prorated over all cost loaded activities as a fixed percentage of the value of the activity. Except as otherwise Directed or Approved by Owner, activities that are not directly associated with the cost of Workinplace, such as mobilization, temporary facilities, and Submittal preparation must not be cost loaded.

.17The sum of the values of all the activities in the Baseline Schedule must equal the total Contract Sum.

.18Include (resource load) manpower requirements, by prevailing wage classification, for each activity. Unless otherwise Approved by the Owner’s Project Manager, Contractor must indicate manpower resource requirements by man-days (MD) for all manpower resources.

.19Include (resource load) the major construction equipment required to perform each activity. Unless otherwise Approved by the Owner’s Project Manager, Contractor must indicate equipment resource requirements by equipment hours (EH) for each major piece of construction equipment.

.20Unless otherwise specifically Approved in writing by the Owner’s Project Manager, if the start of an activity depends on the Owners acceptance of a Submittal(s), identify as two (2) separate preceding activities the preparation and review of the Submittal(s).

.21Unless a longer period is specifically stated in the Contract Documents, Owner will have a minimum of 21 Days to review Complete Submittals. (See Section 01330.1.04, “Scheduling”)

.22Do not schedule activities that are dependent on Submittal acceptance or material delivery to start earlier than the expected approval or delivery dates.

.23Identify as separate activities procurement of major equipment and materials. At a minimum, procurement of major equipment and materials must include the following five (5) dependent activities:

.aPlace purchase order

.bPrepare Submittal

.cReview and accept Submittal

.dFabricate/Manufacture

.eDelivery

.24Identify as separate activities the installation of all Owner Furnished Contractor Installed Items. If Contractor requires product installation information for Owner Furnished Items, include specific interface flags indicating when product installation information is required.

.25If required, include activities for all equipment/systems Performance Period(s). Performance Period activities must occur after operational testing is completed and before Contractor certifies the Work of the Milestone is complete.

.26Include individual activities for the final cleanup effort associated with each Milestone and the final cleanup of the entire Project. Final cleanup activities must be shown occurring prior to Contractor’s Milestone and contract completion inspection requests.

.27Include activities for Contractor completion certification for each Milestone and Project Completion Certification.

.28Include activities and indicate the number of Days allowed (21 Days) for the Owner to prepare Punch lists.

.29Show the number of days needed by the Contractor to correct deficiencies in the completed Work (Punch List durations) after receipt of Punch list from Owner.

.30The duration for Contractor to correct Punch list items for each Milestone must not be less than twenty-one (21) Days. Contractor’s Punch list activities must be shown as starting no earlier than Contractor’s receipt of Owner prepared Punch List.

.31Include interface flags for all points of coordination with the work of other contractors engaged by Owner at the Project Site.

.32With the Baseline Schedule Submission, Contractor must submit a monthly earnings forecast indicating the Contractor’s estimated per month and cumulative-to-date billings to the Owner over the entire Contract Time. The report must include a cash flow envelope diagram, based on the Contractor’s cost loaded Baseline Schedule, showing the cumulative total cost for early start and late finish from the start of the Project to its completion. Submit four (4) paper copies and corresponding electronic data files on Compact Disks (CDs). The CDs must be permanently labeled to indicate the contents of the CD and include the submittal number and data date.