NEWS RELEASE
Date: March 5, 2013
District 7: Los Angeles & Ventura Counties
Contact: Public Affairs
Phone: (213) 897-3656
Online: www.dot.ca.gov/dist07
facebook.com/10605directconnector
twitter.com/10605DirectCon
caltransd7info.blogspot.com
FOR IMMEDIATE RELEASE
Freeway Connector Closures Scheduled for
I-10/I-605 Interchange Improvement Project
Baldwin Park – The California Department of Transportation (Caltrans) will close portions of the San Gabriel River Freeway (I-605) and San Bernardino Freeway (I-10) as part of the Interchange Improvement Project. The following schedule will be in effect, weather permitting.
Monday,March 10 through Thursday, March 13
- 7 p.m. to 6 a.m. – Two lanes of east- and westbound I-10 from I-605 to Frazier Street
- 7p.m. to 6 a.m. – Westbound I-10 Frazier Street, Baldwin Park Boulevard, Francisquito Avenue and Puente Avenue on-ramps
- 8 p.m. to 5 a.m. – Valley Boulevard on-ramp to northbound I-605
- 8 p.m. to 6 a.m. – Two lanes of north- and southbound I-605 from I-10 to West Ramona Boulevard
- 9 p.m. to 6 a.m. – Eastbound I-10 Garvey Avenue on-ramp
- 9 p.m. to 6 a.m. – Northbound I-605 connector to westbound I-10
- 9 p.m. to 5 a.m. – West Ramona Boulevard on-ramp to southbound I-605
- 9 p.m. to 6 a.m. – Southbound I-605 connectors to east- and westbound I-10
- 10 p.m. to 6 a.m. – Westbound I-10 connector to north- and southbound I-605
- 10 p.m. to 5 a.m. – Eastbound I-10 connectors to north- and southbound I-605
- 10 p.m. to 6 a.m. – Eastbound I-10 Frazier Street off-ramp
- 11 p.m. to 5 a.m. – Northbound I-605 connector to eastbound I-10
- 11 p.m. to 4 a.m. – All lanes of westbound I-10 from Puente Avenue to I-605
- 12 a.m. to 4 a.m. – All lanes of southbound I-605 from West Ramona Boulevard to I-10
- 12 a.m. to 5 a.m. – All lanes of northbound I-605 from Valley Boulevard to I-10
Friday,March 14
•7 p.m. to 11 a.m. –Two lanes of east- and westbound I-10 from I-605 to Frazier Street
•7 p.m. to 10 a.m. –Westbound I-10 Frazier Street, Baldwin Park Boulevard, Francisquito Avenue and Puente Avenue on-ramps
•8 p.m. to 7 a.m. –Valley Boulevard on-ramp to northbound I-605
•8 p.m. to 10 a.m. –Two lanes of north- and southbound I-605 from I-10 to West Ramona Boulevard
•9 p.m. to 10 a.m. –Southbound I-605 connectors to east- and westbound I-10
•10 p.m. to 9 a.m. –Eastbound I-10 Garvey Avenue on-ramp
•10 p.m. to 8 a.m. –Northbound I-605 connector to westbound I-10
•10 p.m. to 9 a.m. –Westbound I-10 connector to north- and southbound I-605
•10 p.m. to 8 a.m. –Eastbound I-10 connectors to north- and southbound I-605
•10 p.m. to 10 a.m. –Eastbound I-10 Frazier Street off-ramp
•11 p.m. to 7 a.m. –West Ramona Boulevard on-ramp to southbound I-605
•12 p.m. to 6 a.m. –Northbound I-605 connector to eastbound I-10
•12 a.m. to 5 a.m. –All lanes of southbound I-605 from West Ramona Boulevard to I-10
•1 a.m. to 5 a.m. –All lanes of westbound I-10 from Puente Avenue to I-605
•1 a.m. to 6 a.m. –All lanes of northbound I-605 from Valley Boulevard to I-10
•3 a.m. to 6 a.m. –All lanes of eastbound I-10 from I-605 to Baldwin Park Boulevard
•
MCM Construction, Inc. is the contractor for this $66 million Design Build project, which will create a flyover bridge from the southbound San Gabriel River Freeway (I-605) to the eastbound San Bernardino Freeway (I-10). Detour signs will be posted to direct motorists. Anticipated completion is fall, 2015. Caltrans reminds you to Slow For the Cone Zone.