State of California • Department of Transportation

NEWS RELEASE

Date: March 5, 2013

District 7: Los Angeles & Ventura Counties

Contact: Public Affairs

Phone: (213) 897-3656

Online: www.dot.ca.gov/dist07

facebook.com/10605directconnector

twitter.com/10605DirectCon

caltransd7info.blogspot.com

FOR IMMEDIATE RELEASE

Freeway Connector Closures Scheduled for

I-10/I-605 Interchange Improvement Project

Baldwin Park – The California Department of Transportation (Caltrans) will close portions of the San Gabriel River Freeway (I-605) and San Bernardino Freeway (I-10) as part of the Interchange Improvement Project. The following schedule will be in effect, weather permitting.

Monday,March 10 through Thursday, March 13

  • 7 p.m. to 6 a.m. – Two lanes of east- and westbound I-10 from I-605 to Frazier Street
  • 7p.m. to 6 a.m. – Westbound I-10 Frazier Street, Baldwin Park Boulevard, Francisquito Avenue and Puente Avenue on-ramps
  • 8 p.m. to 5 a.m. – Valley Boulevard on-ramp to northbound I-605
  • 8 p.m. to 6 a.m. – Two lanes of north- and southbound I-605 from I-10 to West Ramona Boulevard
  • 9 p.m. to 6 a.m. – Eastbound I-10 Garvey Avenue on-ramp
  • 9 p.m. to 6 a.m. – Northbound I-605 connector to westbound I-10
  • 9 p.m. to 5 a.m. – West Ramona Boulevard on-ramp to southbound I-605
  • 9 p.m. to 6 a.m. – Southbound I-605 connectors to east- and westbound I-10
  • 10 p.m. to 6 a.m. – Westbound I-10 connector to north- and southbound I-605
  • 10 p.m. to 5 a.m. – Eastbound I-10 connectors to north- and southbound I-605
  • 10 p.m. to 6 a.m. – Eastbound I-10 Frazier Street off-ramp
  • 11 p.m. to 5 a.m. – Northbound I-605 connector to eastbound I-10
  • 11 p.m. to 4 a.m. – All lanes of westbound I-10 from Puente Avenue to I-605
  • 12 a.m. to 4 a.m. – All lanes of southbound I-605 from West Ramona Boulevard to I-10
  • 12 a.m. to 5 a.m. – All lanes of northbound I-605 from Valley Boulevard to I-10

Friday,March 14

•7 p.m. to 11 a.m. –Two lanes of east- and westbound I-10 from I-605 to Frazier Street

•7 p.m. to 10 a.m. –Westbound I-10 Frazier Street, Baldwin Park Boulevard, Francisquito Avenue and Puente Avenue on-ramps

•8 p.m. to 7 a.m. –Valley Boulevard on-ramp to northbound I-605

•8 p.m. to 10 a.m. –Two lanes of north- and southbound I-605 from I-10 to West Ramona Boulevard

•9 p.m. to 10 a.m. –Southbound I-605 connectors to east- and westbound I-10

•10 p.m. to 9 a.m. –Eastbound I-10 Garvey Avenue on-ramp

•10 p.m. to 8 a.m. –Northbound I-605 connector to westbound I-10

•10 p.m. to 9 a.m. –Westbound I-10 connector to north- and southbound I-605

•10 p.m. to 8 a.m. –Eastbound I-10 connectors to north- and southbound I-605

•10 p.m. to 10 a.m. –Eastbound I-10 Frazier Street off-ramp

•11 p.m. to 7 a.m. –West Ramona Boulevard on-ramp to southbound I-605

•12 p.m. to 6 a.m. –Northbound I-605 connector to eastbound I-10

•12 a.m. to 5 a.m. –All lanes of southbound I-605 from West Ramona Boulevard to I-10

•1 a.m. to 5 a.m. –All lanes of westbound I-10 from Puente Avenue to I-605

•1 a.m. to 6 a.m. –All lanes of northbound I-605 from Valley Boulevard to I-10

•3 a.m. to 6 a.m. –All lanes of eastbound I-10 from I-605 to Baldwin Park Boulevard

MCM Construction, Inc. is the contractor for this $66 million Design Build project, which will create a flyover bridge from the southbound San Gabriel River Freeway (I-605) to the eastbound San Bernardino Freeway (I-10). Detour signs will be posted to direct motorists. Anticipated completion is fall, 2015. Caltrans reminds you to Slow For the Cone Zone.