CONSTRUCTION MANAGEMENT PROJECT UPDATE

September 26, 2015 – October 9, 2015

  1. Tennesse/Reading Road Rehabilitation

Engineer/Inspector: Lisa Rowell/Bob Backscheider

Contractor: Prus Construction

Project Description:

The project includes widening Reading Road from Joseph Street to the Norwood Lateral. It will provide new curb and sidewalk as well as new signals at Berkley Avenue and Reading Road. The project also includes constructing new roadway into the proposed Mercy Health Place. Tennessee Avenue will receive new asphalt pavement and concrete curbs in the area between the corps lines between Norwood and St. Bernard.

Project Completion:

January 2016

Community:

Bond Hill

ScheduledActivities for 9/26/2015 – 10/9/2015

  • Excavate driveway at Mercy Health
  • Conduit installation
  • Full depth repairs on Reading Road and Tennessee Avenue

Maintenance of Trafficupdate for 9/26/2015 – 10/9/2015

  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic.

2. 2015 Street Rehab CIP #2

Engineer/Inspector: Lisa Rowell/Emily Hunley/Brian Hurd

Contractor: John R. Jurgensen

Project Description:

This project includes planning the existing asphalt course as necessary; performing partial and full-depth pavement repairs; placing an intermediate course of asphalt where necessary; repairing deteriorated curbs; constructing curb ramps, concrete walk and driveway aprons where necessary; performing inlet adjustments; adjusting utility castings to grade; resurfacing the entire pavement with asphaltic concrete; performing the necessary pavements marking work; removing and replacing traffic signage; and replacing traffic loop detectors where applicable.

Project Completion Date:

November 2015

Community:

Clifton, Northside, Spring Grove Village

ScheduledActivities for 9/26/2015 – 10/9/2015

  • Begin surface course asphalt on Phase I
  • Full depth repairs on Phase II
  • Begin milling streets in Pasee II

Maintenance of Traffic for 9/26/2015 – 10/9/2015

  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic.

3. HAM-Lunken Trail Rehabilitation

Engineer/Inspector: Mike Mann/Tony Baker/Frank Mertz

Contractor: Prus Construction

Project Description:

Replacing the deteriorated trail; rebuilding all trailside driveways and driveway aprons,

Relocating part of the trail in order to provide buffer space; correcting trailside drainage issues, installing curb and performing pot hole repairs.

Project Completion Date:

October 2015

Community:

East End

ScheduledActivities for 9/26/2015 – 10/9/2015

  • Completing full depth base repairs
  • Milling and paving Wilmer Avenue
  • Punchlist items

Maintenance of Traffic 9/26/2015 – 10/9/2015

  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic.

4. 2015 Street Rehab CIP #1

Engineer/Inspector: Mike Mann/Douglas Dornette/Dennis Honerkamp

Contractor: Adleta, Inc.

Project Description:

This project includes planning the existing asphalt course as necessary; performing partial and full-depth pavement repairs; placing an intermediate course of asphalt where necessary; repairing deteriorated curbs; constructing curb ramps, concrete walk and driveway aprons where necessary; performing inlet adjustments; adjusting utility casting to grade; resurfacing the entire pavement with asphaltic concrete; performing the necessary pavements marking work; removing and replacing traffic signage; and replacing traffic loop detectors where applicable.

Project Completion Date:

October 2015

Community:

Bond Hill, Roselawn

Scheduled Activities for 9/26/2015 – 10/9/2015

  • Punchlist items

Maintenance of Traffic for 9/26/2015 – 10/9/2015

  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic.

5.Walnut Hills NBD Streetscape: E. McMillan Street – Phase I

Engineer/Inspector: Don Stiens/Tony Perkins

Contractor: Bansal Construction Inc.

Project Description:

This project includes performing a streetscape on East McMillan Street from Kemper

Lane to Victory Parkway.

Project Completion Date:

August 2015

Community:

Walnut Hills

Scheduled Activities for 9/26/2015 – 10/9/2015

  • Replacing curb
  • Replacing sidewalk
  • Continue installing lighting conduit
  • Continue installing light pole foundations

Maintenance of Traffic for 9/26/2015 – 10/9/2015

  • Traffic will be reduced to one lane in the westbound direction
  • Two lanes will be open and available in the eastbound direction
  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours, the streets shall be open and available for the movement of traffic.

6. 2015 Street Rehab CIP #6

Engineer/Inspector: Mike Mann/Dennis Honerkamp

Contractor: Prus Construction Company

Project Description:

This project included planning the existing asphalt course as necessary; performing partial and full-depth pavement repairs; placing an intermediate course of asphalt where necessary; repairing deteriorated curbs; constructing curb ramps, concrete walk and driveway aprons where necessary; performing inlet adjustment; adjusting utility casting to grade; resurfacing the entire pavement with asphaltic concrete; performing the necessary pavements marking work; removing and replacing traffic signage; and replacing traffic loop detectors where applicable.

Project Completion Date:

December 2015

Community:

West Price Hill

Scheduled Activities for 9/26/2015 – 10/9/2015

  • Curb replacement work
  • Milling and placing the asphalt intermediate course on Phase II streets

Maintenance of Traffic for 9/26/2015 – 10/9/2015

  • Access for emergency vehicle, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic.

7. 2015 Street Rehab CIP #4

Engineer/Inspector: Mike Mann/Frank Mertz

Contractor: John R. Jurgensen

Project Description:

This project includes planning the existing asphalt course as necessary; performing partial and full-depth pavement repairs; placing an intermediate course of asphalt where necessary; repairing deteriorated curbs; constructing curb ramps, concrete walk and driveway aprons where necessary; performing inlet adjustment; adjusting utility casting to grade; resurfacing the entire pavement with asphaltic concrete; performing the necessary pavements marking work; removing and replacing traffic signage; and replacing traffic loop detectors where applicable.

Project Completion Date:

December 2015

Community:

Columbia Tusculum, Mt. Lookout, Mt. Washington

Scheduled Activities for 9/26/2015 – 10/9/2015:

  • Full depth base repairs on Phase II streets
  • Concrete work on Phase I streets

Maintenance of Traffic for 9/26/2015 – 10/9/2015:

  • Access for emergency vehicle, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic.

8. 2015 Street Rehab CIP #7

Engineer/Inspector: Mike Mann/Tony Baker

Contractor: Adleta, Inc.

Project Description:

This project includes planning the existing asphalt course as necessary; performing partial and full-depth pavement repairs; placing an intermediate course of asphalt where necessary; repairing deteriorated curbs; constructing curb ramps, concrete walk and driveway aprons where necessary; performing inlet adjustment; adjusting utility casting to grade; resurfacing the entire pavement with asphaltic concrete; performing the necessary pavements marking work; removing and replacing traffic signage; and replacing traffic loop detectors where applicable.

Project Completion Date:

November 2015

Community:

East Price Hill, Lower Price Hill

Scheduled Activities for 9/26/2015 – 10/9/2015:

  • Asphalt milling and leveling on the Upper Price Hill Streets
  • Begin concrete work after intermediate course asphalt

Maintenance of Traffic for 9/26/2015 – 10/9/2015:

  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic.

9. Clinton Springs & Mitchell Avenue Rehabilitation

Engineer/Inspector: Don Steins/Kevin Feldkamp

Contractor: Prus Construction

Project Description:

This project involves the rehab of Clinton Springs from Dana Avenue to Vine

Street, Dana from near Reading Road, and Mitchell Avenue from Clinton Springs to Red Bud. The project also includes reconfiguring the intersection of Clinton

Springs and Dana, retaining wall work and new traffic signals.

Project Completion Date:

November 2015

Community:

Avondale

Scheduled Activities for 9/26/2015 – 10/9/2015:

  • Full-depth repairs
  • Milling and leveling

Maintenance of Traffic for 9/26/2015 – 10/9/2015:

  • On Clinton Springs Avenue from 6am – 9am and from 4pm – 6pm Monday through Friday and during non-working hours, all lanes will be open and available to traffic.
  • On Mitchell Avenue from 6am – 9am Monday through Friday and during non-working hours all lanes will be open and available to traffic.
  • During all other working hours, at least two lanes will be open and available to traffic (one lane in each direction), except on Clinton Springs Avenue between Dana Avenue and Reading Road, which may be closed.
  • In general during all non-working hours, the streets shall be open and available for the movement of traffic.
  • Access for emergency vehicles, businesses and residents shall be maintained at all times.

10.Northside Arterial Improvement

Engineer/Inspector: Lisa Rowell/David Padur

Contractor: Prus Construction

Project Description:

This project includes planning the existing asphalt course as necessary;

performing partial and full-depth pavement repairs; placing an intermediate

course of asphalt where necessary; repairing deteriorated curbs; constructing

curb ramps, concrete walk and driveway aprons where necessary; performing

inlet adjustment; adjusting utility casting to grade; resurfacing the entire

pavement with asphaltic concrete; performing the necessary pavements

marking work; removing and replacing traffic signage; and replacing traffic

loop detectors where applicable.

Project Completion Date:

September 2016

Community:

Northside

Scheduled Activities for 9/26/2015 – 10/9/2015:

  • Electrical work installing cable and pull boxes

Maintenance of Traffic for 9/26/2015 – 10/9/2015:

  • Access for emergency vehicles, residents and businesses will be maintained at all times
  • During all non-working hours the streets shall be open and available for the movement of traffic.

11.2015 City Bridge Maintenance

Engineer/Inspector: Don Stiens/Kevin Feldkamp

Contractor: Sunesis Construction

Project Description:

This project includes expansion joint work, steel painting, overlay replacement,

waterproofing and deck sealing of various city bridges in different communities

around the city.

Project Completion Date:

November 2015

Community:

Camp Washington, CBD Riverfront, Clifton, Evanston, Millvale, South Cumminsville,

Spring Grove Village, Walnut Hills

Scheduled Activities for 9/26/2015 – 10/9/2015:

  • Replacing expansion joints at the 2nd Street intersections of Rosa Parks Street and Walnut Street

Maintenance of Traffic for 9/26/2015 – 10/9/2015:

  • During the replacement Rosa Parks Street will be closed between 2nd Street and Freedom Way for two days.
  • Walnut Street will be reduced to one lane in each direction between 2nd Street and Freedom Way for two days.