Bid Scope of Work
General Conditions
- Click List canopy is shown as new on Fixture Plan. The above ground canopy will be handled by others .
- Repair all affected finishes to like new conditions.
- Paint newly installed / exposed conduit, refrigeration lines, and uni-strut on sales floor to match adjacent finishes.
- Any trenching and saw-cutting work is to be done during off-peak hours (after 9pm and off sales floor before 8am).
- Contractor to receive all deliveries related to the project.
- Contractor must email weekly updates and photos of areas as they pertain to the project. This must be completed every Wednesday before noon or as requested by project manager.
- Review all documents included in the bid documents before submitting your bid – including the existing store fixture plan, the proposed store fixture plan.
Final Fixture Plan Dated 10/5/2015
New R1-R2Dated6/19/2014
L-733 REQ document.
L-733 XF1
Architectural Drawings as they pertain to Cheese and Sushi Island.
733 Produce Lighting plan.
Refrigeration Systems
- Kroger will perform refrigeration work.
- GC will receive and set up coolers per plan.
- GC responsibility to do complete installation of the RTU.
Kroger Supplied Items
- Refrigerated walk in cooler/freezer.
- Non-Refrigerated Display Cases, shelves and racking.
- Case Protectors
- Light fixtures
- Millwork
- RTU & curb
- Labor for low voltage
- All doors, including entrance doors, cooler doors, hollow metal and sales floor door.
- Vinyl wallcovering
- Carpet
- Lighting contactor
Contractor Supplied Items
- Building – Electrical and Plumbing permits as required by local agencies.
- Labor for receiving and installing fixtures.
- Paint, drywall and finishing materials.
- Millwork installation labor
- Miscellaneous metals for case to wall enclosures and rat runs.
- Electrical components, wiring, conduit, etc.
- Bollards
- Roof penetration and flashing
- Labor to install all doors with exception to entrance door. Finished door opening GC responsibility.
- Labor to install all fixtures shown new on fixture plan.
- Acoustical ceiling tiles and grid.
- All building materials including but not limited to, meat studs, drywall, plywood, steel, concrete, asphalt, fencing above coolers and steel ladder.
- Salvage existing brick for infill areas demo.
- Any additional duct per plans.
- Prefabricated exterior rod hung canopy and downspout
General
Miscellaneous Items:
Electrical
- Refer to REQ (Excel Document) Documents, Electrical Tab.
- Lights must be on night set back panel / circuits.
- Install new case monitoring cables as required.Cable is a Belden Multi conductor cable, rating non plenum, Conductor size 18 Awg Number of pairs or cond. 2ea. Mfr “Part # YN55390 U1000. Kroger Tech will terminate cables
- Abandoned circuits must be removed to first junction box or panel.
- Correct panel schedule.
- Kroger Tech will terminate cables for low voltage, POS, phones
- All electrical, refrigeration and plumbing drop locations must be approved by Kroger PM prior to final connection.
- Lighting must be on night set back panel / circuits
Floor Repair (P.M.)
- Match surrounding slabs elevations.
- Concrete patches must be finished to a hard steel slick finish. Floor leveling compound is not allowed.
- Saw cutting – angled cuts are not allowed. Only parallel or perpendicular cuts with column lines are allowed.
- Abandoned hub drains and any mechanicals must be capped eight inches below finish floor elevation.
- Refer to slab cutting /removal. See saw cut detail.
Plumbing (PM)
- Refer to REQ (Excel Document) Documents, plumbing Tab.
- Refer to Architectural plans for wall framing and materials.
Week: 1 (November 1)
- Work can be scheduled during the daylight hours but minimize disruption to store.
- Contractor will receive and install Kroger supplied equipment as per plan.
- Demo of exterior parking
- Start electrical rough in
- Canopy foundations, complete early and give Kroger PM completion date so canopy install can be scheduled three weeks before opening
- Cut in new entrance door and complete
- When excavating for communications/electric to canopy follow the crosswalk for pedestrians so underground will be camouflagedunder walkway
Week: 2 (November 8)
- Work will be scheduled at night in order to minimize disruption to store.
- Contractor will receive and install Kroger supplied equipment as per plan.
- Demo interior per plans
- Start tying in lighting
- Kroger to move U scans Kroger will coordinate low voltage requirements & CCTV for scales and POS.
- Partition work area from general public shopping area.
- Start metal stud partition walls
- Partition existing office and keep operational.
- Rework HVAC per plans
Week: 3 (November 15)
- Work will be scheduled at night in order to minimize disruption to store.
- Set cooler and freezer boxes
- Complete lighting
- Set up racking
- Décor on sales floor side
- Hang sales floor door
- Set up shelving along outside wall on sales floor side per Fixture plan
Week: 4 (November 22)
- Work will be scheduled at night in order to minimize disruption to store.
- Complete finishes inside and out
- Finalize all work this week in preparation for punch list to be compiled next week.
Week 5 (November 29)
Punch-list
1. November 30 punch-list compiled
2. Dec.1 –Dec. 3 complete punch-list items
Kroger L766 Click list