PREFUNCTIONAL TEST CHECKLIST
Condenser Water System Pre-Operational Flushing and Treatment Procedure
PIPE - ______
Specification Section ______
Project: ______Project No: ______
1. Preparation
a. All special treatment equipment listed in the specifications is installed: N/A / Yes / No
b. Potable water source to fill, dump and flush all piping/associated equipment is connected per drawings/specifications: Yes / No
c. System has been filled with potable water and re-circulated through all piping (cooling tower fan is off): Yes / No
d. System has been dumped and flushed, at the lowest point, until all loose matter has been removed and water is clear for a minimum of 24 hours: Yes / No
e. Interior of pipe has been inspected and/or video taped: Yes / No
f. System has been re-filled with potable water, with air bled from highest points and/or potential air pocket zones: Yes / No
2. Pre-operational Chemicals/Cleaner
a. Project Manager and MDAD water treatment company notified for testing of system (minimum 7 day notice is required): Yes / No
b. System has been placed in normal tower recirculation/operation (tower fans are off): Yes / No
c. System pH has been adjusted to 6.5 – 7.0 (near neutral): Yes / No
d. Stainless Steel Systems
i. Chlorides test results are under 1,000 ppm: Yes / No
ii. Water temperature does not to exceed 90 F – 120 F: Yes / No
e. Galvanized Systems
i. Betzdearborn (or applicable water treatment company) guidelines have been implemented to prevent white rust: Yes / No
ii. 100 ppm of Betzdearborn (or applicable water treatment company) Flogard MS6201 preoperational cleaner (iron & suspended solid dispersant), or PY505 Polymer at 50 ppm, has been added: Yes / No
iii. 5 ppm of Betzdearborn (or applicable water treatment company) AF724 (antifoam) has been added: Yes / No
iv. 40 ppm of Betzdearborn (or applicable water treatment company) Depositrol SF5101 (oil and slime dispersant) has been added: Yes / No
v. 50 ppm of Betzdearborn (or applicable water treatment company) AZ604 (copper corrosion inhibitor) has been added: Yes / No
vi. System has been re-circulated for 12 hours maximum (or 16 – 24 hrs recirculation, if PY505 Polymer is used): Yes / No
f. Non-Galvanized Systems
i. 600 ppm of Betzdearborn (or applicable water treatment company) Flogard MS6201 preoperational cleaner (iron & suspended solid dispersant), has been added: Yes / No
ii. 5 ppm of Betzdearborn (or applicable water treatment company) AF724 (antifoam) has been added: Yes / No
iii. 40 ppm of Betzdearborn (or applicable water treatment company) Depositrol SF5101 (oil and slime dispersant) has been added: Yes / No
iv. 50 ppm of Betzdearborn (or applicable water treatment company) AZ604 (copper corrosion inhibitor) has been added: Yes / No
v. System has been re-circulated for 12 – 48 hours: Yes / No
3. Recirculation and Pre-operational Treatment
a. System has been tested for total iron and pH per Table 1, with results recorded: Yes / No
b. Treatment has been adjusted to meet Table 1 limits: N/A / Yes / No
Table 1
CONTROL LIMITS FOR MS6201 PRE-OPERATIONAL CLEANERLOWER LIMITS
/ UPPER LIMITSFIELD TESTS / DATE / DATE / DATE / VALUE / ACTION / VALUE / ACTION
TOTAL IRON / 0.0 / -- / 10,000 PPM / Dump & re-apply chemicals
PH / 6.5 / -- / 7.0 / Add more H2SO4 of HCl until pH = 6.7
Zinc (if Galvainized) / 0 ppm / -- / 1 ppm / Dump, flush and use PY505
4. Pre-operational Testing
a. After pre-operational treatment parameters have been met (Table 1), system has been dumped and flushed (at its lowest point) until the water is clear (minimum of 24 hours): Yes / No
b. Field test parameters have been met and recorded in Table 2: Yes / No
Table 2
TARGET FIELD VALUES OF FINAL PREOPERATIONAL FLUSHCW LOWER LIMITS
/ CW UPPER LIMITSFIELD TESTS / MAKEUP /
CW
Effluent / CW Pass (Y/N) / FORMULA / RESULT / FORMULA / RESULTCONDUCTIVITY / Makeup x 90% / umhos / Makeup x 110% / Umhos
TOTAL IRON / 0 PPM / Makeup x 150% / PPM
PH / Makeup x 97.5% / units / Makeup x 102.5% / Units
TURBIDITY / -- / 0 FTU / Makeup x 110% / FTU
COLOR / CLEAR / CLEAR
c. Lab test parameters have been met and recorded in Table 3: Yes / No
Table 3
TARGET LAB VALUES OF FINAL PREOPERATIONAL FLUSHCW LOWER LIMITS / CW UPPER LIMITS
LAB TESTS
/ MAKEUP / CWEffluent / CW Pass (Y/N) / TARGET / TOLERANCE LIMITS / TARGET / TOLERANCE LIMITS
Freon extractables (O&G) / <1.0 PPM / 0 PPM / 1.0 PPM / 2.0 PPM
Total Iron / <0.1 PPM / 0 PPM / Makeup x 150% / 5.0 PPM
Conductivity / Makeup x 95% / 100 umhos / Makeup x 105% / 330 umhos
PH / Makeup x 95% / 7.0 units / Makeup x 105% / 9.5 units
Total Alkalinity / Makeup x 90% / 30 PPM / Makeup x 110% / 100 PPM
Calcium Hardness / Makeup x 90% / 30 PPM / Makeup x 110% / 120 PPM
Magnesium Hardness / Makeup x 90% / 5 PPM / Makeup x 110% / 30 PPM
Silica / Makeup x 90% / 0 PPM / Makeup x 110% / 20 PPM
Ryznar Saturation Index / 6.0 RSI
Langelier Saturation Index / (At 6-9 cycles) / +1.0 LSI / (At 6-9 cycles) / +3.0 LSI
d. System is ready for application of initial long term water treatment chemicals: Yes / No
Comments: