Jawaharlal Nehru National Urban Renewal Mission

IMPLEMENTATION OF

JAWAHARLAL NEHRU NATIONAL URBAN RENEWAL MISSION

IN FARIDABAD (HARYANA)

PROGRESS REPORT UPTO 30.09.2009

NATIONAL BUILDINGS CONSTRUCTION CORPORATION LTD.

(A GOVT. OF INDIA ENTERPRISES)

NBCC Bhavan, Lodhi Road, New Delhi – 110 003

BRIEF ABOUT PROJECT

PROJECT: URBAN INFRASTRUCTURE

DEVELOPMENT IN VARIOUS TOWNS OF HARYANA

SCOPE OF WORK:

n  FARIDABAD TOWN (UNDER MISSION-I)

n  OTHER TOWNS (UNDER UIDSSMT)

DATE OF AGGREMENT: 21-11-2006

NODAL AGENCY: HARYANA SLUM CLEARANCE BOARD HARYANA URBAN INFRASTRUCTURE DEVELOPMENT BOARD

URBAN LOCAL BODY: MUNICIPAL CORPORATION OF FARIDABAD

IMPLEMENTING AGENCY: NATIONAL BUILDINGS CONSTRUCTION CORPORATION LIMITED

As per actual allocated funds

by Planning Commission (2005-2012)

for Faridabad City

SCHEME / GOI Share
(Rs. In Crore) / Total Project Cost
(Rs. In Crore)
INFRASTRUCTURE WORKS / 352.25
( @ 50% ) / 704.50
BSUP / 32.31
( @ 50% ) / 64.62
TOTAL / 769.12

STATUS OF DPR’s

(Amount Rs. in Crore)

Sl. No / Name of Work / Amount as per Approved DPR / Date of Approval of DPR / Date of completion (as per DPR)
A) APPROVED DPR UNDER BSUP SCHEME
1 / Construction of 1968 DU’s at Dabua Colony, Faridabad / 38.96 / 28.11.2006 / 31.03.2009
2 / Construction of 1280 DU’s at Bapu Nagar, Faridabad / 25.27 / 28.11.2006 / 31.03.2009
Total / 64.23
B) APPROVED DPR UNDER NURM SCHEME
1 / Revamping/Relaying of Sewers in Old Faridabad Zone / 103.83 / 22.01.2007 / 31.03.2010
2 / Improvement of Drainage System in Old Faridabad Zone / 30.65 / 20.04.2007 / 3 years
3 / Integrated Solid Waste Management in Faridabad / 76.54 / 20.07.2007 / 2 ½ years
4 / Augmentation Water Supply in Faridabad / 493.49 / 14.01.2009 / 31.12.2011
Total / 704.50
Grand Total / 768.83

Ø C) DPR’s UNDER APPRAISAL / SUBMISSION

(Amount Rs. in Crore)

Sl. No / Name of Work / Amount as per DPR / Likely Date of Submission
1 / Revamping/Relaying of Sewerage in Ballabgarh Zone at Faridabad / 80.00 / Submitted
(Under Scrutiny by CPHEEO)
2 / Drainage Work – NIT Zone / 76.00 / Forwarded by MoUD to CPHEEO for the Appraisal
3 / Road Work – NIT Zone / 180.00 / Submitted (Appraised by CRRI under Hold)
4 / 2180 DU’s at Mirzapur/Lakarpur Faridabad / 65.00 / Submitted
(Under Hold)
5 / Road Work – Ballabgarh Zone / 80.00 / Submitted
(With HUIDB)
Total / 460.00

`

STATUS OF HOUSING WORKS UNDER BSUP SCHEME IN FARIDABAD

As on 30.09.2009

(All Amount in Rs. Lacs)

Pkg. No. / Brief Description of Work / Award Value / Date of / Status of Work
Start / Comp
Housing Work at Dabua Colony
I&II / Const. of 1968 DU’s including all Internal & External Works / 3667.88 / 01.07.07 / 31.10.09 / ·  Total 492 Du’s at one floor
GF / 1st / 2nd / 3rd / Roof / Total
Casting of RCC Floors for DU’s / 492 / 492 / 482 / 482 / 1948
Brick work for DU’s / 482 / 486 / 480 / 480 / 1928
Flooring for DU’s / 364 / 366 / 358 / 360 / 1448
Door Window Fixing for DU’s / 382 / 396 / 410 / 410 / 1598
·  Handed over of 202 DU’s to Slum dwellers.
·  810 DU’s are Ready for Handing over
·  Grit Wash – 1368 DU’s completed.
·  Boundary Wall 100% completed.
·  Pumping station No.1 Completed and In operation.
·  Sewer connection – 1290 DU’s completed.
·  Electric D-poles fixed- Sub-station completed.
Physical Progress 95%

STATUS OF HOUSING WORKS UNDER BSUP SCHEME IN FARIDABAD

*As on 30.09.2009

(All Amount in Rs. Lacs)

Pkg. No. / Brief Description of Work / Award Value / Date of / Status of Work
Start / Comp
Housing Work at Bapu Nagar
I & II / Const. of 1280 DU’s including all Internal & External Works / 2376.00 / 01.07.07 / 31.10.09
GF / 1st / 2nd / 3rd / Roof / Total
Casting of RCC Floors for DU’s / 232
100% / 232
100% / 232
100% / 232
100% / 928
Brick work for DU’s / 232 / 232 / 232 / 232 / 928
Flooring for DU’s / 212 / 232 / 232 / 232 / 928
Door Window Fixing for DU’s / 232 / 232 / 232 / 232 / 928
·  716 DU’s are ready for Handing over.
·  External Grit Wash for all the blocks completed.
·  Boundary Wall 300 meters completed.
·  RCC Wall and Slab of Water Tank completed. Pumping station Completed and in operation.
·  Sub-station completed, Transformers & Panels are completed.
·  D Pole Structure Fixed.
·  Sewer Connection for all DU’s Connected.
Physical Progress 96%

STATUS OF REVAMPING OF SEWERAGE SYSTEM AT OLD FARIDABAD

As on 30.09.2009

(All Amount in Rs. Lacs)

Pkg. No. / Brief Description of Work / Award Value / Date of / Status of Work
Start / Comp
I & III / Laying/Revamping of Sewerage Network for IPS – I & II at Old Faridabad / 1880.00 / 01.07.07 / 31.12.09 / ·  The total Qty to be executed is 41831 meters.
·  The R.C.C. hume pipe class NP2 / NP3 31325 meter length have been procured at site as on 31.08.2009 i.e. 75%.
·  Total Sewerage Pipe line has been laid upto 31.08.09 is 29410 meters i.e. 74% of the total work.
·  The work is being executed in Sector-19 and connections are being made.
Physical Progress 83%
V / Laying/Revamping of Sewerage System for IPS – III & IV at Old Faridabad / 1175.00 / 25.10.07 / 31.12.09 / ·  The Total Qty to be executed is 16846 meters.
·  14520 meters length of Sewerage Pipe has been procured i.e. 86%.
·  13960 meters length of Sewerage Pipe has been laid i.e. 83%.
·  The work is being executed in Sector – 14 (along By Pass Road) & Sector – 19, (Old Faridabad).
·  The work is being executed in PS- 3 area Old Faridabad and Escort road Connection of Sewer lines are been in progress.
·  Laying of Sewerage Pipe through Trenchless Technology in Sector-15 market is in progress.
Physical Progress 83%

STATUS OF REVAMPING OF SEWERAGE SYSTEM AT OLD FARIDABAD

As on 30.09.2009

(All Amount in Rs. Lacs)

Pkg. No. / Brief Description of Work / Award Value / Date of / Status of Work
Start / Completion
II & IV / Civil, Electrical and Mechanical work of IPS – I & II and its Rising Mains at Old Faridabad / 1468.00 / 17.08.07 / 31.03.09 / Pumping Station No. 1
·  Commissioned.
·  Approx 100 m length of 800dia DI pipe rising main balance.
·  Permission from UP Irrigation to cross Agra Canal has been obtained.
Physical progress 96%
Pumping Station No. 2
·  Completed and Commissioned Inaugurated by Hon’ble CM on 21.02.09
·  Approx 300 m length of 800 mm dia DI rising main balance across Agra Canal.

(All Amount in Rs. Lacs)

Pkg. No. / Brief Description of Work / Award Value / Date of / Status of Work
Start / Completion
VI & VII / Civil, Electrical and Mechanical work of IPS – III & IV and its Rising Mains at Old Faridabad / 1193.00 / 25.10.07 / 31.10.09 / Pumping Station No. 3
·  Chamber at Inlet balance.
·  Sewer pipe connection in progress.
Pumping Station No. 4
·  Under Trial run & Testing.
VIII / Civil, Electrical and Mechanical Works for Sewerage Treatment Plants / 2899.00 / 17.01.08 / 16.01.10 / Civil works
·  RCC-96% Completed
·  Brick works-95% Completed.
·  Cement Plaster-90% Complete
·  Finishing items:- 30% completed.
E& M Items.
·  Equipments like Decanters, Diffusers,DG set Centrifuge, Air blower, Mechanical screen and Panel Board are delivered at Site.
·  Erection in Progress.
Physical Progress 82%

STATUS OF LAYING OF STORM WATER DRAINAGE SYSTEM IN OLD FARIDABAD

As on 30.09.2009

(All Amount in Rs. Lacs)

Pkg. No. / Brief Description of Work / Award Value / Date of / Status of Work
Start / Comp
I & II / Laying of Storm Water Drainage System in Old Faridabad / 2807.00 / 17.08.07 / 31.12.09 / Package – I
•  The total Qty to be executed is 25330 meters.
•  Total Laying of Storm Water Drainage Length executed upto 31.08.2009 is 14600 meters i.e. 52% of the total work.
•  The work is being executed in Sector – 28 & 37
Package – II
•  The total Qty to be executed is 21410 meters.
•  Total Laying of Storm Water Drainage Length executed upto 31.08.2009 is 6970 meters i.e. 32% of the total work.
•  The work is being executed in Sector – 34.
Package- III : NIT area
·  Drain from Punchkuia road & Dharamshala in progress 1.8 Km completed out of total 2.3 Km.
Package- IV : Ballabhgarh area
·  Drain on dividing road of sector 6 & 8 is completed.
Physical Progress 49%

STATUS OF INTEGRATED SOLID WASTE MANAGEMENT SCHEME FARIDABAD

As on 30.09.2009

(All Amount in Rs. Lacs)

Pkg. No. / Brief Description of Work / Award Value / Date of / Status of Work
Start / Comp
I / Integrated Solid Waste Management Scheme in Faridabad / 25.75 / 10.03.08 / 31.03.10 / ·  Contract for Construction of Integrated MSW Treatment & Processing Plant has been awarded in March 2008 for a total value of Rs 25.75 Crores.
·  Concession Agreement for O &M for 30 Years has also been signed by MCF with the same agency.
·  Survey works in progress at new site Bhandwari.
·  The following Materials has been received.
a)  Bins of 240 liter – 180 nos.
b)  Mobile Bin of 1100 liter Capacity – 190 nos.
c)  Wheel Barrows of 140 liter capacity – 574 nos.
d)  4.5 cum capacity M.S. container - 68 nos.
e)  3000 liter capacity Sewer jetting machine - 3 nos.
f)  Animal catcher van – 3 no.
g)  Trickle Rickshaw - 150 nos.
h)  60 liter capacity litter Bins – 200 nos.
i)  JCB – 7 nos.
j)  S nos.
k)  Refuse collector – 10 nos
l)  Dumper placer – 10 nos
m) Tipper truck – 5 nos
·  Brick Work of Boundary wall 650 meter completed.
·  Brick Work for Boundary wall 250 meter in progress.
6. Augmentation of WATER SUPPLY SYSTEM AT FARIDABAD
Pkg. No. / Brief Description of Work / Award Value (Rs, in Lacs) / Date of / Status of Work
Start / Comp
1
2
3
4
5
6
7
9
10
11 / Commissioning of DI Pipe line from 53 Tube wells to UGSR of different sizes including Electrical & Mechanical works
Constuction, Erection, Testing and commissioning of 53 Tube wells along Gurgaon & Agra canal in clusters as per scheme
Construction, Erection, Testing and commissioning of 3 Nos Radial Collector well & Laying of DI Pipe line up to UGT
Const of 3 nos. Radial Collector Well & Laying of DI Pipe line up to UGT
Const of 4 nos. Radial Collector Well & Laying of DI Pipe line up to UGT
Designing, manufacturing, Laying, Testing & Commissioning of PSC Pipe line 900 mm i/d along with truss bridge & fittings etc complete (line-1)
Designing,manufacturing,laying, Testing & Commissioning of PSC pipe line 900 mm (Line-2)
Providing & Laying of PSC pipe Line 900 & 800 mm I/D along with Truss bridge & fittings (40km) at Fbd.
HT Electrical Independent feeder for MBS/Ranney’s/UGT/TUBEWELLS at Yamuna Flood
Construction of RCC UGT & OHSR at Faridabad Including Elect. Mech. Works of Different capacity and installation of 138 tubewells & Rain water harvesting work / 536.92
573.56
1899.86
1872.37
2391.80
1542.68
1590.41
2717.04
1870.88
11916.54 / 01.06.09
01.06.09
03.07.09
03.07.09
03.07.09
03.07.09
03.07.09
01.10.09
01.10.09
01.10.09 / 31.12.09
31.12.09
31.12.10
31.12.10
31.12.10
31.12.10
31.12.10
31.03.11
31.03.11
31.03.11 / 1.  Under ground Water Tank at
For laying Di pipe 3.80 Km laid. Work is held up on account of permission from HUDA, U.P. & Haryana Irrigation, NHAI, Railways & Forest is required.
(a) Bhudena – RCC UGT comp.
(b)  Subhash Colony- Roofs started
(c) Sector 19 – RCC UGT Completed.
(d)  Dayal Bagh – IIIrd lift of wall completed.
(e)  Sector- 7 & Mirzapur- Excavation completed & PCC started.
Only 48 tubewells could be completed. For balance 20 tubewells, permission from HUDA & Haryana Irrigation deptt. Is required.
Progress is 38%.
Inspection of Pumps completed and material will be received on 03.10.09
Work is could not started due to none acquisition of Land from Panchayat
-do-
-do-
Design of PSC pipe submitted to IIT Delhi for vetting and approval of design is received from IIT. PSC pipe 900mm -1160 meter manufactured at Factory Rajasthan laying on Ground will be started w.e.f 10.10.09
-do-
Letter of Award has been issued to the construction Agency and their contractual date of start is on 01.10.09 Work is at Mobilization stage.
-do-
-do-
Pkg. No. / Brief Description of Work / Award Value(Rs, in Lacs) / Date of / Status of Work
Start / Comp
8
9
10 / Procurement of DI Pipes against Rate Contract No. 10/HR/RC/E-2/2008-09/23649-650 Date 01.04.09 with D, S &D Haryana.
Agency:- M/s Electrosteel Casting Ltd.
Procurement of DI Pipes against Rate Contract No. 10/HR/RC/E-2/2008-09/23649-650 Date 01.04.09 with D,S &D Haryana.
Agency:- M/s Jindal Saw Ltd.
Procurement of DI Pipes against Rate Contract No. 10/HR/RC/E-2/2008-09/23649-650 Date 01.04.09 with D,S &D Haryana.
Agnecy:- M/s Electrotherm (India) Ltd. / 1298.00
616.30
122.22 / 01.06.09
01.06.09
01.06.09 / 15.10.09
15.10.09
15.10.09 / 100% Work Completed.
100% Work Completed.
Material received at Site.
TOTAL / 2036.52

HOUSING WORK IN PROGRESS AT DABUA COLONY & BAPU NAGAR

DRAINAGE WORK IN PROGRESS AT OLD FARIDABAD

PUMPING STATION WORK IN PROGRESS AT OLD FARIDABAD

STP WORK IN PROGRESS AT BADSHAHPUR, FARIDABAD

MPS

DRAINAGE WORK IN PROGRESS AT OLD FARIDABAD