17406 version 3
Page 1 of 3
Operate auxiliary steam systems in a thermal electricity generation power station
Level / 4Credits / 2
PurposePeople credited with this standard are able to: demonstrate knowledge of auxiliary steam systems and controls; operate and monitor station auxiliary steam systems; and identify and respond to deviations.
Subfield / Electricity SupplyDomain / Electricity Supply – Thermal Operations and Control
Status / Registered
Status date / 29 August 2000
Date version published / 25 June 2007
Planned review date / 31 December 2008
Entry information / Open.
Accreditation / Evaluation of documentation and visit by NZQA and industry.
Standard setting body (SSB) / Electricity Supply Industry Training Organisation
Accreditation and Moderation Action Plan (AMAP) reference / 0120
This AMAP can be accessed at
Special notes
1This unit standard is intended for, but not restricted to, workplace assessment. The range statements within the unit standard can be applied according to industry specific equipment, procedures and processes.
2Safety of personnel and plant must be a priority throughout the assessment. If the safety requirements are not met the assessment must stop and the candidate will be assessed as not yet competent.
3Performance and work practices in relation to the elements and performance criteria must comply with all current legislation, especially the Electricity Act 1992, and any regulations and codes of practice recognised under that statute; the Health and Safety in Employment Act 1992; and the Resource Management Act 1991. Electricity supply industry codes of practice and documented industry procedures include the Safety Manual – Electricity Industry (SM-EI) (2004) Wellington: Electricity Engineers’ Association. A full list of current legislation and industry codes is available from the Electricity Supply Industry Training Organisation, PO Box 1245, Hamilton.
4‘Industry requirements’ include all the documented workplace policies, procedures, specifications, business and quality management requirements relevant to the workplace in which assessment is carried out.
5This unit standard excludes the auxiliary boiler.
6The term ‘operate’ is defined as manual operation and testing of thermal electricity generation plant including plant adjustments, isolations and restorations.
Elements and performance criteria
Element 1
Demonstrate knowledge of auxiliary steam systems and controls.
Performance criteria
1.1Auxiliary steam system, location and operation are described in accordance with industry requirements.
Rangeincludes but is not limited to – main system, supplies to the main, equipment supplied from the main, layout and drainage, pressure, temperature, flow.
1.2Auxiliary steam controls are described in accordance with industry requirements.
1.3Operating parameters are identified in accordance with industry requirements.
1.4Steam pipe work drainage philosophy is explained, and drainage mechanisms described, in accordance with industry requirements.
Rangeincludes but is not limited to – water hammer, traps, pressurising.
Element 2
Operate and monitor station auxiliary steam systems.
Performance criteria
2.1Current status of system is identified in accordance with industry requirements.
2.2Operations are carried out in accordance with industry requirements.
Rangeincludes but is not limited to – isolations and restorations, routine testing, supplying steam to auxiliaries, warming through pipe work, pressurising pipe work, drainage operations.
2.3Operating and monitoring actions are logged in accordance with industry requirements.
2.4Operating decisions are determined in accordance with plant status and industry requirements.
Rangeincludes but is not limited to – plant availability and service condition, resource consent and loading limits, impact on operations, options.
2.5Plant and equipment are monitored in accordance with industry requirements.
Element 3
Identify and respond to deviations in the normal operation of auxiliary steam systems.
Performance criteria
3.1Deviations from normal operating conditions are identified, logged and acted upon in accordance with industry requirements.
Rangeincludes but is not limited to – leaks, passing, safety valve feathering.
3.2Plant safety, fire and emergency procedures are followed in accordance with industry requirements.
Please note
Providers must be accredited by NZQA, or an inter-institutional body with delegated authority for quality assurance, before they can report credits from assessment against unit standards or deliver courses of study leading to that assessment.
Industry Training Organisations must be accredited by NZQA before they can register credits from assessment against unit standards.
Accredited providers and Industry Training Organisations assessing against unit standards must engage with the moderation system that applies to those standards.
Accreditation requirements and an outline of the moderation system that applies to this standard are outlined in the Accreditation and Moderation Action Plan (AMAP). The AMAP also includes useful information about special requirements for organisations wishing to develop education and training programmes, such as minimum qualifications for tutors and assessors, and special resource requirements.
Comments on this unit standard
Please contact the Electricity Supply Industry Training Organisation you wish to suggest changes to the content of this unit standard.
New Zealand Qualifications Authority 2018